Metlen Energy & Metals PLC · LSE:MTLN

Metlen Energy & Metals — METKA S.A. Group of Companies — Investor Presentation (October 2026)

100 slides from Metlen Energy & Metals's investor presentation, Oct 28, 2026

  1. Slide 1: Company Presentation October 2026

    Slide 1: Company Presentation October 2026

    COMPANY PRESENTATION October 2026

  2. Slide 2: Disclaimer (1/2)

    Slide 2: Disclaimer (1/2)

    Disclaimer (1/2) This Presentation has been prepared by METKA S.A. GROUP OF COMPANIES (the “Company” and, together with its direct and indirect subsidiaries, “METKA”), an indirect wholly owned subsidiary of Metlen Energy & Metals PLC, whose ordinary shares are listed and admitted to trading on the M

  3. Slide 3: Disclaimer (2/2)

    Slide 3: Disclaimer (2/2)

    Disclaimer (2/2) Accordingly, Backlog should not be considered in isolation or as an alternative to performance measures or revenue calculated under IFRS. In addition, Backlog includes projects at an advanced stage of contracting that have not yet been signed, is subject to unexpected adjustments an

  4. Slide 4: Agenda

    Slide 4: Agenda

    AGENDA 1 Introduction P.5 2 Business Deep Dive P.13 3 Investment Proposition & Strategy P.21 4 Financial Performance & Guidance P.32 5 Appendix P.46 Company Presentation October 2026 4

  5. Slide 5: Introduction

    Slide 5: Introduction

    1 Introduction Company Presentation October 2026 5

  6. Slide 6: METKA Group: An Integrated Infrastructure Platform

    Slide 6: METKA Group: An Integrated Infrastructure Platform

    METKA Group: An Integrated Infrastructure Platform Built on Technical Expertise, Operational Excellence and Financial Strength A PPP-based infrastructure platform strongly positioned for growth Strong €2.1Bn VOAK Concession 1 of 4 Portfolio of 24% stake in the Market Large Infrastructure Constructio

  7. Slide 7: METKA's Evolution into a Reference Infrastructure Player

    Slide 7: METKA's Evolution into a Reference Infrastructure Player

    METKA’s Evolution into a Reference Infrastructure Player A consistent infrastructure focus since 2022, strengthened through execution, bidding and complementary capabilities in the past 4 years Established Dedicated Established references, credentials 1 technical 2 infrastructure focus 3 and experie

  8. Slide 8: Proven Credentials and Complementary Capabilities Across Critical Infrastructure Sectors

    Slide 8: Proven Credentials and Complementary Capabilities Across Critical Infrastructure Sectors

    Proven Credentials and Complementary Capabilities Across Critical Infrastructure Sectors METKA has participated in the execution of a number of landmark infrastructure and PPP projects Transportation Railways Social Infra Environmental Real Estate Roads, motorways, tunnels Infrastructure, telecoms a

  9. Slide 9: METKA Group at a Glance

    Slide 9: METKA Group at a Glance

    METKA Group at a Glance Integrated infrastructure platform based on three complementary businesses across the infrastructure lifecycle Construction PPP | Concessions Facility Management Core construction business delivering complex Infrastructure investment platform focused on Established facility m

  10. Slide 10: A Distinct Infrastructure Platform Built on METLEN's Core DNA

    Slide 10: A Distinct Infrastructure Platform Built on METLEN's Core DNA

    A Distinct Infrastructure Platform Built on METLEN’s Core DNA Shared operating principles, applied through dedicated infrastructure expertise and disciplined investment Built on METLEN’s METKA is METLEN’s dedicated Infrastructure arm in Greece and Southeast Europe Industrial Heritage METLEN Core DNA

  11. Slide 11: METKA in a Nutshell

    Slide 11: METKA in a Nutshell

    METKA in a Nutshell: An Established Infrastructure Platform Ready for a New Phase of Transformation and Growth We have the capabilities, experience and access to deliver on the unprecedented need for infrastructure investment Where We Are Today The Opportunity Where We Are Heading Medium-Term Vision

  12. Slide 12: A Highly Competitive Infrastructure Platform

    Slide 12: A Highly Competitive Infrastructure Platform

    A Highly Competitive Infrastructure Platform Well-Positioned for Future Opportunities Key pillars underpinning our competitive edge Why METKA is Well-Positioned Relevant Project Specialist Ability to participate and bid Proven Delivery Credentials and Technical Track Record independently across Refe

  13. Slide 13: Business Deep Dive

    Slide 13: Business Deep Dive

    2 Business Deep Dive Company Presentation October 2026 13

  14. Slide 14: Strong and Established Construction Arm

    Slide 14: Strong and Established Construction Arm

    Strong and Established Construction Arm Underpinned By Technical Capabilities, Profitability and Ability to Deliver Focus on Balancing Profitable Delivery and Returns, while Simultaneously Maximising Backlog Disciplined Project Selection, Cost Control Outstanding Technical Capabilities and Bidding S

