Agl Energy Limited · ASX:AGL
Agl Energy — Corporate Update (February 2017)
13 slides from Agl Energy's corporate update, Feb 9, 2017
Slide 1: Coopers Gap Wind Farm Community Consultative Committee
Coopers Gap Wind Farm Community Consultative Committee Presented by Tim Knill – Power Development Date Thursday, 9 February 2017 12 pm
Slide 2: Agenda
Presentation title | 2 Agenda 1 2 3 4 5 Welcome Project status Solar for Next Meeting Close update Neighbours Evan Carless – February, 2017
Slide 3: Welcome
Welcome 1 Confirmation of November minutes
Slide 4: Review Previous Meeting Actions
Coopers Gap CCC | 4 Review Previous Meeting Actions Action Item CCC meeting Status Who Ensure minutes are posted to Jim Scutt and Russell Ongoing CM Glode Evan Carless – February, 2017
Slide 5: Project Status Update
Project 2 Status Update
Slide 6: Project Status Update: EIS update
Coopers Gap CCC | 6 Project Status Update EIS update EIS update • 19th Dec 2016 Coordinator General accepted Draft EIS as the Final EIS • Evaluation stage commenced by Coordinator General • Anticipate a decision by Coordinator General early – mid March 2017 Evan Carless – February, 2017
Slide 7: Project Status Update: Grid Connection and Tender
Coopers Gap CCC | 7 Project Status Update Grid Connection and Tender Connection to Grid • Powerlink detailed scope of works for connecting wind farm to Transmission network • Negotiating connection agreement with Powerlink Tender Update • Tender negotiations ongoing with potential suppliers / constr
Slide 8: PARF Update
Coopers Gap CCC | 8 PARF Update • AGL announced on the 19th January 2017 the 200MW Silverton wind farm in western New South Wales is set to proceed to construction having achieved financial close on the sale of the project to the Powering Australian Renewables Fund (PARF) • Approximately $450 millio
Slide 9: Solar for Neighbours
Solar for 3 Neighbours
Slide 10: Other Business: Solar for wind farm neighbours
Coopers Gap CCC | 10 Other Business Solar for wind farm neighbours - Proposal is that AGL will offer to wind farm neighbours within approximately 2 km’s of the wind farm boundary 5 kW of Solar Panels - Offer dependent upon the wind farm being committed to construction - If committed to construction,
Slide 11: Next Meeting
4 Next Meeting
Slide 12: Next Meeting
Coopers Gap CCC | 12 Next Meeting › May 2017 › Time › Location › Next meeting Tim will present on ‘Wind Turbine Technology’ Evan Carless – February, 2017
Slide 13: Close
5 Close