EcoGraf Ltd. · ASX:EGR

EcoGraf — Shareholder Meeting (November 2026)

36 slides from EcoGraf's shareholder meeting presentation, Nov 24, 2026

  1. Slide 1: Annual General Meeting 2026

    Slide 1: Annual General Meeting 2026

    24 November rsonal use only Annual General Meeting 2026 Building a Vertically Integrated Global Graphite Supply Chain ASX: EGR FSE: FMK

  2. Slide 2: Disclaimer

    Slide 2: Disclaimer

    Disclaimer Securities Disclaimer Competent Person and Compliance Statements This document is for informational purposes only and does not constitute an offer to sell, or solicit to purchase, any securities. The information in this presentation that relates to Exploration Results for the Golden Eagle

  3. Slide 3: Corporate Snapshot

    Slide 3: Corporate Snapshot

    Corporate Snapshot Market Cap: Stock Listings Major shareholders A$103.8 million ASX: EGR FSE: FMK rsonal use only Australian Securities Exchange Frankfurt Stock Exchange (Börse Frankfurt) 45.3% 52-week range: A$0.18 - A$0.505 HFfree 49.8% Facilities EU 4.9% Ordinary Shares US DEMAND on Issue: DEMAN

  4. Slide 4: Our Board and Management Team

    Slide 4: Our Board and Management Team

    Our Board and Management Team BOARD & DIRECTORS ADVISORY BOARD rsonal use only ROBERT PETT ANDREW SPINKS JOHN CONIDI SVEN OLSSON DR PETER SCHUHMACHER VOLKMAR KLEIN Non-Executive Chair Managing Director Non-Executive Director Non-Executive Director Advisory Board Advisory Board MANAGEMENT Experienced

  5. Slide 5: Strategic Vertically Integrated Business

    Slide 5: Strategic Vertically Integrated Business

    Strategic Vertically Integrated Business rsonal use only Upstream Epanko Mine Midstream Mechanical Shaping Facility Large-scale, development-ready graphite project in Tanzania, offering compelling Value-addition processing in Tanzania through the micronising and spheronising of natural economics and

  6. Slide 6: Key Highlights for 2026

    Slide 6: Key Highlights for 2026

    Key Highlights for 2026 Progress across the vertically 01 EPANKO ADVANCEMENT 02 MIDSTREAM VALUE integrated graphite business, Mine Access Road compensation Up to €2m EIB Technical Assistance strategic partnerships and rsonal use only underway; development pathway commenced; shaping optimisation / co

  7. Slide 7: 2026 Year in Review

    Slide 7: 2026 Year in Review

    2026 Year in Review rsonal use only VIEW VIDEO > https://tinyurl.com/275pywu9 VIEW VIDEO: XXXXXXXXXX ASX:EGR FSE: FMK November 2026 www.ecograf.com.au 7

  8. Slide 8: From mining to integrated battery materials

    Slide 8: From mining to integrated battery materials

    Lithium–ion Battery Anode Cell Manufacturing From mining to integrated battery materials Value, margins and strategic importance increases Downstream Global Battery Manufacturing Markets rsonal use only MINING MECHANICAL HFfree COATING ANODE CELL SHAPING PURIFICATION MANUFACTURING • Extraction / Pro

  9. Slide 9: Lithium-ion Battery Manufacturing Hubs (Ex-China)

    Slide 9: Lithium-ion Battery Manufacturing Hubs (Ex-China)

    Lithium-ion Battery Manufacturing Hubs (Ex-China) Finland Sweden rsonal use only Germany Poland Canada France Hungary Compelling new global Spain South Korea Japan business opportunity to Portugal U.S. Morrocco develop raw material and anode supply chains India Vietnam In 2025 the battery market Mal

