  1. Slide 1: UBS Electric Power Conference

    Slide 1: UBS Electric Power Conference

    2012 UBS Electric Power Conference UBS Electric Power Conference February 29, 2012 Dallas, TX Exhibit 99.1

  2. Slide 2: Forward Looking Disclosures

    Slide 2: Forward Looking Disclosures

    2 2012 UBS Electric Power Conference Forward Looking Disclosures Forward-looking statements: Certain matters discussed in this presentation are “forward- looking statements.” The Private Securities Litigation Reform Act of 1995 has established that these statements qualify for safe harbors from liab

  3. Slide 3: Recent Events

    Slide 3: Recent Events

    3 2012 UBS Electric Power Conference Rate request settlement filed ($50 million rate increase) Priced $250 million First Mortgage Bond 2011 results $1.95 per share; ongoing earnings $1.81 per share Dividend increased to $0.33 per share, 3% increase 2012 EPS guidance range $1.85 - $2.00 per share 201

  4. Slide 4: 2011 General Rate Request

    Slide 4: 2011 General Rate Request

    4 2012 UBS Electric Power Conference Provisions of Settlement filed in February include: – Annual retail revenue increase $50 million, effective May – $11 million annual increase in tree trimming expense – $33 million annual increase in pension expenses – $40 million annual lower depreciation expens

  5. Slide 5: First Mortgage Bond Offer

    Slide 5: First Mortgage Bond Offer

    5 2012 UBS Electric Power Conference Priced $250 million FMB Coupon 4.125% 30 year maturity, due March 2042 Use of Proceeds – provide long-term funding of investment in infrastructure Planned closing March 1, 2012 First Mortgage Bond Offer

  6. Slide 6: 2011 Ongoing EPS Results Unchanged From 2010

    Slide 6: 2011 Ongoing EPS Results Unchanged From 2010

    6 2012 UBS Electric Power Conference EPS from continuing operations of $1.81 vs. $1.81 for 2010 Retail MWh sales increased 1% – Warmer than normal weather, modestly above 2010 – Continued signs of industrial growth – 2% over 2010 Implemented all planned price adjustments (annualized amts): – Transmi

  7. Slide 7: 2012 Earnings Guidance of $1.85 - $2.00

    Slide 7: 2012 Earnings Guidance of $1.85 - $2.00

    7 2012 UBS Electric Power Conference KCC approval of Stipulation & Agreement (S&A) in rate review – Annual retail revenue increase $50 million, effective May Planned price adjustments via tracking mechanisms Expect weather-adjusted retail sales to grow 1% Combined O&M and SG&A (excl. SPP costs) incr

  8. Slide 8: Capital Expenditure Forecast 2012 - 2014

    Slide 8: Capital Expenditure Forecast 2012 - 2014

    8 2012 UBS Electric Power Conference Capital Expenditure Forecast 2012 - 2014 Actual Forecast Forecast Forecast Forecast Method of Cost 2011 2012 2013 2014 2012 - 2014 Recovery Generation replacements and other 132.8 $ 159.8 $ 172.3 $ 164.6 $ 496.7 $ GRC Westar environmental 153.4 219.3 121.8 107.4

  9. Slide 9: Environmental Rules

    Slide 9: Environmental Rules

    9 2012 UBS Electric Power Conference Mercury and Air Toxics Standards (MATS) – Final rule issued February 2012 – Not viewed as problematic Reasonable time for compliance Compliance viewed as additive to current environmental plans Projected investment up to $40 million Cross-States Air Pollution Rul

  10. Slide 10: 2012 Plans

    Slide 10: 2012 Plans

    10 2012 UBS Electric Power Conference 2012 Plans

  11. Slide 11: Annualized Rate & Revenue Changes

    Slide 11: Annualized Rate & Revenue Changes

    11 2012 UBS Electric Power Conference Annualized Rate & Revenue Changes Actual and Estimated 2011 2012 (Estimated) 2013 (Estimated) Base rates $50 million May Transmission rates (a) $17 million Jan 1 $25 million Jan 1 $17 million Jan 1 ECRR $10 million June 1 $15 million June 1 $27 million June 1 En

  12. Slide 12: Major Construction Projects Underway

    Slide 12: Major Construction Projects Underway

    12 2012 UBS Electric Power Conference Major Construction Projects Underway Air Quality Improvements – Lawrence Energy Center Fabric filters, rebuild scrubbers, precipitator, low NOx system – Jeffrey Energy Center SCR on 1 unit – La Cygne Energy Center Scrubbers, fabric filters, common chimney, SCR a

