Slide 1: Construction of Gas Interconnection Poland–Lithuania in the Territory of the Republic of Lithuania (GIPL)
Draft of conditions Construction of Gas Interconnection Poland–Lithuania in the Territory of the Republic of Lithuania (GIPL) April 2018
Slide 2: Table of contents
Draft of conditions Table of contents 1. Procured works 2. Procurement procedure 3. Requests to participate 4. Qualification requirements 5. Right to perform works in Lithuania 6. Initial tenders 7. Negotiations 8. Final tenders 9. Tender evaluation criteria 10. Award of the contract
Slide 3: Interconnection Poland-Lithuania (GIPL)
Interconnection Poland-Lithuania (GIPL) Draft of conditions e Ryga Kieménai LATVIA Klaipeda LNG terminal RUSSIA tal POLAND / BELARUS \ Warszawa N e Hotoncye Ambe Grid
Slide 4: Projected Gas Pipeline Route
Construction of Gas Interconnection Poland–Lithuania in the Territory of the Republic of Lithuania (GIPL) Draft of conditions Projected Gas Pipeline Route Projected length of the route is about 165 km and the diameter is DN700. According to the engineering design, the projected gas pipeline will run
Slide 5: Description of the prospective Gas Transmission Pipeline
Construction of Gas Interconnection Poland–Lithuania in the Territory of the Republic of Lithuania (GIPL) Draft of conditions Description of the prospective Gas Transmission Pipeline 1) MAOP between Jauniūnai DKS and DASRS is 5.4 Mpa; 2) MAOP between DASRS and the state (LT/PL) border is 8.4 MPa; 3)
Slide 6: Interconnections between the Gas Pipeline and Utility Lines
Construction of Gas Interconnection Poland–Lithuania in the Territory of the Republic of Lithuania (GIPL) Draft of conditions Interconnections between the Gas Pipeline and Utility Lines The projected gas pipeline will have 9 intersections with the existing gas pipelines, 3 intersections with pressur
Slide 7: Interconnections between the Gas Pipeline and Water Bodies
Construction of Gas Interconnection Poland–Lithuania in the Territory of the Republic of Lithuania (GIPL) Draft of conditions Interconnections between the Gas Pipeline and Water Bodies The projected gas transmission pipeline will cross two major rivers: - The Neris River as one thread (about 500 m);
Slide 8: The Neris River
Construction of Gas Interconnection Poland–Lithuania in the Territory of the Republic of Lithuania (GIPL) Draft of conditions Interconnections between the Gas Pipeline and Water Bodies The Neris River 8
Slide 9: The Nemunas River
Construction of Gas Interconnection Poland–Lithuania in the Territory of the Republic of Lithuania (GIPL) Draft of conditions Interconnections between the prospective Gas Transmission Pipeline and Water Bodies The Nemunas River 9
Slide 10: Stages of Construction
No 1, STAGES OF CONSTRUCTION Jauniūnai DKS Draft of conditions Stage I No 6 Stage II No 10 Stage III No 13 Stage IV DASRS 10
Slide 11: Construction Stages
CONSTRUCTION STAGES Draft of conditions Stage I: line block valve sites No 1/Jauniūnai DKS÷6 73 km - 30 September 2020 but not earlier than by 1 March 2020. Stage II: valve sites No 6÷10 30 km - 31 December 2020 but not earlier than by 1 June 2020. Stage III: valve sites No 10÷13 26 km - 30 June 202
Slide 12: Works to be procured: Scope of Works (I)
Works to be procured Scope of Works (I) Draft of conditions • AB „Amber Grid“ will provide with the following supplies of coated steel pipes required for the performance of Works: External diameter (mm) Wall thickness (mm) Steel Quantity (m) • supplier 711 (HDD sections) 12.5 L415 ME 3000 711 8.0 L4
Slide 13: Works to be procured (2)
Works to be procured (2) Draft of conditions The components of the price for the object of procurement – construction works for the part of gas interconnection Poland-Lithuania in the territory of the Republic of Lithuania – are as follows: The components of the price for the object of procurement.d
Slide 14: Procurement procedure
Procurement procedure Negotiated procedure with prior contract notice Draft of conditions Requests Initial Negotiat Final Confirmat tenders ions tenders ion Award of contract submission – approx. submissio Submission To be concluded: 60 days n – 30 – approx. 7 Actual - Upon expiry of the days days d
Slide 15: Requests for participation in the Tender
Requests for participation in the Tender Preliminary requirements Draft of conditions • In order to be invited to submit an initial tender the supplier shall submit request to participate in the tender and : o A filled out and signed European Single Procurement Document (ESPD) filled by all consorti
Slide 16: ESPD
ESPD Coverage and provision of documents Draft of conditions • European Single Procurement Document (ESPD) is a self-declaration of the businesses' financial status, abilities and eligibility for a public procurement procedure. • By submitting ESPD, the contractor will self declare the compliance to
Slide 17: Exclusion grounds
Exclusion grounds Draft of conditions • Judgement or criminal conviction in the course of past 5 years for the specified activities • Judgement or conviction in the course of past 5 years for failure to pay taxes, including social insurance contributions or the supplier fails to pay taxes, including
Slide 18: Exclusion grounds (2)
Exclussion grounds (2) Draft of conditions • Supplier has consealed information or provided false information on compliance or has failed to provide documentary evidence during this procedure or has been excluded during previous procedures • Unlawfull actions taken to influence the contracting entit
Slide 19: Qualification requirements
Qualification requirements General Qualification Requirements Draft of conditions 1. Certified licence to be a contractor for the construction of a structure of exceptional significance and carry out construction works (installation) of transmission gas pipelines 2. The supplier shall have the right