  15. Slide 15: A Robust Construction Backlog Underpins Revenue Visibility

    Slide 15: A Robust Construction Backlog Underpins Revenue Visibility

    A Robust Construction Backlog Underpins Strong Revenue Visibility and a Firm Foundation for Future Growth Projects Remaining Backlog Construction Backlog (€Bn) and Backlog Coverage(2) Projects signed pre-June 2026 | >€30.0ΜΜ per project ~€833MM 4.8x 3.2x 2.7x Since Jun-26 ~€200m of the Casino VORIA

  16. Slide 16: PPP & Concession Portfolio

    Slide 16: PPP & Concession Portfolio

    PPP & Concession Portfolio: A Maturing Portfolio Advancing Steadily Toward Long-Term, Recurring Cash Flow PPP Portfolio with 26-year Average Remaining Life and Availability-Payments and Participation in VOAK Operating Today (October 2026) Nov. 2024 Jul. 2026 Nov. 2040 Epirus Street Construction Oper

  17. Slide 17: PPPs Operational Contractual Frameworks Designed to Manage Risk

    Slide 17: PPPs Operational Contractual Frameworks Designed to Manage Risk

    PPPs Operational Contractual Frameworks Designed to Manage Risk An Optimized Contractual Framework to Mitigate Uncertainties at Construction and Operation Stages Contractual framework PPP Agreement Construction agreement  The project SPV sits at the centre of the contractual framework, entering int

  18. Slide 18: Experienced Leadership Team

    Slide 18: Experienced Leadership Team

    Experienced Leadership Team with Deep Sector Expertise Across Construction, Concessions and Facility Management Group Leadership Evangelos Chrysafis Dinos Benroubi Vasilis Karagkioules Konstantinos Tsamouras Ioannis Mytilinaios Chairman of METKA CEO of METKA Group General Manager – General Manager –

  19. Slide 19: Standalone Infrastructure Platform with METLEN's Strategic Support

    Slide 19: Standalone Infrastructure Platform with METLEN's Strategic Support

    Standalone Infrastructure Platform Combining Strong Governance and Operational Autonomy with METLEN’s Strategic Support Strategic relationship with METLEN’s infrastructure investment platform for the broader region; METLEN remains majority METLEN shareholder and strategic partner Standalone manageme

  20. Slide 20: Certified Management Systems

    Slide 20: Certified Management Systems

    METKA ATE Applies Certified Management Systems, Ensuring High Operational Standards Across All of its Activities Certified Quality, Safety & Compliance Standards Quality, Health and Safety Compliance and Governance Quality Health & Safety Business Continuity Information Security ISO 9001:2015 ISO 45

  21. Slide 21: Competitive Strengths & Strategy

    Slide 21: Competitive Strengths & Strategy

    3 Competitive Strengths & Strategy Company Presentation October 2026 21

  22. Slide 22: Key Highlights

    Slide 22: Key Highlights

    Key Highlights A PPP-led infrastructure platform with proven credentials, strong firepower and significant value creation still ahead Proven Credentials Across All Major Infrastructure Verticals A Purpose-Built Platform with a Clean Starting Point and Strong Firepower Top-Tier Leadership and Deep En

  23. Slide 23: Our Synergistic Business Model Amplifies Bidding Competitiveness

    Slide 23: Our Synergistic Business Model Amplifies Bidding Competitiveness

    Our Synergistic Business Model Amplifies our Bidding Competitiveness and Project Economics… Capturing value across different pockets throughout the project lifecycle Our Complementary Segments Underpin the Attractiveness of our Infrastructure Platform Our construction capability enables stronger bid

  24. Slide 24: Creating an Attractive Cashflow Profile

    Slide 24: Creating an Attractive Cashflow Profile

    …Creating an Attractive Cashflow Profile to Power Growth and Yield Attractive Returns Unlocking stronger project flow and supporting investments across the platform A high construction driven cash conversion funds growth and supports margin expansion Long-term contracts providing multi- 3–5-year pro

  25. Slide 25: Secular Trends Underpinned by Long-Term Infrastructure Need

    Slide 25: Secular Trends Underpinned by Long-Term Infrastructure Need

    Secular Trends Underpinned by Long-Term Need for Infrastructure and Real Estate Investments Across Greece and Southeast Europe A broad opportunity set aligned with METKA’s capabilities, supported by strong macro momentum and attractive funding Greek Real Greece Mobility & Social Sustainability, Esta

  26. Slide 26: Core Platform with Secured Income and Upside Potential

    Slide 26: Core Platform with Secured Income and Upside Potential

    METKA Combines a Core Platform with Secured, Recurring Income Streams and Significant Upside Potential from Further Growth Opportunities Value mix shifting towards long-duration infrastructure investments, particularly PPPs The Future Core Platform with Secured Income Streams Significant Value Upsid

  27. Slide 27: Expanding the Greek PPP and Concession Portfolio

    Slide 27: Expanding the Greek PPP and Concession Portfolio

    We Aim at Expanding the Greek PPP and Concession Investment Portfolio Ample opportunities to grow concession and PPP portfolio across mobility, social and environmental Infrastructure Visible Near-Term PPP Project Wallet(1) Potential Future Opportunities Further Upside METKA already participating in

