British Land Company PLC · LSE:BLND

British Land — Corporate Update (February 2022)

23 slides from British Land's corporate update, Feb 9, 2022

  1. Slide 1: Canada Water Development Construction Liaison Forum

    Canada Water Development Construction Liaison Forum Plots Al & A2 (and surrounding area) 9 February 2022

  2. Slide 2: Overview of tonight's presentation

    * Introductions + Jobs and training opportunities * Keeping you informed * Canada Water development * Construction management Ove rview of * Canada Dock to nig ht ’ Ss + Updates from contractors G - Construction of Plot A2 (Mace) presentation - Construction of Plot Al (Wates) * Q&A

  3. Slide 3: Our presenters

    Our presenters SARAH WARD Construction Neighbour Liaison Manager MICHAEL DELFS British Land lead for Canada Dock OLLY MACK DANIEL BOULTON EMMALEEN MAYELL Contractor, Wates Contractor, Mace Contractor, Mace Construction of Construction of Construction of Plot Al Plot A2 Plot A2

  4. Slide 4: Jobs and training opportunities

    Jobs and training opportunities * Over 100 jobs expected to be created over the next four years * Working with local partners to help local people of all ages access these opportunities, with a focus on those who are unemployed/school leavers * Southwark Construction Skills Centre open and acting as

  5. Slide 5: Keeping you informed

    Keeping you informed Construction Liaison Forums and Construction drop-ins * Construction drop-ins at Canada Water Library on 16* March and 20* April in the evening, more detail will be shared closer to the time * Next Construction Liaison Forum will be in May 2022 Printed newsletters: CANADAANATER

  6. Slide 6: Wider Canada Water Development Works

    Wider Canada = Water x _. > em Poa Development 2 fig a Works

  7. Slide 7: Key

    Key Canada Water Development boundary @ First phase of the development Former Dock Offices (retained) CANADA ‘@ New public square in the Dock Offices courtyard WATER @ New pedestrian route from Lower Road to Canada Water Dock © First section of New High Street CANADA DOCK N

  8. Slide 8: Construction traffic and site layout

    << ——— Construction traffic Pedestrian route Hoarding Welfare facilities

  9. Slide 9: Common working practices

    Common working practices Standard construction working hours: * Monday - Friday: 8am - 6pm * Saturday: 8am - 2pm (no noisy works before 9am) « When work outside of standard hours is needed, this will be agreed with Southwark Council and communicated in advance via our website: Wwww.canadawater.co.uk

  10. Slide 10: Canada Dock

    Canada Dock

  11. Slide 11: . a apg

    . a apg on

  12. Slide 12: Slide 12

  13. Slide 13: Slide 13

  14. Slide 14: Slide 14

  15. Slide 15: 15

    15

  16. Slide 16: Canada Dock programme timeline

    Reserved Matters Planning Approval 18 Jan 2022 Waterfowl & Reed Bed Protection Measures 11 Feb 2022 Vegetation Clearance 14 Feb 2022 Site Investigations & Enabling Works 7 Mar 2022 Main Works 1 Jul 2022 Completion Aug 2023

  17. Slide 17: Plot A2 (Mace)

    iimace Plot A2 idan | ain smn Mh " }

  18. Slide 18: Plot A2 - Current site activity

    Plot A2 - Current site activity * Piling works are underway, expected to finish in March 2022 * First phase of bulk excavation for the basement of the new building has begun and temporary propping to support the building structure is underway * First of three tower cranes will be installed towards t

  19. Slide 19: Plot A2 - Indicative Timeline

    Plot A2 — Indicative Timeline Spring/Summer 2022 Spring 2023 Summer Groundwork Facade (exterior 2024 ongoing and of building) works Expected substructure begin as well as ‘Winter 2023/24 completion works begin internal fit out Facade completes date Winter Winter Summer 2023 Spring 2024 2021/22 2022/

  20. Slide 20: Plot A1

    Plot Al i aia can i ; a hese ai aparece | mt

  21. Slide 21: Plot A1 - Current site activity

    Plot Al - Current site activity * Piling works are underway, expected to finish in March/April 2022 * Bulk excavation due to begin from late March 2022 * First of three tower cranes will be installed in May, with the remaining two in summer 2022 * Site accommodation installed and operational

  22. Slide 22: Plot A1 - Indicative Timeline

    Plot Al — Indicative Timeline Summer 2022 ‘Spring/Summer 2023 Pile cap construction, Residential tower Spring 2024 ‘Autumn 2024 basement drainage and core, staircase and Balcony Internal fit out, ground slab construction, roof completes, installation begins, ground floor residential tower core inter

  23. Slide 23: Contact us

    CANADAANATER Contact us You can contact the Canada Water Masterplan team at: Tel: 0800 +70 4593 (freephone) Email: [email protected] Website: www.canadawater.co.uk