General Moly Inc

General Moly — Idaho General Mines — Investor Presentation (September 2007)

59 slides from General Moly's investor presentation, Sep 21, 2007

  1. Slide 1: Mt. Hope

    Mt. Hope

  2. Slide 2: Forward Looking Statements

    Forward Looking Statements This presentation contains “forward-looking statements” within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Seourities Exchange Act of 1934, as amended that are intended to be covered by the safe harbor created by such sectio

  3. Slide 3: Mt. Hope Background

    Early 1970s Late 1970s 1978 1982 1988 1995 2004 Oct 2005 Mt. Hope Background Zinc and adjacent copper mineralization drilled by Phillips Petroleum. Further zinc and initial molybdenum mineralization identified by ASARCO. Exxon Minerals acquired option on property from underlying landowners. Exxon dr

  4. Slide 4: Mt. Hope Background

    Mt. Hope Background Mount Hope: North-South Section Looking West * Mt. Hope located in lower foothills of Roberts Mountains, 8.000 ft in elevation. + Located on the Battle Mountain/Eureka mineral belt + 13 Patented and 1.374 unpatented claims — total land package of 28.2 sq miles + Higher-grade moly

  5. Slide 5: Mt. Hope - Geology

    Mt. Hope - Geology

  6. Slide 6: Historic Mining

    ——— er a — == mano “(GENERAL tee’ Historic Mining a GMO:AMEX ESS * 1870’s through 1970's * Zn-Pb-Cu-Ag * All underground methods ¢ $1M polymetallic produced @ 6% Zn « Polymetalic Zone of unknown extent around exterior of deposit ey

  7. Slide 7: Historic Mining

    Historic Mining — SSS | \ 1942-45 Wil) \ USBM Drilling fo ) i) 1926 U.S. Smelting ide Calahan Zn-Pb Se ~ “4890's Whim Shaft | 886 Lorraine = & No. 2 Adit

  8. Slide 8: Mt. Hope Geology

    cmoamex “psss® Mt. Hope Geology Simplified Geologic Map of the Mount Hope Molybdenum Project with Pit Outline Intrusive/Volcanic rocks + Green = Metamorphic rocks + Blue = Permian Limestone (zinc host) * Brown = Vinini Fm = Valley Fill Deposits

  9. Slide 9: Bulk of High Grade Mineralization Hosted in K-Sil Alteration

    Bulk of High Grade Mineralization Hosted in K-Sil Alteration

  10. Slide 10: Ultimate Pit

    Ultimate Pit Waste Rock Waste Rock Coreshed 0.069% Mo Grade Shell 165 historic drill holes mostly conducted by Exxon 230,000 feet of core meticulously preserved in core database & warehouse 49 samples check assayed by GMO, all conform to historic sample & results Ongoing confirmatory drilling by Ida

  11. Slide 11: Mount Hope Cross-sections

    Mount Hope Cross-sections Mount Hope: North-South Section Looking West et _ = a ¢Mt. Hope’s highest grades (red) are located near the top of the deposit ¢Mining & processing these high grades early drives high production tates, low cash costs, high NPV and short capital payback period

  12. Slide 12: Molybdenum Mineralization - Average Grade Doubles in Overlap Zone

    PAHO Generar d [Molybdenum Mineralization — Average Grade Doubles in Overlap Zone GMO:AMEX Overlap 0.12% * The overlap between the Eastern and Western mineralization lobes generates the high-grade core

  13. Slide 13: Location of 2007 drilling at Mt. Hope

    Location of 2007 drilling at Mt. Hope East side Condemnation and Exploration 10 Year Pit Infill Water Delineation” Green = Completed Red = Pre-collar Orange = Oriented Hole Blue = Water delineation 13 mot

  14. Slide 14: 2007 Mt. Hope Infill Drilling Highlights

    2007 Mt. Hope Infill Drilling Highlights Significant Intercepts for 24 & 3" Quarter Drilling Hole From To Length Assay (Mo %) MH-183 405 1235 830 0.1390 MH-184 365 1270 905 0.1453 MH-185 625 1330 705 0.1249 MH-186 635 1340 705 0.1208 MH-187 745 1380 635 0.1181 MH-188 780 1450 670 0.0965 MH-195 450 1

  15. Slide 15: Future Reserve Potential

    Future Reserve Potential GMO:AMEX. * Infill drilling in main porphyry * Open to the north, east, west and depth Peripheral polymetallic skarn ore Deep east side Moly ore extension