  28. Slide 28: Selected Southeast European Projects

    Slide 28: Selected Southeast European Projects

    We Are Reviewing Opportunities to Take Our Greek Capabilities into Selected Southeast European Projects Capitalising on the Infrastructure Growth Across Southeast Europe Regional Markets of Interest A Project-led, Partnership-led Approach c.€5Bn PPPs and Concession needs across Apply domestic capabi

  29. Slide 29: Selective High-Value Real Estate Opportunities in Greece

    Slide 29: Selective High-Value Real Estate Opportunities in Greece

    We Are Looking to Capture Selective and High-Value Real Estate Opportunities in Greece Strong market opportunity to utilize on METKA’s existing capabilities Focusing on Areas with Growing Demand and Structural Undersupply How we enter the market 1 Resorts, Hospitality & Tourism Infrastructure Build-

  30. Slide 30: Targeted Acquisitions and Partnerships

    Slide 30: Targeted Acquisitions and Partnerships

    We Will Consider Targeted Acquisitions and Partnerships to Add Capabilities that Support the Platform’s Expansion and Development Prioritise specialist expertise, critical capabilities and complementary activities where developing these would require significantly greater time and resources Consiste

  31. Slide 31: The Next Phase of METKA's Infrastructure Growth

    Slide 31: The Next Phase of METKA's Infrastructure Growth

    The Next Phase of METKA’s Infrastructure Growth Creating additional capacity to capture attractive opportunities on top of the existing strong cashflows  Provide direct exposure to METKA’s integrated infrastructure platform through a Create a Dedicated standalone listing Investment Opportunity  Hi

  32. Slide 32: Financial Performance and Guidance

    Slide 32: Financial Performance and Guidance

    4 Financial Performance and Guidance Company Presentation October 2026 32

  33. Slide 33: Basis of Preparation

    Slide 33: Basis of Preparation

    Basis of Preparation Key Considerations 1 Unless otherwise stated all financial information is presented in Euro (€) 2 Calculations of all numbers presented in this document have been conducted before rounding, and then outputs were rounded for presentation purposes 3 Financial years presented in

  34. Slide 34: A Profitable, Cash-Generative Platform

    Slide 34: A Profitable, Cash-Generative Platform

    METKA Group – A Profitable, Cash-Generative Platform with the Balance-Sheet Firepower to Fund Its Next Phase of Growth €869MM (+2.4x) €158MM (18%) €152MM (18%) €10MM Revenue EBITDA EBIT Construction Capex(1) (Growth vs 2024A) (% margin) (% margin) (LTM Jun-2026) (LTM Jun-2026) (LTM Jun-2026) (LTM Ju

  35. Slide 35: Integrated Platform Delivering Rapid, Diversified Growth

    Slide 35: Integrated Platform Delivering Rapid, Diversified Growth

    1 2 3 METKA Group – An Integrated Platform Delivering Rapid, Diversified Growth Across Construction, Concessions and Facility Management Revenue(1) (€MM) EBITDA (€MM) 869 83 158 689 72 2 81 110 7 42 3 364 7 769 57(1) 148 73 4 594 2 100 289 56 2024a 2025a LTM Jun-2026 2024a 2025a LTM Jun-2026 Constru

  36. Slide 36: Construction Performance and Margin Outlook

    Slide 36: Construction Performance and Margin Outlook

    1 Construction Performance and Margin Outlook Revenue (€MM) Key Highlights  Revenue visibility underpinned by signed backlog, with multi-year projects running into 2027–2029 and further support from advanced- stage contracts (incl. VOAK) and selective new awards 769  Above-peer average margins are

  37. Slide 37: PPPs & Concessions Fast-Scaling Platform

    Slide 37: PPPs & Concessions Fast-Scaling Platform

    2 PPPs & Concessions – A Fast-Scaling Platform Building Long- Term, Low-Demand-Risk Cash Flow Visibility and Resilience Revenue (€MM) Secured PPP Availability Payments (€MM) Cum. Investment Funded/Deployed(1) (€MM) 1,676 72 1,373 57 1,103 42 41 15 4 2024a 2025a LTM Jun-2026 31 Dec 2024 31 Dec 2025 3

  38. Slide 38: Availability-Based PPPs and a Secured Concession

    Slide 38: Availability-Based PPPs and a Secured Concession

    2 Availability-Based PPPs and a Secured Concession Extend Cashflow Visibility and Resilience A high-quality portfolio, already well advanced, securing long-term returns At 100% Project Level METKA Total Contracted Total Project Construction Operation Operation End METKA Committed Availability Asset

  39. Slide 39: Expertise in Project Financing

    Slide 39: Expertise in Project Financing

    METKA’s Expertise in Project Financing to Optimize Returns A Proven Ability to Leverage PPPs Risk Profile and Projects Quality to Secure Competitive Financing Illustrative Terms for a PPP Project Sizing rules Competitive commercial terms Strong Project Long-term Financing Capabilities Market-practic

