Citigold Corporation Limited · ASX:CTO

Citigold — Shareholder Meeting (November 2005)

26 slides from Citigold's shareholder meeting presentation, November 2005

  1. Slide 1: Warrior Gold Mine

    Citigold AGM November 2005 WARRIOR GOLD MINE Garry Foord General Manager – Engineering

  2. Slide 2: Decline Development

    DECLINE DEVELOPMENT Washington Pit Warrior Warrior West 1000 m Annual General Meeting 2005 Garry Foord 2

  3. Slide 3: Decline Development

    DECLINE DEVELOPMENT Annual General Meeting 2005 Garry Foord 3

  4. Slide 4: Decline Development: Planned decline

    DECLINE DEVELOPMENT Planned decline Annual General Meeting 2005 Garry Foord 4

  5. Slide 5: Decline Development: 366m from portal, 594m to ore

    DECLINE DEVELOPMENT portal 366m from portal 594m to ore Annual General Meeting 2005 Garry Foord 5

  6. Slide 6: Decline Development

    DECLINE DEVELOPMENT Annual General Meeting 2005 Garry Foord 6

  7. Slide 7: Decline Development

    DECLINE DEVELOPMENT Annual General Meeting 2005 Garry Foord 8

  8. Slide 8: Decline Development: progressing in good solid ground

    DECLINE DEVELOPMENT Progressing in good solid ground with no known problems Annual General Meeting 2005 Garry Foord 7

  9. Slide 9: Next Year

    NEXT YEAR …… ƒ Completion of decline access ƒ Install ventilation and second exit ƒ Recommission processing plant ƒ Gold Production Annual General Meeting 2005 Garry Foord 9

  10. Slide 10: Warrior Ore Production

    WARRIOR ORE PRODUCTION 200,000 tonnes 40,000ozs Annual General Meeting 2005 Garry Foord 10

  11. Slide 11: Production Stoping Sequence

    PRODUCTION STOPING SEQUENCE Two levels 10m apart Annual General Meeting 2005 Garry Foord 11

  12. Slide 12: Production Stoping Sequence

    PRODUCTION STOPING SEQUENCE Initial (Leading) stope ore from bottom level Annual General Meeting 2005 Garry Foord 12

  13. Slide 13: Production Stoping Sequence

    PRODUCTION STOPING SEQUENCE Long holes drilled from top level Annual General Meeting 2005 Garry Foord 13

  14. Slide 14: Production Stoping Sequence

    PRODUCTION STOPING SEQUENCE Broken ore collected on bottom level Annual General Meeting 2005 Garry Foord 14

  15. Slide 15: Initial Production Sequence: Plan View

    INITIAL PRODUCTION SEQUENCE Resource outline 40,000 ozs Decline from surface PLAN VIEW Annual General Meeting 2005 Garry Foord 15

  16. Slide 16: Initial Production Sequence

    INITIAL PRODUCTION SEQUENCE 850 Access First Level (850) Annual General Meeting 2005 Garry Foord 16

  17. Slide 17: Initial Production Sequence

    INITIAL PRODUCTION SEQUENCE Drive along level in ore 850 Ore stockpiled on surface Annual General Meeting 2005 Garry Foord 17

  18. Slide 18: Initial Production Sequence

    INITIAL PRODUCTION SEQUENCE Continue driving 850 level Decline down to second level Annual General Meeting 2005 Garry Foord 18

  19. Slide 19: Initial Production Sequence

    INITIAL PRODUCTION SEQUENCE Complete driving in first two levels 840 850 Ventilation shaft and access drive completed Annual General Meeting 2005 Garry Foord 19

  20. Slide 20: Initial Production Sequence

    INITIAL PRODUCTION SEQUENCE Ore from 840 Level to surface 840 850 Decline down to next level (830) Annual General Meeting 2005 Garry Foord 20

  21. Slide 21: Initial Production Sequence

    INITIAL PRODUCTION SEQUENCE Ore from second Production Level (830) begins 830 840 850 Annual General Meeting 2005 Garry Foord 21

  22. Slide 22: Initial Production Sequence

    INITIAL PRODUCTION SEQUENCE Continue mining from 2 levels Decline down to (3300ozs per month) another level (820) Annual General Meeting 2005 Garry Foord 22

  23. Slide 23: Initial Production Sequence

    INITIAL PRODUCTION SEQUENCE New level developed First internal curve go back in west direction Annual General Meeting 2005 Garry Foord 23

  24. Slide 24: Production Planning

    PRODUCTION PLANNING Annual General Meeting 2005 Garry Foord 24

  25. Slide 25: Production Planning: Marginal Cost Analysis

    PRODUCTION PLANNING tonnes g/t ozs width $value (profit) Marginal Cost Analysis Annual General Meeting 2005 Garry Foord 25

  26. Slide 26: Warrior Gold Mine

    WARRIOR GOLD MINE Annual General Meeting 2005 Garry Foord 26