  16. Slide 16: Mt. Hope - Water

    Mt. Hope - Water 16

  17. Slide 17: Water Agency Review

    Agency Review June 29, 7 2007 i) Draft completion by August 2007 Well field testing Model will likely indicate minimal drawdown Model will be used for Pit Lake Geochem Recent drilling indicates potential increase in pit water — Pit water continues not to be a significant issue

  18. Slide 18: Water Drilling Plan and Schedule

    Water Drilling Plan Water Drilling Schedule * Base of Roberts Mountains Started Drilling April 25 * 10 Initial Holes Single RC Rig / Second Rig in Place + Target 1000 GPM Each May 15 + Targets Carbonates Completed August + Bore out if Productive to flow Full Well Test to begin September + Total Budg

  19. Slide 19: Mt. Hope Water Rights

    Mt. Hope Water Rights Source Rights MMUse Ad) = MMUse AFA Cost/Offer_—__Status MM AFA Sum GPM Bar Tine 59266 70% 41486 | § = Tabled - o Demale Bean Flat e064 70% 58145 § 777.448 Closing 58145, 360 Demale Dry Creek 689.72 70% 48280 $ 685,468 Closing 482.80 299 ‘OutBach 90 70% 6300S = 83.00 0 Targeted

  20. Slide 20: Kobeh Valley Water Drilling

    GMO:AMEX. ites: Y 2-4 Quarter Mt. Hope Kobeh Valley Water Drilling Exploration holes RWX-203 through 209 completed - 7 holes 7001’ drilled All holes, save RWX-208, encountered significant water; 203 & 204 in valley fill, all others in bedrock Observation and pump test wells planned and permitted Beg

  21. Slide 21: Mt. Hope - Mine Plan, Schedule & Equipment

    Mt. Hope - Mine Plan, Schedule & Equipment 21

  22. Slide 22: Mt. Hope Mine Plan

    Mt. Hope Mine Plan > Delivers higher grade mill feed in early years > Average ore grade in 1t 10 years of 0.094% Mo (0.100% over first 5 yrs) > Molybdenum contained in TMO in 1st 10 years averages 36.1 mlbs > Conventional open pit mining methods > Conventional processing plant methods 2

  23. Slide 23: Mt. Hope Molybdenum Production Schedule

    a > Recovered Lbs Mo x 1000 per Year Mt. Hope Molybdenum Production Schedule Mine life of 32 years Low grade stockpile processing for 12 years after mining activities cease Total project life of 44 years Mount Hope Molybdenum Production Schedule Summary 45000] Early High Grade Stockpile Treatment Ye

  24. Slide 24: Mt. Hope Mine Schedule

    GMO:AMEX Mt. Hope Mine Schedule > Nominal ore production rate of 60.6k tons/day; 22.1m tons/year » Nominal mining rate of 262k tons/day; 95.5m tons/year ‘Tonnes x 1000 per Year 100,000 90,000 80,000 70,000 60,000 50,000 40,000 Mount Hope Production Schedule Summary 30,000 +] 20,000 10,000 Year oezse

  25. Slide 25: Mt. Hope Site Plan

    Mt. Hope Site Plan

  26. Slide 26: Mt. Hope Plant Layout

    Mt. Hope Plant Layout

  27. Slide 27: Mt. Hope Mine Operational Plan

    Gmomex, Cee? Mt. Hope Mine Operational Plan Vv Conventional open pit mining methods including: drill, blast, load and haul Blastholes will be drilled, sampled and assayed for molybdenum content and metal generation potential After assay and blasting, material will be identified and designated for ha

  28. Slide 28: Mt. Hope Process Overview

    Mt. Hope Process Overview [DA GBIERAL VEEN, ML per usa ow Ses | ny 24,2007

  29. Slide 29: Mt. Hope Mine Equipment

    Mt. Hope Mine Equipment » 3.Loading Units: ~43 yard electrically powered shovels > Schedule: First unit at start of pre-production; second unit at 2"¢ quarter of pre-production; third unit at 3 quarter of pre-production > Haul Trucks: ~240 ton capacity >» Schedule: Five units at start of pre-product

  30. Slide 30: Mt. Hope - Manpower and Housing

    Mt. Hope - Manpower and Housing 30

  31. Slide 31: Combined Total Project Manpower

    400 200 [mIGMiI Operating Personnel EIConstruction Personne! Combined Total Project Manpower Total Projected Site Personnel 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Months from Start of Construction

  32. Slide 32: Housing of Construction Labor

    Housing of Construction Labor cmoamex pans * Construction labor pool by origin: — 300 housed in man camp at Gale Ranch — 100 housed in motels and RV sites in and around Eureka — 400 commuting from Austin, Carlin, Elko & Ely — Optional shuttle bus service