  10. Slide 10: EcoGraf HFfree Progresses European Industrial Site

    Slide 10: EcoGraf HFfree Progresses European Industrial Site

    EcoGraf HFfree® Progresses European Industrial Site Supporting Europe's push for secure, sustainable and diversified graphite and battery material supply chains. rsonal use only • Advancing assessment of a preferred German industrial site for a 25,000tpa EcoGraf HFfree® purification facility POLAND:

  11. Slide 11: Natural High-Purity Graphite and Battery Anode Demand

    Slide 11: Natural High-Purity Graphite and Battery Anode Demand

    Natural High-Purity Graphite and Battery Anode Demand Natural global graphite demand is NATURAL GRAPHITE DEMAND BY END-USE SECTOR forecast to significantly increase through the high-purity graphite and battery anode rsonal use only ’000 Tonnes Batteries Refractories Foundries & castings Friction Pro

  12. Slide 12: Structured Project Financing Strategy Advancing

    Slide 12: Structured Project Financing Strategy Advancing

    Structured Project Financing Strategy Advancing • Targeting optimal mix of senior debt, equity and strategic participation aligned with international project finance standards rsonal use only • KfW IPEX-Bank leading US$105M senior debt under German Government UFK program for Stage 1 (73,000 tpa) • P

  13. Slide 13: Strategic Project Equity Process and Value Proposition

    Slide 13: Strategic Project Equity Process and Value Proposition

    Strategic Project Equity Process and Value Proposition Focus is on securing strategic project equity for Stage 1 of the Epanko Project through partnerships in Midstream and Downstream developments in the lithium-ion battery manufacturing hubs rsonal use only Process progressing with large pool of ta

  14. Slide 14: Upstream Epanko Mine

    Slide 14: Upstream Epanko Mine

    Upstream Epanko Mine KfW IPEX-Bank mandated for UFK Loan up to PRIORITIES US$105M for development of Epanko • Stage 1 - 73,000tpa BFS complete with the Debt financing program progressing potential 20% increase to 87,600tpa rsonal use only Mwanza Project execution planning • ‘Life of Mine’ Special Mi

  15. Slide 15: Epanko Project Advantages

    Slide 15: Epanko Project Advantages

    Epanko Project Advantages Key advantages to drive lowest cost feedstock for lithium-ion battery market TRANSPORT DISTANCE 450km TO PORT rsonal use only EPANKO MINE 75km TO RAIL MINERAL RESOURCE ESTIMATE ORE RESERVE ORE RESERVE GRADE AVERAGE THICKNESS 8.2% 200 300 21 57 % 250 200 150 290 TGC 100 MILL

  16. Slide 16: Epanko BFS Key Highlights for Stage 1

    Slide 16: Epanko BFS Key Highlights for Stage 1

    Epanko BFS Key Highlights for Stage 1 – 73,000tpa Low-cost, high margin graphite project with market-leading technical advantages and rigorous independent bank due diligence complete US$516M 31.1% 73,000tpa rsonal use only Pre-tax NPV10% Internal rate of return Stage 1 production – First 15 Years US

  17. Slide 17: Epanko – Largest Development Ready Resource in Africa

    Slide 17: Epanko – Largest Development Ready Resource in Africa

    Epanko – Largest Development Ready Resource in Africa • Epanko will provide long-term scalable lowest-cost natural graphite feedstock MINE LAYOUT for the Company’s downstream development • Extensive engineering studies, drilling and resource evaluation undertaken rsonal use only that’s delivered a n

  18. Slide 18: Epanko Processing Plant Flythrough

    Slide 18: Epanko Processing Plant Flythrough

    Epanko Processing Plant Flythrough rsonal use only PLANT FLYOVER VIDEO > https://tinyurl.com/ypmd7vme PROCESSING PLANT VIDEO > https://tinyurl.com/4k859b2h ASX:EGR FSE: FMK November 2026 www.ecograf.com.au 18