  13. Slide 13: Capital Expenditure Forecast 2012 - 2014

    Slide 13: Capital Expenditure Forecast 2012 - 2014

    13 2012 UBS Electric Power Conference Capital Expenditure Forecast 2012 - 2014 Actual Forecast Forecast Forecast Forecast Method of Cost 2011 2012 2013 2014 2012 - 2014 Recovery Generation replacements and other 132.8 $ 159.8 $ 172.3 $ 164.6 $ 496.7 $ GRC Westar environmental 153.4 219.3 121.8 107.4

  14. Slide 14: Capital Expenditure Forecast 2012 - 2014

    Slide 14: Capital Expenditure Forecast 2012 - 2014

    14 2012 UBS Electric Power Conference Capital Expenditure Forecast 2012 - 2014 $0 $100 $200 $300 $400 $500 $600 $700 $800 $900 $1,000 2011 2012 2013 2014 $697 $871 $875 $713 Air Quality Other Transmission 43% 37% 41% 49% La Cygne

  15. Slide 15: Projected Rate Base 2010 - 2015

    Slide 15: Projected Rate Base 2010 - 2015

    15 $3.4 $3.8 $4.1 $4.3 $4.4 $4.4 2012 UBS Electric Power Conference Projected Rate Base 2010 – 2015 (in billions) 2011 2012 2013 2014 2015 2016 Base Air Quality Transmission $6.9 $6.7 $6.5 $6.0 $5.4 $4.8 $0.8 $0.9 $1.1 $1.3 $1.4 $1.6 $0.6 $0.7 $0.8 $0.9 $0.9 $0.9

  16. Slide 16: Environmental

    Slide 16: Environmental

    16 2012 UBS Electric Power Conference Environmental

  17. Slide 17: Environmental Regulation Summary

    Slide 17: Environmental Regulation Summary

    17 Cross-State Air Pollution Rule Mercury and Air Toxics Standards Water 316(b) Coal Combustion Waste 2012 UBS Electric Power Conference Status Stayed by DC Circuit Court Published February 2012 Proposed Proposed Effective Pending Court Decision April 2012 (3 to 5 years to comply) July 2012 Mid 2013

  18. Slide 18: Mercury and Air Toxics Standards (MATS)

    Slide 18: Mercury and Air Toxics Standards (MATS)

    18 2012 UBS Electric Power Conference Rule issued February 2012 Westar does not view as problematic – No surprises in final rule – Allow three years for compliance Opportunity for one additional year – View as additive to current environmental plans Incorporated anticipated rules in current complian

  19. Slide 19: Dramatic Improvement in Air Quality

    Slide 19: Dramatic Improvement in Air Quality

    19 2012 UBS Electric Power Conference Dramatic Improvement in Air Quality Actual Projected Actual Projected Nitrogen Oxide 57% (tons per year) Sulfur Dioxide 83% (tons per year) 10,000 20,000 30,000 40,000 50,000 60,000 70,000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 201

  20. Slide 20: Westar Coal Fleet Emission Control Equipment

    Slide 20: Westar Coal Fleet Emission Control Equipment

    20 2012 UBS Electric Power Conference Westar Coal Fleet Emission Control Equipment Unit Scrubber Precipitator Fabric Filter Low NOx SCR ACI DSI Jeffrey 1 Yes Yes No plans Yes Planned Planned No plans Jeffrey 2 Yes Yes No plans Yes Uncertain Planned No plans Jeffrey 3 Yes Yes No plans Yes No plans Pl

  21. Slide 21: Air Quality Controls

    Slide 21: Air Quality Controls

    21 2012 UBS Electric Power Conference Air Quality Control Targeted Emission / Benefit Low NOx Burner Systems NOx Selective Non-Catalytic Reduction NOx Selective Catalytic Reduction NOx Scrubber SO Acid gases Small amount of mercury Baghouse Particulate matter Small amount of mercury Metals Electrost

  22. Slide 22: Transmission

    Slide 22: Transmission

    22 2012 UBS Electric Power Conference Transmission

  23. Slide 23: Major Transmission Investments Underway

    Slide 23: Major Transmission Investments Underway

    23 2012 UBS Electric Power Conference Major Transmission Investments Underway Rose Hill – Oklahoma Under construction Target completion Apr 2012 Investment n $80 million Favorable to budget Prairie Wind Transmission 50/50 JV with ETA Siting approved June 2011 Acquiring ROW and clearing Begin constru