  40. Slide 40: Facility Management: Resilient, Asset-Light Recurring Income

    Slide 40: Facility Management: Resilient, Asset-Light Recurring Income

    3 Facility Management – Resilient, Asset-Light Recurring Income Revenue (€MM) and YoY Growth (%) EBITDA (€MM) and Margin (%) n.a 10.5% 3.2% 3.8% 2.6% 81 83 73 3 2 2 2024a 2025a LTM Jun-2026 2024a 2025a LTM Jun-2026  Stable, recurring, lower-cyclicality income balancing project-based construction, w

  41. Slide 41: Capital-Light Growth and Working-Capital Management

    Slide 41: Capital-Light Growth and Working-Capital Management

    Capital-Light Growth Supported by Disciplined Investment and Working-Capital Management Total Investments (€MM) Committed Investments(1) (€MM) Key Highlights Funding PPPs & Concession Capex  Capital-light construction model – low capex intensity reflects an equipment-light, subcontracting-led 34 35

  42. Slide 42: H1 2026 Current Trading

    Slide 42: H1 2026 Current Trading

    H1 2026 Current Trading H1 2026 Current Trading (€MM) H1 2025 H1 2026 (1) Revenue (incl. Intercompany eliminations) 264 444 Construction 224 399 PPPs & Concessions 8 38  Revenue growth reflecting selective bidding Facility Management 39 41 and acceleration of high-value projects rather than volume

  43. Slide 43: Medium-Term Financial Objectives

    Slide 43: Medium-Term Financial Objectives

    Medium-Term Financial Objectives ● Topline driven by the execution of the current strong backlog and backlog replenishment; on average, >€1.0bn annual replenishment of the backlog throughout the cycle(1) ● Good visibility on a growing project wallet with METKA well positioned to achieve win rate of

  44. Slide 44: Next Wave of Growth: PPPs, Concessions and Real Estate

    Slide 44: Next Wave of Growth: PPPs, Concessions and Real Estate

    Our Next Wave of Growth Driven by PPPs, Concessions and Real Estate Optionality A wide infrastructure opportunity set for METKA Creating Headroom to Capture Attractive Opportunities and Expand Our Business Illustrative Sources & Uses, medium-term horizon Organic Cashflows of METKA Group Existing Cas

  45. Slide 45: Capital Allocation Policy

    Slide 45: Capital Allocation Policy

    Capital Allocation Policy Operating cash flow to be reinvested in the platform to support equity commitments on secured and expected PPPs/Concessions The company's net proceeds from the issuance of new shares will enhance financial flexibility to pursue additional growth on PPPs/Concessions as well

  46. Slide 46: Appendix 1: Business Overview Additional Materials

    Slide 46: Appendix 1: Business Overview Additional Materials

    Appendix 1: Business Overview Additional Materials Company Presentation October 2026 46

  47. Slide 47: Nationwide Footprint of Landmark METKA Projects

    Slide 47: Nationwide Footprint of Landmark METKA Projects

    Nationwide Footprint – Landmark METKA Projects Delivered Spanning the Length And Breadth Of Greece Construction(1) PPPs Under Construction Casino Voria 17 Bioclimatic Schools Integrated resort casino development featuring a 160+ room luxury hotel, gaming, Design, financing, construction, entertainme

  48. Slide 48: Building a More Sustainable Future, the METKA Way

    Slide 48: Building a More Sustainable Future, the METKA Way

    Building a More Sustainable Future, the METKA Way – Greener Buildings, Safer Sites and Strong Governance Resource-efficient, low-impact construction Energy, water & resource  Energy- and water-efficient, lower-carbon efficiency construction – LEED-certified and bioclimatic buildings– plus environme

  49. Slide 49: METKA Turns Sustainability into Action

    Slide 49: METKA Turns Sustainability into Action

    METKA Turns Sustainability into Action – Sustainable Buildings & Urban Regeneration, Energy-Efficient Infrastructure and a Robust ESG Framework Sustainable buildings & urban Resilient infrastructure & resource ESG framework & sustainability regeneration efficiency credentials Growing environmental-i

  50. Slide 50: Governance Framework Protecting All Shareholders

    Slide 50: Governance Framework Protecting All Shareholders

    Governance Framework Protecting All Shareholders, Alongside METLEN’s Continued Strategic Support Operational Autonomy, with METLEN Remaining Majority Shareholder and Strategic Partner Strategic relationship with METLEN Related-party arrangements ■ Role: METKA is METLEN’s infrastructure investment pl

  51. Slide 51: Appendix 1.2: Construction Projects

    Slide 51: Appendix 1.2: Construction Projects

    Appendix 1.2: Construction Projects Company Presentation October 2026 51

  52. Slide 52: Built Around METKA ATE: A Contractor Platform

    Slide 52: Built Around METKA ATE: A Contractor Platform

    Built Around METKA ATE: A Contractor Platform Integrating Complementary Specialists Across the Full Value Chain METKA ATE ELEMKA Flagship contractor Building construction specialist ● Holds a 4th-class contractor’s license and delivers civil-engineering projects €287MM from design to delivery Backlo

  53. Slide 53: Portfolio of Projects Under Construction (1/7)

    Slide 53: Portfolio of Projects Under Construction (1/7)

