9 slides from Barrick Mining's earnings presentation, May 6, 2008

  1. Slide 1: First Quarter Results Conference Call

    BARRICK GOLD CORPORATION First Quarter Results Conference Call May 6, 2008 Strategy Investment Execution Results First Quarter Results – May 6, 2008 First Quarter Results Peter Munk Gregory Wilkins Peter Kinver Alex Davidson Jamie Sokalsky Patrick Garver 1

  2. Slide 2: Cautionary Statement on Forward-Looking Information

    BARRICK GOLD CORPORATION First Quarter Results Conference Call May 6, 2008 CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION Certain information contained or incorporated by reference in this presentation and related material, including any information as to our strategy, plans or future financial

  3. Slide 3: Operating and Financial Results

    BARRICK GOLD CORPORATION First Quarter Results Conference Call May 6, 2008 Operating and Financial Results ƒ Gold production of 1.74 Moz at $393/oz (1) ƒ Copper production of 87 Mlbs at $0.94/lb (1) ƒ Net income of $514 M ($0.59/share) – 29% increase from Q1’07 adjusted net income (2) ƒ Record earni

  4. Slide 4: Margin Expansion and Dividend Increase

    BARRICK GOLD CORPORATION First Quarter Results Conference Call May 6, 2008 Margin Expansion 925 Average Total Cash Costs vs Gold Prices (1) Realized Price US dollars per ounce 532 Margin 619 541 274 439 392 262 366 339 393 Total 180 214 345 Cash Cost 162 179 279 212 225 177 187 02 03 04 05 06 07 Q1

  5. Slide 5: Q1 2008 Production and Buzwagi Project Update

    BARRICK GOLD CORPORATION First Quarter Results Conference Call May 6, 2008 Q1 2008 Production ounces thousands North America Africa 614 144 541 435 South Australia America Pacific 9 Other Buzwagi Project Update ƒ On schedule and budget ƒ Capex: $400 M (1) – 75% committed or spent ƒ +10 year mine lif

  6. Slide 6: Cortez Hills and Pueblo Viejo Project Updates

    BARRICK GOLD CORPORATION First Quarter Results Conference Call May 6, 2008 Cortez Hills Project Update ƒ On schedule and budget ƒ Capex: $480-500 M(1) – 50% committed or spent ƒ +10 year mine life ƒ 1 Moz/yr(2,4) producer ƒ Cash costs $280-290/oz (2,3,4) ƒ Record of Decision expected in H2 2008 (1)

  7. Slide 7: Nevada – A Key Focus; Pueblo Viejo 2008 Targets

    BARRICK GOLD CORPORATION First Quarter Results Conference Call May 6, 2008 Nevada – A Key Focus Turquoise Ridge Goldstrike Elko Carlin Marigold Battle Mtn. Cortez N E V A D A Bald Mtn. Ruby Hill Round Mountain Pueblo Viejo – 2008 Targets Cumba N Arroyo Hondo Monte Oculto Monte Negro Moore Planta 7

  8. Slide 8: PNG – Kainantu and Tabar JV; Zaldivar Deep Sulfide Potential

    BARRICK GOLD CORPORATION First Quarter Results Conference Call May 6, 2008 PNG – Kainantu and Tabar JV Simberi Lihir BARRICK INDONESIA Tabar JV BARRICK Ok Tedi Porgera BARRICK Kainantu Wamun Current & Past Producer Development & Exploration 0 miles 100 200 Tolukuma Port Moresby INDIAN OCEAN PACIFIC

  9. Slide 9: In Closing

    BARRICK GOLD CORPORATION First Quarter Results Conference Call May 6, 2008 In Closing ƒ Positive gold price outlook ƒ Maintaining 2008 operating guidance ƒ Delivering strong financial results ƒ Increased dividend by 33% ƒ Advancing project pipeline ƒ Strong leverage to the gold price – benefiting fr