  33. Slide 33: Housing of Operations Staff

    Housing of Operations Staff « Eureka Housing Development — 190 ¢ Third party housing developments — 20 * Atlas Mobile Home Park/ IGMl-owned - 35 « Eureka mobile home parks - 60 * Commuters from Austin, Carlin, Elko & Ely — 95 * Optional temporary housing in motels * Optional shuttle bus service 3 mb

  34. Slide 34: Eureka Housing Development

    Eureka Housing Development « Location: Annexed areas north and south of Eureka * 22 miles south of mine * 170 acres total * 230 lots total

  35. Slide 35: Mt. Hope - Permitting

    Mt. Hope - Permitting 35

  36. Slide 36: Major Permitting Requirements

    Major Permitting Requirements Plan of Operations Submittal — Submittal to Bureau of Land Management in September 2006 Air Quality Control Permit — Submittal to Nevada Division of Environmental Protection in Q3 2007 Water Pollution Control Permit — Submittal to Nevada Division of Water Resources in Q

  37. Slide 37: Mt. Hope Permitting Timeline

    Mt. Hope Permitting Timeline BaGaie —_[SvGnmr showin [ig nie GpsGate __[Sdoiedw_[aownte [tm unde wR an | em Sr Ne | Sor "Pwr Nats Se de | Se | San PM ———— eee —s (SaaS out: Share: lanka —— elt me ‘Ne Ft so Pad es rst ‘Reclamation Permit Bel te [a She

  38. Slide 38: Mt. Hope Permitting & Community Engagement

    Mt. Hope Permitting & Community Engagement * The site conditions at Mt Hope are notably conducive to permitting — there are no environmental show-stoppers. + Excellent relations with regulatory agencies and community of Eureka. « Experienced Community Relations Manager hired to ensure concerns of co

  39. Slide 39: Mt. Hope Water Supply Permitting Overview

    GMO:AMEX Geology limits groundwater movement Topography Limits Recharge Mt. Hope Water Supply Permitting Overview « Pit dewatering to be minimal given site hydrogeology « Hydrologic model to evaluate drawdown in region encompasses all or part of 5 hydrographic basins * 8 test wells drilled, 6 indica

  40. Slide 40: Roasting Facility Air Permitting Overview

    Roasting Facility Estimated Emission level to classify roaster as Class II (<100 tons/yr) Very minor natural amounts of mercury in ore body Dual Alkaline Scrubbers to reduce sulfur oxide emissions by 99%+ Relatively clean airshed Nevada history of permitting larger sources Class II Permit accommodat

  41. Slide 41: Mt. Hope - EPCM, Power and Long-Lead Items

    Mt. Hope - EPCM, Power and Long-Lead Items 4t

  42. Slide 42: EPCM Milestones

    Basic Engineering Starts Long-Lead Equipment Purchase Orders Detailed project schedule complete Control Budget Complete Basic Engineering Complete Construction Contract in place Machacek Substation Upgrades Complete Complete 70% of design and procurement Construction Begins Power Line and Plant Subs

  43. Slide 43: Long-Lead Items Purchase Schedule

    > Finalizing purchase of SAG Mill, Ball Mills and Shovels to be completed by end of Q4 2007. > 1 SAG Mill, 2 Ball Mills and 3 Shovels have the longest Lead Times. SEPT18 ——= Initial Meeting wiFFE SEPT 19 —— Initial Meeting wiMetso SEPT 24 ——= Initial Meeting w/ Thyssen Krupp SEPT 27 —— Initial Meeti

  44. Slide 44: MH Long Lead Item Schedule

    GMO:AMEX. MH Long Lead Item Schedule [Task Name Start Finish [2008 2009) 2070 Bot a4] at] aay a3] a4] ai] a2] a3] as] ai] a2] a3] a4] ar ‘SAG (order to ship) |SAG (Shipping and Assembiy) Ball Mill 7 (Order to Ship) Fri 10/5/07 Thu 11/5/08) Thu 11/5/09 Tue 5/4/10 Fri 10/5/07 Thu 11/5/08: Ball Mill 7

  45. Slide 45: Mt. Hope Electricity Supply

    Mt. Hope Electricity Supply Build 230 kV Power Line from Machacek Substation (Eureka) to Mount Hope v v This option is approved by Sierra Pacific Power and Mount Wheeler Planning for Engineering and Procurement are underway Secure Transmission Capacity into Machacek Substation v Verbal agreement has