    Portfolio of Projects Under Construction (1/7) Casino VORIA Thessaloniki Port Extension The VORIA Project is a mixed-use tourism and entertainment development in The project relates to the construction of 513m long by 306.5m wide quay Marousi, Athens. Spanning a 55,000-square-meter plot, the project

  54. Slide 54: Portfolio of Projects Under Construction (2/7)

    Slide 54: Portfolio of Projects Under Construction (2/7)

    Portfolio of Projects Under Construction (2/7) Thessaloniki Ring Road – Flyover Chalkida & Psachna Bypass The project upgrades a total 12-13 km highway axis, highlighted by a The project entails constructing an upgraded 27-to-28 km highway axis landmark 7.54 km elevated expressway built directly abo

  55. Slide 55: Portfolio of Projects Under Construction (3/7)

    Slide 55: Portfolio of Projects Under Construction (3/7)

    Portfolio of Projects Under Construction (3/7) Yperia–Orfana Irrigation Network Ellinikon Commercial Complex – Riviera Galleria The engineering scope entails the full design, financing, construction, and The project involves the development of a premium retail, F&B, and leisure long-term maintenance

  56. Slide 56: Portfolio of Projects Under Construction (4/7)

    Slide 56: Portfolio of Projects Under Construction (4/7)

    Portfolio of Projects Under Construction (4/7) Athens-Thessaloniki Railway Restoration 17 Bioclimatic Schools The milestone development involves the turnkey study, financing, and rollout The Athens–Thessaloniki railway line is a 500-kilometer, double-track, fully of 17 bioclimatic school complexes s

  57. Slide 57: Portfolio of Projects Under Construction (5/7)

    Slide 57: Portfolio of Projects Under Construction (5/7)

    Portfolio of Projects Under Construction (5/7) Western Attica Suburban Railway Naval Heritage Park The engineering scope involves constructing and upgrading a 34.6-kilometer The Naval Tradition Park "Odysseus" is a cultural and maritime infrastructure single-track rail line built along the historic,

  58. Slide 58: Portfolio of Projects Under Construction (6/7)

    Slide 58: Portfolio of Projects Under Construction (6/7)

    Portfolio of Projects Under Construction (6/7) Ellinikon Residential Complex (Little Athens) AENAON Urban Metropolitan Park Macro-scale residential and urban regeneration development located at the Part of a broader investment program aimed at redeveloping the Faliro Bay Alimos-facing zone. Construc

  59. Slide 59: Portfolio of Projects Under Construction (7/7)

    Slide 59: Portfolio of Projects Under Construction (7/7)

    Portfolio of Projects Under Construction (7/7) Skaramagas Triple Junction The development is engineered to unclog one of Greece’s most crucial commercial freight arteries. The infrastructure scope entails the complete construction of 3 grade-separated interchanges in the wider Skaramagas area (Skara

  60. Slide 60: From Award to Final Acceptance

    Slide 60: From Award to Final Acceptance

    From Award to Final Acceptance: How Projects are Executed, Billed and De-risked Project Lifecycle 1 Award & mobilisation 2 Construction 3 Provisional acceptance 4 Warranty period 5 Final acceptance Advance payment funds Periodic (typically monthly) Testing & commissioning Up to 3 years: repairs, At

  61. Slide 61: Strong Construction Project Pipeline

    Slide 61: Strong Construction Project Pipeline

    Strong Construction Project Pipeline to Support Backlog Replenishment in Coming Years Broader references and growing Greek infrastructure market support disciplined construction growth across public and private sector Apply and Strengthen Proven Capabilities to the Next Opportunities Strong Opportun

  62. Slide 62: Appendix 1.3: PPPs & Concessions

    Slide 62: Appendix 1.3: PPPs & Concessions

    Appendix 1.3: PPPs & Concessions Company Presentation October 2026 62

  63. Slide 63: M Concessions: PPPs & Concessions Platform

    Slide 63: M Concessions: PPPs & Concessions Platform

    M Concessions – METKA's PPPs & Concessions Platform, Building Long-term, Visible Cash Flows with Significant Growth Ahead Scaling, Recurring Concession Income Nationwide PPP Footprint Revenue (€MM) 72 42 17 Thessaloniki Central Macedonia 17 bioclimatic schools in Central Macedonia 4 Key Highlights 2

  64. Slide 64: Signed PPP Project: Thessaloniki Ring Road – Flyover

    Slide 64: Signed PPP Project: Thessaloniki Ring Road – Flyover

    Signed PPP Project: Thessaloniki Ring Road – Flyover Upgrade and Extension of the Thessaloniki Inner Ring Road Thessaloniki Key Highlights Ring Road - Project includes design, construction, operation & maintenance of an upgrade of the Thessaloniki Eastern Inner Ring Road The existing road is a dual

  65. Slide 65: Signed PPP Project: 17 Bioclimatic Schools

    Slide 65: Signed PPP Project: 17 Bioclimatic Schools

    Signed PPP Project: 17 Bioclimatic Schools Construction and Management of 17 Bioclimatic Schools in Central Macedonia 17 Bioclimatic Key Highlights Schools Project includes design, financing, construction, maintenance and operation of 17 schools in 9 municipalities of Central Macedonia State-of-the-