  24. Slide 24: Prairie Wind Transmission Regulation

    Slide 24: Prairie Wind Transmission Regulation

    24 2012 UBS Electric Power Conference Prairie Wind Transmission Regulation Received FERC incentives – Recovery of pre-commercial development costs – CWIP recovery in rate base – Allowed ROE of 12.8% KCC – Siting approved June 2011 Southwest Power Pool – Regional cost allocation approved by FERC – “N

  25. Slide 25: Potential for High Voltage Transmission Growth

    Slide 25: Potential for High Voltage Transmission Growth

    25 2012 UBS Electric Power Conference Potential for High Voltage Transmission Growth A. JEC to Iatan Energy Center B. Wolf Creek to Swissvale C. Concordia to Salina D. Salina to Hays E. JEC to Swissvale F. Hutchinson to Spearville G. Wichita to Rose Hill H. JEC to Concordia F G A B C E D H

  26. Slide 26: Profile

    Slide 26: Profile

    26 2012 UBS Electric Power Conference Profile

  27. Slide 27: Strategic Approach

    Slide 27: Strategic Approach

    27 2012 UBS Electric Power Conference Strategic Approach Embrace uncertainty – Acknowledge inability to predict the future Value flexibility – Operational – Financial – Regulatory Leverage actions and strategies around intrinsic advantages Seek collaborative and constructive approaches to regulation

  28. Slide 28: Regulatory Approach

    Slide 28: Regulatory Approach

    28 2012 UBS Electric Power Conference Regulatory Approach A sound regulatory and energy policy platform – KCC and FERC Ultimately results in lower rates for customers

  29. Slide 29: Favorable Supply Portfolio

    Slide 29: Favorable Supply Portfolio

    29 2012 UBS Electric Power Conference Favorable Supply Portfolio $52.65 $19.30 $7.15 Uranium Coal Gas Ave. Fuel Cost $20.60/MWh Fuel Mix Coal 49% Gas 39% Wind 4% Uranium 8% MW Capacity 5.0¢ 6.0¢ 7.0¢ 8.0¢ 9.0¢ 10.0¢ Westar Energy Kansas City Power and Light (KS) Empire District Electric (KS) Nationa

  30. Slide 30: Diverse Energy Sales (MWh)

    Slide 30: Diverse Energy Sales (MWh)

    30 2012 UBS Electric Power Conference Diverse Energy Sales (MWh) Chemical & oil Food processing Aerospace Consumer manufacturing Other Commercial 37% Residential 35% Industrial 28% 40% 17% 15% 16% 12% 12% 18% 8% 7% 3% 4% 48% Other General merchandise Grocery/ Convenience Real estate Health care Gove

  31. Slide 31: Strong Service Territory

    Slide 31: Strong Service Territory

    31 2012 UBS Electric Power Conference Strong Service Territory Economy significantly stronger than for the nation – No real estate crash – Unemployment remains 2+ pts favorable to nation Economic development gains fueling industrial resurgence – Sales up 2% 12me Dec ‘11 – EcoDevo successes: Mars Cho

  32. Slide 32: Liquidity and Capitalization

    Slide 32: Liquidity and Capitalization

    32 2012 UBS Electric Power Conference Liquidity and Capitalization Target n 50/50 capital structure Debt 47% Equity 52% Preferred <1% Dec. 31, 2011 (a) (millions) Long-term, net $2,491 Preferred Common 2,769 Total Capitalization $5,281 (a) Capitalization excludes short-term debt and adjustments for

  33. Slide 33: Dividend

    Slide 33: Dividend

    33 2012 UBS Electric Power Conference $0.92 $1.00 $1.08 $1.16 $1.20 $1.24 $1.28 $1.32 $0.75 $0.85 $0.95 $1.05 $1.15 $1.25 $1.35 2005 2006 2007 2008 2009 2010 2011 2012 Dividend Quarterly dividend increased 3% effective April 1 Long-standing dividend payout target of 60%-75% of earnings – 2012 guidan

  34. Slide 34: Westar's Value Proposition

    Slide 34: Westar's Value Proposition

    34 2012 UBS Electric Power Conference Westar’s Value Proposition Solid, transparent business strategy Strong, experienced utility management team Thoughtful, disciplined approach to operations, capital planning and financing Constructive regulatory and policy environment – Results in lower, more gra

  35. Slide 35: Rates and Regulation

    Slide 35: Rates and Regulation

    35 2012 UBS Electric Power Conference Rates and Regulation

  36. Slide 36: Kansas Regulators

    Slide 36: Kansas Regulators

    36 2012 UBS Electric Power Conference Kansas Corporation Commission – Three-member board appointed by governor Serve staggered four year terms Current KCC commissioners – Mark Sievers (R), chairman Term expires March 2015 – Thomas Wright (D) Term expires March 2014 – Ward Loyd (R) Term expires March