Slide 20: Qualification requirements (2)
Qualification requirements (2) Requirements for economic and financial state Draft of conditions 1. Average annual turnover from all activites during last 3 financial years is at least EUR 30 000 000 2. Current liquidity ratio for the last financial year (ratio of current assets and short term liabi
Slide 21: Qualification requirements (3)
Qualification requirements (3) Technical and professional capacity requirements Draft of conditions During the last 5 years the supplier shall have properly performed at least: 1. 1 but not more than 3 contracts with total value of at least EUR 15 million under which at least 1 main gas pipeline was
Slide 22: Qualification requirements (4)
Qualification requirements (4) Technical and professional capacity requirements (II) Draft of conditions Shall have and propose at least the following specialists: 1. 1 construction manager of a structure of exceptional significance, qualified in the area of construction of main gas pipelines and eq
Slide 23: Qualification requirements (5)
Qualification requirements (5) Technical and professional capacity requirements (III) Draft of conditions Shall have and propose at least the following specialists: 4. 1 design manager, qualified in the area of design of transmission gas pipelines and their installations (structures: engineering net
Slide 24: Qualification requirements (6)
Qualification requirements (6) Technical and professional capacity requirements (IV) Draft of conditions Shall have and propose at least the following specialists: 6. 1 manager of a part of the engineering design, qualified in the area of the design of transmission gas pipelines and their installati
Slide 25: Qualification requirements (7)
Qualification requirements (7) Technical and professional capacity requirements (V) Draft of conditions Shall have and propose at least the following specialists: 7. 2 qualified work superintendents, who have the right to manage the work of the construction of natural gas transmission system pipelin
Slide 26: Right to perform works in Lithuania
Right to perform works in Lithuania Draft of conditions Right for foreign suppliers to perform construction and engineering design works in Lithuania Suppliers from the EU States and Switzerland shall obtain documents proving the right to perform construction or design works in Lithuania (i) by impl
Slide 27: Right to perform works in Lithuania (2)
Right to perform works in Lithuania (2) Right of foreign specialists to perform construction and design works in Lithuania (II) Draft of conditions In order to recognise their rights to perform respective construction or design works the Contractor (legal person) has to submit: 1. A written applicat
Slide 28: Rights to perform works in Lithuania (3)
Rights to perform works in Lithuania (3) Rights of foreign specialists to perform construction and design works in Lithuania (III) Draft of conditions In order to recognise their rights to perform construction or design works the Contractor‘s specialists will have to: 1. Submit a written application
Slide 29: Right to perform works in Lithuania (4)
Right to perform works in Lithuania (4) Right to carry out works for the testing of the transmission gas pipeline and near an operating transmission gas pipeline Draft of conditions In order to obtain right to to carry out works for the testing and rapairing of the transmission gas pipeline the Cont
Slide 30: Right to perform works in Lithuania (5)
Right to perform works in Lithuania (5) Right to carry out works for the testing of the transmission gas pipeline and near an operating transmission gas pipeline (II) Draft of conditions In order to perform works near an operating transmission gas pipeline, the specialists must obtain certificates o
Slide 31: Initial tenders
Initial tenders Intended requirements Draft of conditions • Only the suppliers who submitted compliant requests and meet the qualification requirements, shall be invited to submit initial tenders • Tender security of EUR 1 million shall be provided together with the initial tender
Slide 32: Negotiations
Negotiations Tentative requirements list Draft of conditions • The suppliers, who have submitted initial requests in compliance with the requirements, shall be invited to the negotiations • AB “Amber Grid” will be entitled to negotiate any terms of procurement save for: − compliance of the works, ma
Slide 33: Final proposals
Final proposals Intended requirements Draft of conditions • Upon completion of the negotiations, the suppliers which have not been dismissed shall be invited to submit their final tenders • The terms and conditions of the final tender shall not be worse than those fixed in the initial tender and min
Slide 34: Proposal evaluation criteria
Proposal evaluation criteria Draft of conditions Evaluation criteria for the most economically advantageous tender Criterion Weight Price 84 Efficiency of the project management plan 15 Salary for contract staff 1 The plan shall cover the following matters (generalized): − team of the proposed speci
Slide 35: Award of the procurement contract
Award of the procurement contract Intended requirements (II) Draft of conditions • Procurement contract shall be awarded to the supplier whose final proposal has the best price-quality ratio • Procurement contract shall be awarded : − Upon expiry of the postponement term − Upon receipt of the approv
Slide 36: Implementation of the GIPL project in the territory of Lithuania
Implementation of the GIPL project in the territory of Lithuania Draft of conditions Scheduled Task Name Start Finish Duration Implementation of the GIPL project in the territory of Lithuania Mon 17.05.08 Fri 21.12.31 1215 days? Publication of a Public Tender Notice for the procurement of Works Tue