Orsted · OMXCOP:ORSTED
Orsted — Ørsted — Corporate Update (April 2026)
15 slides from Orsted's corporate update, April 2026
Slide 1: HOW03 Progress Report: Onshore Converter Station
HOW03 Progress Report Onshore Converter Station April 2026
Slide 2: Onshore Converter Station
Onshore Converter Station This progress report presents an overview of the main activities undertaken to date and upcoming works as part of the installation of the Onshore Converter Station (OnCS) for the Hornsea 3 Offshore Wind Farm (‘the Project’). This is a series of progress reports which will b
Slide 3: Conceptual Design
Conceptual Design A47 BESS A Link 1 Link 2 B1113 BESS B Conceptual design of the Hornsea 3 OnCS and Battery Energy Storage System 3
Slide 4: Site Entrance and Overview
Site Entrance and Overview Overview Access to the OnCS site is via a newly built asphalt bell mouth (site entrance) adjacent to the B1113. Temporary security huts and gate guards have been installed. This bell mouth is connected to all work areas, including the offices and welfare facilities, via a
Slide 5: Welfare Facilities and Car Park
Welfare Facilities and Car Park Overview The OnCS welfare facilities and car park are temporary structures installed in June 2024. These structures are substantial to provide adequate facilities for the site staff and workers who will be involved in the installation of the Project. These facilities
Slide 6: Link 1
Overview Link 1 Link 1 (valve hall) is the point where the onshore cable from the wind farm connects into the OnCS and then goes to National Grid. As part of our reinforced concrete (RC) works on link 1, we have completed the alternating current (AC) yard and six pits for the 400 kilovolt (kV) alter
Slide 7: Link 2
Overview Link 2 Link 2 (valve hall) is the point where the onshore cable from the wind farm connects into the OnCS and then continues to the National Grid. All civils / construction works are complete for all buildings, access roads, drainage, and earthing. Some fencing additions are ongoing. Metal
Slide 8: Transformer movements
Transformer movements • Our transformer installation activities involve the transportation of abnormal loads, meaning they are either larger, heavier or wider than what can be transported on a standard vehicle. These will be passing through or in proximity to your local area, starting in the Port of
Slide 9: What is a transformer?
What is a transformer? A transformer in a UK converter station is a key piece of electrical equipment that changes the voltage of alternating current (AC) electricity so it can be transmitted safely and efficiently from the OnCS into the National Grid, and then on to homes and businesses. Transforme
Slide 10: Engagement - OnCS
Engagement - OnCS Community engagement Neighbouring Parish Councils include Newton Flotman, Caistor St Edmund, Stoke Holy Cross and Dunston. These Parish Councils have shown interest in or have reached out to the Community Relations Team to discuss the OnCS, and to learn more about the project in ge
Slide 11: Have you signed up to the Hornsea Three Community newsletter?
Have you signed up to the Hornsea Three Community newsletter? The Hornsea 3 Offshore Wind Farm is a major infrastructure project of national importance. With a generating capacity of 2.9 GW, Hornsea 3 will produce enough green energy to power more than 3 million UK homes. We know that as with any la
Slide 12: How to get in touch
How to get in touch Project enquiries Community Liaison Officer Telephone: 0800 158 2354 Email: [email protected] Community Relations Team We aim to provide a full response to all enquiries within 10 working days. 12
Slide 13: Glossary
Glossary Links 1 and 2 The electricity generated by the offshore wind turbines is Alternating Current (AC), which when transmitted, loses more power than Direct Current (DC). To avoid this loss the AC is converted into DC to be transmitted along the length of the cable. At the OnCS, the Links will t
Slide 14: Glossary
Glossary Bell mouths To access land plots for our works, new gated construction traffic access points (bell mouths) need to be installed at highway entrance/exit points. The bell mouths provide access to the work area for plant, machinery, materials and anything else required to ensure the project i
Slide 15: Let's create a world that runs entirely on green energy
Let’s create a world that runs entirely on green energy