  19. Slide 19: Increased Production Lowers C1 Cost

    Slide 19: Increased Production Lowers C1 Cost

    Increased Production Lowers C1 Cost Supports Growing Customer Demand for Graphite • 20% production increase identified for Stage 1 capacity, from 73,000tpa to 87,600tpa. rsonal use only • Lower operating costs, with first 10-year C1 costs reduced 5.8% to approximately US$512/t. • Expansion achievabl

  20. Slide 20: Midstream Mechanical Shaping Facility

    Slide 20: Midstream Mechanical Shaping Facility

    Midstream Mechanical Shaping Facility Positioning to be first development PRIORITIES supporting Tanzanian Government’s Secure financing arrangements ‘Vision 2030’ value-addition strategy rsonal use only • Ifakara identified as the preferred location Mwanza Finalise offtake agreements Arusha • 75km f

  21. Slide 21: Mechanical Shaping Facility

    Slide 21: Mechanical Shaping Facility

    Mechanical Shaping Facility • Accelerated development pathway through completed engineering studies • Extensive testwork programs delivering high yields rsonal use only of ~60% • Independent engineering study completed for 20,000tpa Stage 1 Facility Cost Operating Cost US$58.6m US$419/t • European I

  22. Slide 22: Product Qualification Facility (PQF)

    Slide 22: Product Qualification Facility (PQF)

    Product Qualification Facility (PQF) Jointly funded under the Australian Government’s A$48.9 million Critical Minerals rsonal use only Development Program, with EcoGraf receiving A$2.9 million in grant funding for the PQF PQF piloting facility developed using r EcoGraf HFfree® Chemical Purification

  23. Slide 23: Downstream Chemical Purification Facilities

    Slide 23: Downstream Chemical Purification Facilities

    Downstream Chemical Purification Facilities Industry-leading low-cost driving growth, PRIORITIES supported by legislation advancing Formalise strategic partnerships for sustainable, diversified supply chains rsonal use only commercial scale production • Product qualification facility (PQF) programs

  24. Slide 24: HFfree Battery Anode Material Development History

    Slide 24: HFfree Battery Anode Material Development History

    HFfree Battery Anode Material Development History Extensive testwork, bench scale and piloting programs completed underpins and derisks EcoGraf HFfree® processing technology PQF Delivers HFfree Cost Major Project Status Competitiveness Approved by Australian rsonal use only Government Australian Pat

  25. Slide 25: EcoGraf HFfree Process Advantages

    Slide 25: EcoGraf HFfree Process Advantages

    EcoGraf HFfree® Process Advantages HIGHLY EFFECTIVE CHEMICAL PROCESS TO REMOVE IMPURITIES FROM NATURAL GRAPHITE & CARBON MATERIALS rsonal use only Proprietary technology Low-cost Intellectual property security process Competitive economics advanced including: compared to the other • Europe, Malaysia

  26. Slide 26: Downstream Financial Metrics for 25,000tpa Facility

    Slide 26: Downstream Financial Metrics for 25,000tpa Facility

    Downstream Financial Metrics for 25,000tpa Facility Financial metrics based on U.S. location confirms high margin business US$282M 39% 25,000tpa rsonal use only Pre-tax NPV10% Internal rate of return Stage 1 production – First 15 Years US$95M US$42M US$478/t Stage 1 Capex (real) Annual EBITDA (real)

  27. Slide 27: EcoGraf HFfree Purification Delivers Industry-leading Cost

    Slide 27: EcoGraf HFfree Purification Delivers Industry-leading Cost

    EcoGraf HFfree® Purification Delivers Industry-leading Cost Significant cost advantage confirmed via PURIFICATION OPERATING COST COMPARISON - U.S. LOCATION updated benchmarking study 1,200 rsonal use only • Updated cost comparison based on global engineering & construction consultancy, comparing Eco