  66. Slide 66: Signed PPP Project: Yperia-Orfana Irrigation Network

    Slide 66: Signed PPP Project: Yperia-Orfana Irrigation Network

    Signed PPP Project: Yperia-Orfana Irrigation Network Construction and Management of the Yperia – Orfana Irrigation Network Key Highlights Project includes design, financing, construction, operation and maintenance of the Yperia-Orfana irrigation network Yperia-Orfana Irrigation Network It aims to mo

  67. Slide 67: Signed PPP Project: Epirus Street Lighting

    Slide 67: Signed PPP Project: Epirus Street Lighting

    Signed PPP Project: Epirus Street Lighting Upgrade of the Epirus Region Lighting Network Key Highlights Project includes design, financing, upgrade, installation and management of the street-lighting system of the Region of Epirus Epirus It aims to improve the road safety, reduce energy consumption

  68. Slide 68: Preferred Bidder: University of Western Macedonia Student Halls

    Slide 68: Preferred Bidder: University of Western Macedonia Student Halls

    PPP Project – Preferred Bidder: University of Western Macedonia Student Halls Preferred Bidder for a 30-Year Concession for Student Halls Across Four University of Western Macedonia (UoWM) campuses Key Highlights University of Western Macedonia The project relates to the design, financing, construct

  69. Slide 69: Northern Road Axis of Crete (VOAK)

    Slide 69: Northern Road Axis of Crete (VOAK)

    Concession Project – Slated for Inclusion: Northern Road Axis of Crete (VOAK) Concession for the Northern Road Axis of Crete, Connecting Chania-Heraklion Motorway Key Highlights Project includes the design, financing, construction, operation and maintenance of a two-lanes road section in Northen Cre

  70. Slide 70: Near Term Wallet of Live Tenders

    Slide 70: Near Term Wallet of Live Tenders

    Deep, Diversified Project Near Term Wallet of Live Tenders Providing Visibility for Growth A Diversified Pipeline of 19 Projects Spanning Subsectors, Sizes and Stages of Commercial Maturity Project Sector NPV(1) Tender Stage 1 Corfu Island Water Supply Water / Irrigation €146MM Competitive Dialogue

  71. Slide 71: PPP Accounting & Cash Flow Profile (1/2)

    Slide 71: PPP Accounting & Cash Flow Profile (1/2)

    PPP Accounting & Cash Flow Profile – Illustrative Example (1/2) Accounting of an illustrative PPP project under IFRS (IFRIC 12)(1) Illustrative figures Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y15 Y20 Y26 Y27 Y28 Total Total Total Comments Y1-3 Y4-28 Y1-28 Construction Revenue 2.9 30.1 22.3 - - - - - - - - -

  72. Slide 72: PPP Accounting & Cash Flow Profile (2/2)

    Slide 72: PPP Accounting & Cash Flow Profile (2/2)

    PPP Accounting & Cash Flow Profile – Illustrative Example (2/2) Accounting of an illustrative PPP project under IFRS (IFRIC 12)(1) Illustrative figures Y1 Y2 Y3 Y4 Y5 Y6 Y7 Y8 Y9 Y10 Y15 Y20 Y26 Y27 Y28 Total Total Total Comments Y1-3 Y4-28 Y1-28 Therefore, the key difference is Construction Revenue

  73. Slide 73: Appendix 1.4: Facility Management

    Slide 73: Appendix 1.4: Facility Management

    Appendix 1.4: Facility Management Company Presentation October 2026 73

  74. Slide 74: Unison – Greece's Leading Facility Management Platform

    Slide 74: Unison – Greece's Leading Facility Management Platform

    Unison – Greece’s Leading Facility Management Platform Delivering Resilient, Recurring Income from a Blue-Chip Client Base Trusted by Greece’s 14 One Contract, Every Service Leading Organizations Certifications Integrated Facility Management with tailored Unison’s client base includes solutions unde

  75. Slide 75: Unison: Closing the Loop – Synergies & Repositioning

    Slide 75: Unison: Closing the Loop – Synergies & Repositioning

    Unison: Closing the Loop – Synergies & Repositioning Build Own & operate Maintain & manage An integrated build-operate-maintain platform – Unison closes the loop with long-term, recurring services on Group-built and PPP assets Revenue Synergies Repositioning Cross-sell O&M and facility management on

  76. Slide 76: Appendix 2: Additional Macro & Market Materials

    Slide 76: Appendix 2: Additional Macro & Market Materials

    Appendix 2: Additional Macro & Market Materials Company Presentation October 2026 76

  77. Slide 77: Supportive Macroeconomic Background

    Slide 77: Supportive Macroeconomic Background

    Supportive Macroeconomic Background with Solid Fundamentals and EU-Leading Growth Nominal GDP Growing Consistently Ahead of the EU Inflation Easing Sharply from Its 2022 Peak Nominal GDP (€Bn) CPI Inflation (YoY, %) (8%) 14% (0%) 11% 5% 9% 10% 4% 16% (2%) 13% (3%) 10% 4% 9% 8% 3% 12% 8% 269.8 280.9