  46. Slide 46: Mt. Hope - Economic Summary

    Mt. Hope - Economic Summary 46

  47. Slide 47: Mount Hope Economics

    Mount Hope Economics Price Forecast [ Project Year| Price Per Lb Yr $28.00 High Grade Ore (M tons) 703 vez | e240 Last3YrsAvg | $30.47 Low Grade Ore (M tons) 263 Yea | $10.50 i) Avg Price Frest | $14.92 Total Ore Milled (M tons) 966 Yrs | $46.00 - yr | $44.50 % Discount -51% Total Moly Recovered (M

  48. Slide 48: Hall-Tonopah

    Hall-Tonopah 48

  49. Slide 49: Hall-Tonopah Project

    Hall-Tonopah Project * Molybdenum and copper mineralization identified in the 1930's + 1955: Anaconda leased 9,000 acres of the “Hall” molybdenum mine to evaluate moly and copper resources + 1956 — 1966: Anaconda delineated mineralization of 200 million tons grading at 0.091% molybdenum. + Mine cons

  50. Slide 50: Hall-Tonopah Geology

    Hall-Tonopah Geology Hall-Tonopah Project + The orebody at Hall-Tonopah cylindrical, roughly coincident | with and draped across, the + igneous contact of a hh retaceous quartz porphyry stock and the metamorphosed 5 volcanic host rock. Te + The cylinder plunges -35° to i the southeast. + Molybdenite

  51. Slide 51: 2007 IGMI Drilling

    2007 IGMI Drilling * Completed 1: Round, Historic Assessment in Blue * Second Round, Model Verification in ¢ Third Round, Definition Drilling in Green Hall-Tonopah 2007 Drilling

  52. Slide 52: 2007 First Round Drilling Highlights

    cmo:amex >, Ces? 2007 First Round Drilling Highlights HT-781 460 825 365 0.2321 HT-782 505 615 110 0.1802 HT-783 215 530 315 0.1581 HT-782 50 245 195 0.1393 HT-765 190 550 360 0.1187 HT-776 295 665 370 0.1073 HT-679 5 530 525 0.1010 HT-777 370 610 240 0.0991 HT-780 5 250 250 0.0757

  53. Slide 53: Hall-Tonopah Phase Drilling Program 2007

    Hall - Tonopah Phase 1 Drilling Program 2007 “ ~ Cross - Section 35,500 Loouing = N meg 88 : e a 773 5,000 ef Mineralization Defined [im For MO% Less than 025. 2 3! ForMO%e Between 025 & 050 ForM%e Between 030 8 $00 ins For MO% Grenter Than 100

  54. Slide 54: Hall-Tonopah Geology

    Hall-Tonopah Geology QA/QC, Mapping, Drilling Ongoing Projects: Assay Quality Assurance/ Quality Control *High Wall Mapping Preparation for Phase 2 and 3 Drilling... Planned Drill hole #12— east of the Moly Pit.

  55. Slide 55: Deliverable

    Deliverable Evaluation of Existing Mine Data Engineering: -20% / +25% CapEx + 100 Drawings Third Party Economic Analysis Mining Pre-Feasibility Report (+/-20%Capex/Opex) * Block Model w/Geological Constraints * Mining Schedule w/Capex and Opex * Ni 43-101 Report (like Mount Hope’s) + _ TSF Capex and

  56. Slide 56: Hall-Tonopah Permitting Advantage

    Hall-Tonopah cmowmex “epsys” Permitting Advantage * Private lands; Opportunity to develop without extensive NEPA (EIS) evaluation * Significant, recent environmental analyses available « Recent mining disturbance reduces baseline surveys * Favorable socio-economic climate

  57. Slide 57: Preliminary Permitting Timeline

    Hall-Tonopah Preliminary Permitting Timeline 1 [rask name T Yeart 7 a o 3 2 a le g IMing Pian Process Design (Data Reviewr lAgency Meeting [Air Quality Permit, Meteorological Baseline Emissions Inventory & Modeling Air Permit Application ‘Agency Review & Approval Water Pollution Control Permit Hydro

  58. Slide 58: Pre-Feasibility Update

    Hall-Tonopah cmoumex Pre-Feasibility Update >» Mine Design (22,046 stpd ore) > Preliminary assessment 100% completed, 334 million tons ore at 0.076% Mo (46 years) » New block model 85% complete, MoOx check in progress, mining schedule in progress (tons and grade similar to preliminary assessment) >»

  59. Slide 59: Pre-Feasibility Update

    Hall-Tonopah GMO:AMEX Pre-Feasibility Update > Tailings Storage Facility Design » Design criteria 95% complete, awaits IGMI review, due Sep 19 » Geotechnical investigation report 75% complete, due Oct 5 » Preliminary design drawings 25% complete, due Oct 19 > Quantity and cost estimate 15% complete,

Idaho General Mines — Investor Presentation (September 2007) on 6ix