  28. Slide 28: Leading Lowest-Cost to Drive Production Growth

    Slide 28: Leading Lowest-Cost to Drive Production Growth

    Leading Lowest-Cost to Drive Production Growth Epanko feedstock combined with Midstream and HFfree delivers significant cost advantage as alternative to peers rsonal use only • EcoGraf positioned to be the leading lowest-cost against graphite producers for purified HFfree SpG (SPG) battery anode mat

  29. Slide 29: HFfree Technology Supports Global Battery Recycling

    Slide 29: HFfree Technology Supports Global Battery Recycling

    HFfree Technology Supports Global Battery Recycling EcoGraf HFfree® purification supports closed PRIORITIES loop recycling and battery circular economy Feedstocks supplied by EV and • Essential for maximising battery manufacturer rsonal use only battery manufacturers to advance to piloting processin

  30. Slide 30: Low Cost, High Margin with Leading ESG

    Slide 30: Low Cost, High Margin with Leading ESG

    Low Cost, High Margin with Leading ESG EcoGraf HFfree® Vertically Integrated Battery Anode Materials Business Integrated from mine-to-battery anode material, capturing rsonal use only value across the supply chain Epanko Graphite Project provides a long-life, high quality graphite feedstock Propriet

  31. Slide 31: HFfree Development Pathways on a Global Scale

    Slide 31: HFfree Development Pathways on a Global Scale

    HFfree Development Pathways on a Global Scale Partnerships through Strategic Project Equity Process to Drive Downstream Chemical Purification Facilities in the Lithium-ion Battery Manufacturing Hubs GOVERNMENT SUPPORT rsonal use only EU DEMAND Germany, France, Poland, Hungary, Spain, Portugal, Swede

  32. Slide 32: Golden Frontier – Value-Add Gold Assets

    Slide 32: Golden Frontier – Value-Add Gold Assets

    GOLDEN FRONTIER rsonal use only Value-Add Gold Assets Decades of in-country and geological expertise allows us to explore Tanzania’s gold frontiers ASX: EGR FSE: FMK

  33. Slide 33: Golden Frontier – Investment Highlights

    Slide 33: Golden Frontier – Investment Highlights

    Golden Frontier – Investment Highlights US$9m AngloGold Ashanti farm-in agreement at Golden Eagle commenced1 rsonal use only Southern Frontier delivering phenomenal results including 4.45 g/t gold rock chip & 3 km anomaly at Hazina2 Projects proximal to gold mining centres, including high-grade Wins

  34. Slide 34: Targeting Proterozoic Gold Mineralisation - Frontier Projects

    Slide 34: Targeting Proterozoic Gold Mineralisation - Frontier Projects

    Targeting Proterozoic Gold Mineralisation - Frontier Projects OUR PROJECTS N Northern Frontier rsonal use only Major Gold Projects NORTH MARA +70 Moz gold Archean Golden Frontier Project Lake Victoria Goldfield Archean Gold Project GEITA Proterozoic Gold Project NYANZAGA Proterozoic Terrain Archean

  35. Slide 35: The future is electric with EcoGraf HFfree purification

    Slide 35: The future is electric with EcoGraf HFfree purification

    The future is electric with EcoGraf HFfree® purification and Tanzanian graphite rsonal use only 18 Richardson Street, West Perth WA 6005 [email protected] www.ecograf.com.au ASX: EGR FSE: FMK

  36. Slide 36: Appendix – Epanko MRE and Ore Reserve

    Slide 36: Appendix – Epanko MRE and Ore Reserve

    Appendix 1 Table 1 – Epanko MRE >5.5% TGC JORC Tonnage Grade Contained Graphite rsonal use only Classification (Mt) (%TGC) (Kt) Measured 32.3 7.8 2,500 Indicated 55.7 7.5 4,200 Measured+ Indicated 88.0 7.6 6.710 Inferred 202.8 7.2 14,310 Total 290.8 7.2 21,010 Notes for Table 1: Tonnage figures cont

Source: ASX announcement, Nov 24, 2026

More decks from EcoGraf Ltd.

All 53 EcoGraf decks