Admiralty Resources NL · ASX:ADY
Admiralty Resources NL — 5th America's Iron Ore Conference 2012
36 slides from Admiralty Resources NL's conference presentation, Nov 6, 2012
Slide 1: Presentation at the 5th America's Iron Ore Conference
ASX Announcement 6 November 2012 For personal use only Presentation at the 5th America’s Iron Ore Conference (6-8 November 2012, Belo Horizonte, Brazil) I enclose herewith the presentation to be provided by Stephen Prior, Managing Director of Admiralty Resources NL, at the 5th America’s Iron Ore Con
Slide 2: High Quality Iron Ore Production from Chilean Magnetite
High Quality lron Ore Production from Chilean Magnetite By Stephen C. Prior Managing Director AMERICAS wae TRON ORE ericas Iron Ore Conference
Slide 3: Forward Looking Statements
Slide - 2 - Forward Looking Statements For personal use only The information in this presentation is published to provide information about Admiralty Resources NL (“Admiralty” or “ADY”) and its subsidiaries. All reasonable effort has been made to provide accurate information, but Admiralty makes no
Slide 4: Agenda
Slide - 3 - For personal use only Agenda 1 2 3 4 Admiralty’s Exploration Case Resource Summary of approach to Study: La Exploitation Admiralty’s exploration Chulula Projects
Slide 5: Summary of Exploration Workflow
Slide - 4 - Summary of Exploration Workflow For personal use only Low Impact Ground Disturbing Exploration Exploration Rock chip, soil sampling and surface geological Airborne magnetic Trenching mapping survey Geological & Low-Resolution geochemical sampling ground magnetic Drilling survey Resource
Slide 6: Case Study: La Chulula Ore Body
Exploration and Mineral Deposit Slide - 5 - Evaluation For personal use only Case Study: La Chulula Ore Body (Harper South, Vallenar, Chile) Location map of the La Chulula target. Image obtained from Google Earth ©2012
Slide 7: Airborne Survey (1999)
Slide - 6 - Airborne Survey (1999) For personal use only HARPER NORTH The area has been extensively survey since 1960 Surveys have been carried out by mining companies operating in the area (CMP, Barrick, BHP and others) and the United Nations In 2005, all available survey data was reviewed an
Slide 8: Ground Magnetic Survey (2005-2007)
Slide - 7 - Ground Magnetic Survey (2005-2007) For personal use only Above: Magnetic field reduced to pole. La Chulula area.
Slide 9: Gravimetry (2010)
Slide - 8 - Gravimetry (2010) For personal use only Left: Geological map of the La Chulula area. Right: Gravimetry image.
Slide 10: Low-Resolution Ground Magnetic Survey (2010)
Slide - 9 - Low-Resolution Ground Magnetic Survey (2010) For personal use only An integration of different ground magnetic surveys performed in 2005 and 2007 was performed A new survey was carried out in March/April 2010, covering a total of 330,623m Readings were taken at 100m intervals, from
Slide 11: High Resolution Ground Magnetic Survey (2011)
Slide - 10 - Phase 1 -High Resolution Ground Magnetic Survey (2011) For personal use only Survey factsheet 37 lines of 1,100m length (Mariposa & La Chulula), Spaced at 50m apart Covering an area of 2 km2 Performed in August 2011 by Quantec Geoscience Ltd. Depth slices of magnetic susceptibil
Slide 12: High Resolution Ground Magnetic Survey (2011)
Slide - 11 - Phase 1 - High Resolution Ground Magnetic Survey (2011) For personal use only 3D inversion & interpretation of the high- resolution ground magnetic survey
Slide 13: High Resolution Ground Magnetic Survey (2011)
Slide - 12 - Phase 2 -High Resolution Ground Magnetic Survey (2011) For personal use only Survey factsheet 25 lines of 750m length Spaced at 50m apart Covering an area of 0.8 km2 Performed in February/March 2012by Quantec Geoscience Ltd. Comparison of maps of magnetic susceptibility for Phas
Slide 14: High Resolution Ground Magnetic Survey (2012)
Slide - 13 - Phase 2 -High Resolution Ground Magnetic Survey (2012) For personal use only Survey Results Magnetic susceptibility levels higher than 0.9 S.I. units between 600m and 0m elevations Fully confined within the boundaries of Admiralty’s property Located near the surface Lateral dime
Slide 15: High Resolution Ground Magnetic Survey (Continued)
Slide - 14 - High Resolution Ground Magnetic Survey (Continued) For personal use only Depth slices of magnetic susceptibility at different elevations
Slide 16: Drilling
Slide - 15 - Drilling For personal use only PRE-DRILLING WORK: Complete geological appraisal of the ore potential to sink drill holes in the areas of maximum opportunity for ore discovery STRATEGY: Provide reliable information while minimising cost and maximising results discovery in the ore body st
Slide 17: La Chulula Diamond Drilling test hole