  37. Slide 37: Regulatory Approach

    Slide 37: Regulatory Approach

    37 2012 UBS Electric Power Conference Regulatory Approach A sound regulatory and energy policy platform – KCC and FERC Ultimately results in lower rates for customers

  38. Slide 38: Methods of Cost Recovery

    Slide 38: Methods of Cost Recovery

    38 2012 UBS Electric Power Conference Methods of Cost Recovery Revenue Requirement Method of Recovery Comment 1. Fuel, purchased power and environmental consumables Quarterly adjustment based on forecasted cost, with annual true-up Adjusts prices for actual costs, protecting both customers and inves

  39. Slide 39: Retail Energy Cost Adjustment (RECA)

    Slide 39: Retail Energy Cost Adjustment (RECA)

    39 2012 UBS Electric Power Conference Retail Energy Cost Adjustment (RECA) Provides timely price adjustments for fuel and purchased power costs Retail rates based on forecast of fuel and purchased power costs and retail sales – Set quarterly – Difference between forecast and actual is deferred Quart

  40. Slide 40: Pension Tracker

    Slide 40: Pension Tracker

    40 2012 UBS Electric Power Conference Pension Tracker Defer as regulatory asset shortfall between funding of GAAP pension/OPEB expense and pension/OPEB currently authorized in rates Maintain minimum funding level equal to GAAP pension/OPEB expense Recover deferred expenses through multi-year amortiz

  41. Slide 41: Environmental Cost Recovery Rider Mechanics

    Slide 41: Environmental Cost Recovery Rider Mechanics

    41 2012 UBS Electric Power Conference Environmental Cost Recovery Rider Mechanics ECRR adjusts retail rates annually to reflect capital investments in emission controls – Investments as of December 31 recovered in rates subsequent June – Eliminates need to file a rate case to capture rate base addit

  42. Slide 42: Illustrative ECRR Mechanics

    Slide 42: Illustrative ECRR Mechanics

    42 2012 UBS Electric Power Conference Illustrative ECRR Mechanics (1) Illustration reflects only the projects publicly announced and assumes one-half of annual investment in service at year end (2) Illustration uses n 11.9% pretax return and 4% depreciation recovery (3) Annual ECRR Tariff is effecti

  43. Slide 43: Transmission Cost Recovery

    Slide 43: Transmission Cost Recovery

    43 2012 UBS Electric Power Conference Transmission Cost Recovery FERC formula transmission rate – Changes in cost of service reflected in annual update of FERC tariff Update posted each October using projected test year – Capital expenditures – O&M – Tariff based on year-end consolidated capital str

  44. Slide 44: Transmission Formula Rate Mechanics

    Slide 44: Transmission Formula Rate Mechanics

    44 2012 UBS Electric Power Conference Transmission Formula Rate Mechanics Fixed formula with changing inputs – Updated annually using Form 1 data – Established protocols for updates Uses projected test year – Rate base (based on 13 month average) – O&M, depreciation and taxes – Cost of debt Annual t

  45. Slide 45: Energy Efficiency Initiatives

    Slide 45: Energy Efficiency Initiatives

    45 2012 UBS Electric Power Conference Energy Efficiency Initiatives SmartStar Lawrence smart grid project – Installing 48,000 “smart” meters – Advanced outage management system – Total project cost of $40 million Reduced by 50% DOE match – Expect to implement over 2 - 3 years Deferred accounting for

  46. Slide 46: Kansas' Renewable Requirements

    Slide 46: Kansas' Renewable Requirements

    46 2012 UBS Electric Power Conference Kansas’ Renewable Requirements Renewable Portfolio Standard established – Installed capability standard in lieu of energy standard 10% of peak load by 2011, 15% by 2016 and 20% after 2020 – If generated in Kansas, treated at 110% of requirement – Relief from sta

  47. Slide 47: Addition of Renewables in 2012

    Slide 47: Addition of Renewables in 2012

    47 2012 UBS Electric Power Conference Statute requires 200 MW additional renewables by 2011 – KCC approved use of RECs to satisfy 2011 requirement until projects placed in-service in late 2012 KCC approved request for 370 MW through PPAs – Agreements for 2 projects Post Rock Wind Farm - 201 MW Ironw

  48. Slide 48: Westar Renewables Compliance

    Slide 48: Westar Renewables Compliance

    2012 UBS Electric Power Conference 48 Westar Renewables Compliance Favorable pricing allowed for head start on 2016 statute requirements KCC allowed the 2011 statute requirement to be satisfied with Renewable Energy Credits