  78. Slide 78: Greece Increasingly Attractive for Debt and Equity Investors

    Slide 78: Greece Increasingly Attractive for Debt and Equity Investors

    Greece Is Increasingly Attractive for Both Debt and Equity Investors Investment Grade Rating from All Five Major Agencies Greek Spreads to Established EU Economies Tightening 10Y Benchmark Yield, Quarterly Yields, % BBB Stable 5% 4.0% 3.9% BBB 3.6% Positive 3% 3.2% BBB 1% 0.7% Positive 0.3% (0.1%) B

  79. Slide 79: Persistent Infrastructure Underinvestment Creates a Catch-Up Need

    Slide 79: Persistent Infrastructure Underinvestment Creates a Catch-Up Need

    Persistent Infrastructure Underinvestment Creates a ‘Catch-Up’ Need, Supporting a Visible Multi-Year Investment Opportunity Sizeable Investment Pipeline Across Our Four Core Long-Accumulated Infrastructure Investment Gap in Greece Infrastructure Categories Infrastructure Spend Gap in Greece (Compare

  80. Slide 80: Strong Momentum in Construction Activity

    Slide 80: Strong Momentum in Construction Activity

    Strong Momentum in Construction Activity Driven by Growing Investment Construction Output Has Accelerated Sharply… …Led by a Surge in Housing Investment… Construction Production Index(1), 2019 = 100 Gross Capital Formation, Housing, €Bn n.m. (10) 6 12 10 24 3 1% 1% 1% 2% 2% 3% 3% 146.6 7.6 143.1 119

  81. Slide 81: Established PPP Framework and Pipeline

    Slide 81: Established PPP Framework and Pipeline

    Established PPP Framework Combined with Significant Pipeline of New Opportunities Across Sectors Established Legal Framework and Dedicated Approval Supportive Recent Legislative and Funding Process Developments for PPP Frameworks 34 Approved PPP Projects (2) March 2026 Contracting • Defines the proj

  82. Slide 82: Water, Climate Resilience and Environmental Infrastructure

    Slide 82: Water, Climate Resilience and Environmental Infrastructure

    Water, Climate Resilience and Environmental Infrastructure Emerging as Major Investment Themes Launch of Comprehensive €3.4Bn Substantial Water Investment Needs and Announced Programmes National Water Strategy >50% Decline Sizeable Investments Required Across the Country in water reserves serving At

  83. Slide 83: Recovering Real Estate Market

    Slide 83: Recovering Real Estate Market

    Recovering Real Estate Market Creates Growing Pipeline of New Opportunities Residential Property Prices Up 37% Since 2019 Office Values Up 25% Since 2019, Rising Every Year Retail Housing Price Index, 2019 = 100 Office Price Index, 2019 = 100 124.7 136.5 118.7 130.2 112.8 119.7 102.9 106.6 111.7 100

  84. Slide 84: Logistics Opportunity

    Slide 84: Logistics Opportunity

    Scarcity of Modern Logistics Space and Port–Rail Connectivity Investments Create a Growing Logistics Opportunity Greek Logistics Yields at a Premium to Core Europe Demand for Modern Space Outpacing Supply Prime Logistics Net Initial Yields (%) c.200bps premium vs. Pan- European average 6.75% c.5% €5

  85. Slide 85: Facility Management Services Activity Expanding

    Slide 85: Facility Management Services Activity Expanding

    Facility Management Services Activity Expanding with Increasing Focus on Lifecycle Performance Broad Service Offering Greek Building-Services Activity Growing Hard services — Maintaining the asset Services to Buildings Turnover, (Turnover Index 2021 = 100) Preventive and corrective maintenance of bu

  86. Slide 86: Attractive Macroeconomic Backdrop in Southeast Europe

    Slide 86: Attractive Macroeconomic Backdrop in Southeast Europe

    Attractive Macroeconomic Backdrop in Southeast Europe with Solid Fundamentals and Ongoing Growth Trajectory Mainly Investment Grade markets remaining on above-EU growth path GDP per Capita Converging Towards the EU, with Continued Room to Grow Economies Forecasted to Grow Faster than the EU in 2027

  87. Slide 87: Focus Markets Share Macro Tailwinds and EU / IFI Funding

    Slide 87: Focus Markets Share Macro Tailwinds and EU / IFI Funding

    Focus Markets Share Macro Tailwinds and Deep EU / IFI Funding, with Romania and Serbia Leading the Opportunity Key Focus Markets, Ranked by Infrastructure Opportunity Country Ranking (1) #1 Romania #2 Bulgaria #3 North Macedonia #4 Serbia #5 Croatia Macroeconomic Tailwinds      BBB- / Baa3 BBB+

  88. Slide 88: Appendix 3: Financials

    Slide 88: Appendix 3: Financials

    Appendix 3: Financials Company Presentation October 2026 88

  89. Slide 89: Transparent Financial Framework: Segment-to-Group Reconciliation

    Slide 89: Transparent Financial Framework: Segment-to-Group Reconciliation

    Transparent Financial Framework Connecting Segment Performance, Group Results and PPP Economics Across an Integrated Infrastructure Platform Segment-to-Group Reconciliation (€MM) How to Read the Segment Figures €MM 2024a 2025a H1 2025a H1 2026a LTM Jun-2026 Revenue (incl. intercompany eliminations)