Slide - 16 - La Chulula Diamond Drilling (DD) test hole For personal use only Factsheet Date of execution: 5-18 February 2012 Number of holes: 1 x 600m Inclination of drill hole: 50 degrees Results Confirmation of mineralisation depth Confirmation of mineralisation volume: 450m out of 600m
Slide 18: La Chulula RC drilling programme – Phase 1
Slide - 17 - La Chulula RC drilling programme – Phase 1 For personal use only Factsheet Date of execution: 6 June – 10 July 2012 Number of metres drilled: 2,748m Number of holes: 10 holes of 200-350m each Inclination of drill hole: 50-60 degrees Results Confirmation of mineralisation exten
Slide 19: La Chulula RC drilling programme – Phase 2
Slide - 18 - La Chulula RC drilling programme – Phase 2 For personal use only Factsheet Date of execution: 4 September – 19 October 2012 Number of metres drilled: 3,135m Number of holes: 17 holes of 150-315m each Inclination of drill hole: 50-60 degrees Results Confirmation of mineralisati
Slide 20: At the field at La Chulula
For personal use only At the field at La Chulula
Slide 21: Resource Exploitation
For personal use only Resource Exploitation
Slide 22: Magnetite Iron Production Workflow
Slide - 21 - Magnetite Iron Production Workflow For personal use only MAGNETIC MINE TRANSPORT SCREENING FILTERING/ DRYING CRUSHING SEPARATION EXTRACTION TO PLANT GRINDING (high speed drums) (wet or dry) *It takes about 1.5 tonnes of iron and 0.5 tonne of coke to produce a tonne of pig iron, the raw
Slide 23: Conceptual Crushing Plant
Slide - 22 - Conceptual Crushing Plant For personal use only Above: Jaw Crusher. Below: Cone Crusher. Source: Project & Maintenance Engineering S.A. (PME), Chile
Slide 24: Conceptual Crushing Plant Design (Continued)
For personal use only Source: Project & Maintenance Engineering S.A. (PME), Chile Conceptual Crushing Plant Design (Continued) Slide - 23 -
Slide 25: Conceptual Beneficiation Plant Design
Slide - 24 - Conceptual For personal use only Beneficiation Plant Design Source: Project & Maintenance Engineering S.A. (PME), Chile
Slide 26: Final Product: Lump and Fines
Slide - 25 - Final Product: Lump and Fines For personal use only Production from the real live test performed on Soberana ROM (July 2012).
Slide 27: Final Product Composition
Slide - 26 - Final For personal use only Product Composition Extract from Certificate of Analysis issued by Alex Stewart International on the 44,592,413 WTM iron ore fines shipped by MV ZHI QIANG on 22 October 2008.
Slide 28: Admiralty's Projects Summary
For personal use only Admiralty’s Projects Summary
Slide 29: Projects Location
Slide - 28 - 6,800 Ha in the Chilean iron belt with internal roads network and no high mountain formations Projects Location 46km from the Guacolda and Las Losas ports For personal use only 7km from the railway line owned by Ferronor S.A. and 3km from the Pan American highway, with direct acce
Slide 30: Projects Location
Slide - 29 - Projects Location For personal use only Distance from Vallenar by road Las Losas Port 49 km Guacolda Port 49 km Castilla Port 135 km Punta Caleta Port 265 km Punta Totoralillo Port 280 km Image obtained from Google Earth ©2012. Map is not to scale.
Slide 31: Project – Harper South District
Slide - 30 - PROJECT 1 – Harper South District For personal use only 7 targets confirmed and 2 anomalies identified by high resolution ground magnetic survey 2 sorts of mineralisation found in the district: magnetite style in the east and IOCG (iron oxide, copper & gold) in the west with zones s
Slide 32: Project – Pampa Tololo District
Slide - 31 - PROJECT 2 – Pampa Tololo District For personal use only 3 targets confirmed by high resolution ground magnetic survey Simpson – UNDER EXPLORATION This is the most important target in relation to size/susceptibility. An oblate spheroid shape of 800m in diameter, located at a depth of
Slide 33: Project – Cojin District
Slide - 32 - PROJECT 3 – Cojin District For personal use only Three exploitation concessions, covering 647 hectares, 10% of Admiralty’s mineral tenure Located 8-15 km from El Algarrobo, iron ore mine owned by CMP1 El Algarrobo supplies preconcentrates to CMP’s iron pellet plant in Huasco and 6
Slide 34: Appendix
For personal use only Appendix
Slide 35: Corporate Directory
Slide - 34 - Corporate Directory For personal use only BOARD OF DIRECTORS CONTACT Professor J. Ross Harper, Chairman Level 16, 379 Collins Street, Stephen C. Prior, Managing Director Melbourne VIC 3000, Australia Michael S. Perry, Non-executive Director Dr Shaoqing Li, Non-executive Director Tel: +6
Slide 36: Thank you for your attention
For personal use only Thank you for your attention. I would be pleased to address any questions from the floor.
Admiralty Resources NL — 5th America's Iron Ore Conference 2012 on 6ix