  49. Slide 49: Statutes for Predetermination and CWIP

    Slide 49: Statutes for Predetermination and CWIP

    49 2012 UBS Electric Power Conference Statutes for Predetermination and CWIP Predetermination – Utilities can obtain order establishing ratemaking principles that will apply over the life of the asset Construction Work in Progress (CWIP) – Utilities can include CWIP in rate cases

  50. Slide 50: Capital Structure for Ratemaking (Per Recent Orders)

    Slide 50: Capital Structure for Ratemaking (Per Recent Orders)

    50 2012 UBS Electric Power Conference Capital Structure for Ratemaking (Per Recent Orders) Capitalization Ratio Cost of Capital Weighted Cost of Capital Pre-tax Weighted Cost of Capital Long-term debt 48.66% 6.55% 3.19% 3.19% Preferred 0.51 4.55 .02 .04 Common 50.83 10.40 5.29 8.77 100.00% 8.50% 12.

  51. Slide 51: Capital Structure for Ratemaking (Proposed)

    Slide 51: Capital Structure for Ratemaking (Proposed)

    51 2012 UBS Electric Power Conference Capital Structure for Ratemaking (Proposed) Capitalization Ratio Cost of Capital Weighted Cost of Capital Pre-tax Weighted Cost of Capital Long-term debt 46.97% 6.65% 3.12% 3.12% Preferred 0.40 4.55 .02 .03 Common 52.63 10.00 5.26 8.71 100.00% 8.40% 11.86% KCC (

  52. Slide 52: Abbreviated (Limited Scope) Rate Case (ARC)

    Slide 52: Abbreviated (Limited Scope) Rate Case (ARC)

    52 2012 UBS Electric Power Conference Obtain permission from KCC to file ARC – Request made in a general rate case (GRC) – Identify scope of proposed ARC Must file within 12 months of final GRC order Applicant must adopt from previous rate order: – All regulatory procedures – All regulatory principl

  53. Slide 53: Background

    Slide 53: Background

    53 2012 UBS Electric Power Conference Background

  54. Slide 54: Westar Energy Legal Structure

    Slide 54: Westar Energy Legal Structure

    54 2012 UBS Electric Power Conference Westar Energy Legal Structure Kansas Gas and Electric Company Consolidated capital structure is used for ratemaking (Rate regulated utility) (Rate regulated utility) Westar Energy, Inc. Parent Subsidiary Combined company does business under the name “Westar Ener

  55. Slide 55: Westar's Generating Resources

    Slide 55: Westar's Generating Resources

    55 2012 UBS Electric Power Conference Westar’s Generating Resources Indicates proposed facility

  56. Slide 56: Westar's Plants

    Slide 56: Westar's Plants

    56 2012 UBS Electric Power Conference Westar’s Plants Westar's MW Operator Years Installed Pulverized coal Jeffrey Energy Center 2,005 Westar 1978, 1980, 1983 Lawrence Energy Center Westar 1954, 1960, 1971 Tecumseh Energy Center Westar 1957, 1962 LaCygne Station KCPL 1973, 1977 Nuclear Wolf Creek WC

  57. Slide 57: Low-Cost Coal Fleet

    Slide 57: Low-Cost Coal Fleet

    57 2012 UBS Electric Power Conference Low-Cost Coal Fleet Very low fuel cost – PRB coal – Excellent rail arrangements – Proximity to mines Low embedded capital cost No high-heat rate obsolete plants LAC 2 subject to lease agreement $0 $150 $300 $450 $600 JEC JEC JEC LEC LAC LAC TEC LEC TEC LEC Low E

  58. Slide 58: Westar Energy Coal Fleet

    Slide 58: Westar Energy Coal Fleet

    58 2012 UBS Electric Power Conference Westar Energy Coal Fleet Unit Capacity (MW) WR Share (MW) Age Heat Rate (Btu/kWh) Net Book Value (Millions) $/KW Jeffrey 3 11,265 $ $ Jeffrey 2 11,256 $ $ Jeffrey 1 11,204 $ $ Lawrence 5 10,713 $ $ La Cygne 1 10,497 $ $ La Cygne 2 (a) 10,500 $ $ Tecumseh 8 11,18

  59. Slide 59: Coal Supply

    Slide 59: Coal Supply

    59 2012 UBS Electric Power Conference Westar-operated plant fuel supply (80%) JEC supply under contract through 2020 (10+ million tons/year) – 70% has no market openers – 30% reopened on price every 5 years Next re-pricing will occur in 2013 – All volumes have cost escalators – Rail contract through

Source: SEC EDGAR · 8-K filed Feb 28, 2012