  90. Slide 90: Strong Net Cash Generation and Net Cash Position

    Slide 90: Strong Net Cash Generation and Net Cash Position

    Strong Net Cash Generation and a Robust Net Cash Position Providing the Capacity to Self-Fund the Investment Programme EBITDA to Free Cash Flow (€MM) Adjusted Net Cash Reconciliation (€MM) LTM €MM 31 Dec 2024 31 Dec 2025 30 Jun 2026 €MM 2024a 2025a H1 2025a H1 2026a Jun-2026 Cash and cash equivalent

  91. Slide 91: Summary P&L

    Slide 91: Summary P&L

    Summary P&L 1 P&L Overview Key Highlights €MM 2024a 2025a H1 2025 H1 2026 2 Sales 363.9 688.8 263.8 444.0 Cost of goods sold (294.0) (564.6) (227.3) (355.2) Gross profit 70.0 124.2 36.5 88.8 1  Figures are presented on the combined carve-out 3 % margin 19.2% 18.0% 13.8% 20.0% basis for the proposed

  92. Slide 92: Summary Balance Sheet

    Slide 92: Summary Balance Sheet

    Summary Balance Sheet 1 Balance Sheet Overview – Assets Key Highlights €MM 31 Dec 2024 31 Dec 2025 30 Jun 2026 Property, plant and equipment 35.0 36.0 27.0 Goodwill 19.5 17.4 17.4 Intangible assets 9.1 4.7 0.1 1  Balance sheet reflects the combined carve-out 2 Investments in associates 0.2 6.6 9.6

  93. Slide 93: Summary Balance Sheet

    Slide 93: Summary Balance Sheet

    Summary Balance Sheet Balance Sheet Overview – Equity & Liabilities Key Highlights €MM 31 Dec 2024 31 Dec 2025 30 Jun 2026 Share capital / Share premium 0.7 0.7 0.7 Reserves (10.6) (0.4) (1.1) 1 Retained earnings 243.6 328.4 395.7 Equity attributable to equity holders of the parent 233.7 328.6 395.3

  94. Slide 94: Summary Cash Flow Statement

    Slide 94: Summary Cash Flow Statement

    Summary Cash Flow Statement Cash Flow Statement Overview Key Highlights €MM 2024a 2025a H1 2025 H1 2026 Profit before income tax 53.0 108.3 32.9 83.5 Depreciation of property, plant and equipment 1.6 2.3 1.1 1.5 Amortization of intangible assets 2.4 2.3 2.3 0.2 Depreciation of right-of-use assets 1.

  95. Slide 95: Appendix 4: Investment Proposition & Strategy

    Slide 95: Appendix 4: Investment Proposition & Strategy

    Appendix 4: Investment Proposition & Strategy Company Presentation October 2026 95

  96. Slide 96: Glossary of Terms (1/5)

    Slide 96: Glossary of Terms (1/5)

    Glossary of Terms (1/5) Definitions of presentation-specific measures should be read together with the relevant slide footnotes Terms Definitions Adjusted Net Cash Cash and cash equivalents plus restricted cash deposits less recourse debt related to Unison; project-level debt, which is non-recourse,

  97. Slide 97: Glossary of Terms (2/5)

    Slide 97: Glossary of Terms (2/5)

    Glossary of Terms (2/5) Terms Definitions EBITDA Margin EBITDA / Revenue. EBRD European Bank for Reconstruction and Development. EC European Commission. ECB European Central Bank. EEA European Economic Area. EIB European Investment Bank. ELSTAT Hellenic Statistical Authority. EPA National Developmen

  98. Slide 98: Glossary of Terms (3/5)

    Slide 98: Glossary of Terms (3/5)

    Glossary of Terms (3/5) Terms Definitions FY Financial Year. GDP Gross Domestic Product. GVA Gross Value Added. H1 / H2 First Half / Second Half of the relevant financial year. HSE Health, Safety and Environment. International Financial Reporting Interpretations Committee Interpretation 12, Service

  99. Slide 99: Glossary of Terms (4/5)

    Slide 99: Glossary of Terms (4/5)

    Glossary of Terms (4/5) Terms Definitions LEED Leadership in Energy and Environmental Design. LSE London Stock Exchange. LTM Last Twelve Months ending on the stated reporting date; LTM Jun-2026 is calculated as 2025a less 1H 2025a plus 1H 2026a. M&A Mergers and Acquisitions. MM Million. MW Megawatt.

  100. Slide 100: Glossary of Terms (5/5)

    Slide 100: Glossary of Terms (5/5)

    Glossary of Terms (5/5) Terms Definitions PLC Public Limited Company. Public-Private Partnership; a long-term arrangement under which a private party designs / delivers, finances and operates or maintains a public asset or service under PPP contract with a public authority. Aggregate project NPV (10

Source: company website