  1. Slide 1: Vale's Performance in 3Q20

    Loading ship at Ponta da Madeira Maritime Port, São Luís, MA, Brazil. Vale’s Performance in 3Q20 Rio 1 de Janeiro, October 29th, 2020

  2. Slide 2: Opening remarks

    Opening remarks 2

  3. Slide 3: We are delivering on the Integral Reparation Plan

    3 We are delivering on the Integral Reparation Plan US$ 2.6 billion ininreparation individualactions¹ indemnifications² +8,200 people indemnified² in environmental reparation US$ 470 million (e.g. Ground Zero) Brumadinho’s Master Plan Built on extensive listening to communities, submitted to the aut

  4. Slide 4: In tailings management, quickly moving towards full adherence to ICMM standards

    4 In tailings management, quickly moving towards full adherence to ICMM standards Our ambition world-class in individual standards indemnifications² and processes Routine ▪ New ICMM standard – minor gaps. Full System Performance implementation expected for 2021 Risk ▪ New TMS ▪ Hazard Identification

  5. Slide 5: We are closing our ESG gaps

    5 We are closing our ESG gaps 52 gaps mapped inwith individual actionindemnifications² plans For further information, visit www.vale.com/esg 31 gaps closed since 2019 In 2020, 5 gaps already solved ✓ More disclosure on management compensation ✓ Audit committee ✓ Tax Transparency Report ✓ Creation of

  6. Slide 6: We are performing with record production in the Northern System

    6 We are performing with record production in the Northern System… 56.9 Mt Northern System All-time production record 24.4 Mt S11D All-time production record US$ 5.856 billion Record EBITDA in Ferrous Minerals since 4Q13 US$ 6.224 billion Record EBITDA since 1Q14 6

  7. Slide 7: … while increasing production capacity and strengthening our supply chain

    7 … while increasing production capacity and strengthening our supply chain Serra Sul 120 Mtpy Project Adding 20 Mtpy to S11D mine-plant capacity ✓ Buffer of productive capacity ✓ US$ 1.5 billion investment Project West III Adding +20 Mtpy to the Shulanghu Port capacity¹ ✓ Through JV ✓ US$ 100-150 m

  8. Slide 8: We are de-risking Vale

    8 We are de-risking Vale Keeping a fast pace and quality at Brumadinho’s reparation Becoming one of the safest and most reliable mining companies Resuming production under safe conditions Focusing on discipline in capital allocation 8

  9. Slide 9: Iron Ore Business

    Iron Ore Business 9

  10. Slide 10: Operations are progressing on stabilization and resumption

    10 Operations are progressing on stabilization and resumption roadmap from Analyst & Investor Tour is on track 2020 production (Mt) 3Q20 • Record in Northern System and S11D • Solid production in Southern and Southeastern Systems 89 60 68 4Q20 • Expect to sustain robust production rates • Risks rela

  11. Slide 11: Vale recovered its operational flexibility, reducing major sales variation looking forward

    11 Vale recovered its operational flexibility, reducing major sales variation looking forward 1 BRBF is Vale’s main product 3 Operational inventories needed BRBF sales 2020 2019 ~145Mt of operational inventories 14 Mt drew down 2017 94Mt 9M20 Margin over volume strategy and portfolio optimization of

  12. Slide 12: 12

    12

Vale — Q3 2020 Earnings Presentation on 6ix