  1. Slide 1: Terramin General Update

    Terramin General Update Joe Ranford – General Manager Angas Zinc Mine 1

  2. Slide 2: AZM: Closure Plan and PEPR Completion

    AZM: Closure Plan and PEPR Completion  20th January 2017

  3. Slide 3: Angas Zinc Mine

    Angas Zinc Mine  December rainfall 3x higher than average (77mm:25mm)  Tailings Dam – No exceedance of Lease Conditions or Outcome Criteria  Pump failure in November from SA power outage  Secondary pump and evaporation system installed in November activated  Increased rainfall resulted in water

  4. Slide 4: Terramin - Projects

    Terramin - Projects  Bird in Hand  Ongoing baseline studies and modelling  Currently working through revised Project Risk Assessment now baseline reports almost complete  New Source Pathway Receptor risk model from DSD  Preliminary design work  Draft of Mining Lease Proposal by end of March 

  5. Slide 5: Quarterly Environment Report

    Quarterly Environment Report Katy Fechner – Environment and Community Officer Angas Zinc 5

  6. Slide 6: Rainfall (mm/month)

    Angas Zinc Mine  Tailings Dam – No exceedance of Lease Conditions or Outcome Criteria  Increased rainfall resulted in higher than 15000m2 surface area (approx. 16000m2)  Secondary pump and evaporation system activated after rainfall events  29th January instance rectified within the compliance c

  7. Slide 7: Secondary pump turned on

     24th December 2016  13950m2  29th December 2016  67mm rainfall in 3 hours  Approx. 16000m2  Secondary pump turned on  6th January  <15000m2

  8. Slide 8: Litres/minute

         Litres/minute 0.00 5.00 10.00 15.00 20.00 25.00  05/09/08 24/10/08 12/12/08 30/01/09 20/03/09 06/05/09 26/06/09 14/08/09 09/10/09 2L/minute 27/11/09 08/01/10 26/02/10 16/04/10 04/06/10 23/07/10 10/09/10 29/10/10 17/12/10 04/02/11 25/03/11 67mm over 3 hours 27/05/11 becomes free water 15/0

  9. Slide 9: Dust: Offsite Gauges high - Landuse

    Dust: Offsite Gauges high - Landuse  No mining activities onsite  Elevated dust levels due to agricultural activities  Govt. records: Light purple and Light Green = Cropping  Late Spring/early Summer = Harvest/Reaping  Lead readings = Naturally occurring – soil parameters = Govt. records of top

  10. Slide 10: Special Interest: Surface Water Sampling

    Special Interest: Surface Water Sampling  EPA requirement  Three samples are taken at both Hogben and Croser  This reduced risk of bias, outliers and errors  Testing for  Basic Chemistry - pH, EC, TDS, Turbidity, SO4,  Metals - As, Cd, Cu, Pb, Mn, Se, Zn, Fe HOGBEN  Organics – Nitrates, Phosp

  11. Slide 11: Landscape Function Analysis completed for 2016

    Landscape Function Analysis completed for 2016 T2 T3  Care of Our Environment Pty Ltd T4 T5  Reviewed Terramin’s 2014-2015 LFA reports  Monitoring Sites T1  Six 100m transects were established  Five revegetation sites within the our land Angas Zinc Mine 2016 Landscape Function Analysis transect

  12. Slide 12: Soil Health Assessment

    Soil Health Assessment Target  Control Site “WC1” comparison 70  Stability is similar amongst on-site (T1-T5) 60 (58-65%) and analogue site (WC1)(61%) 50  Nutrients at T1 (Western) and T4 (Eastern) are greater than WC1 40  Stability and nutrient cycling is most 30 different between WC1 and T5 (E

  13. Slide 13: Upcoming Works for Q1 2017

    Upcoming Works for Q1 2017  TSF Annual Surveillance Site Visit and Review – 2nd March  Develop fact sheets on Closure Plan aspects under the guidance of SCCC feedback to report to community on closure plan aspects  Summer weed control and fuel load management

  14. Slide 14: Closure Plan Update

    Closure Plan Update Katy Fechner – Environment and Community Officer Angas Zinc 14

  15. Slide 15: Closure Plan

    Closure Plan  Submitted 20th January after internal management review  Closure plan currently being reviewed by Government regulators and their consultants

  16. Slide 16: Closure Plan includes

    Closure Plan includes  Legislative requirements from Mining Act, Regulations, Determinations and guidelines  Failure Modes and Effects Analysis – additional risk assessment  PEPR Guidelines and Lease Conditions (Outcomes)  Tailings and Large Dam Guidelines  General Mining Guidelines  Internati

  17. Slide 17: Leading Indicators for Erosion

    Leading Indicators for Erosion  Monitoring:  LFA (rill and gully analysis)  Photo and visual monitoring of topsoil  Qualified expert (to DSD’s satisfaction) verifies:  Boxcut has been constructed to design  Decline cap and vent raise cap has been constructed to design  TSF cover landforms has

  18. Slide 18: Closure Criteria for Erosion

    Closure Criteria for Erosion  Monitoring  Surface water at site water exit points for turbidity  Qualified expert (to DSD’s satisfaction) analyses:  All erosion leading indicators over the closure monitoring phase  Qualified expert (to DSD’s satisfaction) analyses:  All LFA data and reports ba