British Land Company PLC · LSE:BLND
British Land — Corporate Update (February 2022)
23 slides from British Land's corporate update, Feb 9, 2022
Slide 1: Canada Water Development Construction Liaison Forum
Canada Water Development Construction Liaison Forum Plots Al & A2 (and surrounding area) 9 February 2022
Slide 2: Overview of tonight's presentation
* Introductions + Jobs and training opportunities * Keeping you informed * Canada Water development * Construction management Ove rview of * Canada Dock to nig ht ’ Ss + Updates from contractors G - Construction of Plot A2 (Mace) presentation - Construction of Plot Al (Wates) * Q&A
Slide 3: Our presenters
Our presenters SARAH WARD Construction Neighbour Liaison Manager MICHAEL DELFS British Land lead for Canada Dock OLLY MACK DANIEL BOULTON EMMALEEN MAYELL Contractor, Wates Contractor, Mace Contractor, Mace Construction of Construction of Construction of Plot Al Plot A2 Plot A2
Slide 4: Jobs and training opportunities
Jobs and training opportunities * Over 100 jobs expected to be created over the next four years * Working with local partners to help local people of all ages access these opportunities, with a focus on those who are unemployed/school leavers * Southwark Construction Skills Centre open and acting as
Slide 5: Keeping you informed
Keeping you informed Construction Liaison Forums and Construction drop-ins * Construction drop-ins at Canada Water Library on 16* March and 20* April in the evening, more detail will be shared closer to the time * Next Construction Liaison Forum will be in May 2022 Printed newsletters: CANADAANATER
Slide 6: Wider Canada Water Development Works
Wider Canada = Water x _. > em Poa Development 2 fig a Works
Slide 7: Key
Key Canada Water Development boundary @ First phase of the development Former Dock Offices (retained) CANADA ‘@ New public square in the Dock Offices courtyard WATER @ New pedestrian route from Lower Road to Canada Water Dock © First section of New High Street CANADA DOCK N
Slide 8: Construction traffic and site layout
<< ——— Construction traffic Pedestrian route Hoarding Welfare facilities
Slide 9: Common working practices
Common working practices Standard construction working hours: * Monday - Friday: 8am - 6pm * Saturday: 8am - 2pm (no noisy works before 9am) « When work outside of standard hours is needed, this will be agreed with Southwark Council and communicated in advance via our website: Wwww.canadawater.co.uk
Slide 10: Canada Dock
Canada Dock
Slide 11: . a apg
. a apg on
Slide 12: Slide 12
Slide 13: Slide 13
Slide 14: Slide 14
Slide 15: 15
15
Slide 16: Canada Dock programme timeline
Reserved Matters Planning Approval 18 Jan 2022 Waterfowl & Reed Bed Protection Measures 11 Feb 2022 Vegetation Clearance 14 Feb 2022 Site Investigations & Enabling Works 7 Mar 2022 Main Works 1 Jul 2022 Completion Aug 2023
Slide 17: Plot A2 (Mace)
iimace Plot A2 idan | ain smn Mh " }
Slide 18: Plot A2 - Current site activity
Plot A2 - Current site activity * Piling works are underway, expected to finish in March 2022 * First phase of bulk excavation for the basement of the new building has begun and temporary propping to support the building structure is underway * First of three tower cranes will be installed towards t
Slide 19: Plot A2 - Indicative Timeline
Plot A2 — Indicative Timeline Spring/Summer 2022 Spring 2023 Summer Groundwork Facade (exterior 2024 ongoing and of building) works Expected substructure begin as well as ‘Winter 2023/24 completion works begin internal fit out Facade completes date Winter Winter Summer 2023 Spring 2024 2021/22 2022/
Slide 20: Plot A1
Plot Al i aia can i ; a hese ai aparece | mt
Slide 21: Plot A1 - Current site activity
Plot Al - Current site activity * Piling works are underway, expected to finish in March/April 2022 * Bulk excavation due to begin from late March 2022 * First of three tower cranes will be installed in May, with the remaining two in summer 2022 * Site accommodation installed and operational
Slide 22: Plot A1 - Indicative Timeline
Plot Al — Indicative Timeline Summer 2022 ‘Spring/Summer 2023 Pile cap construction, Residential tower Spring 2024 ‘Autumn 2024 basement drainage and core, staircase and Balcony Internal fit out, ground slab construction, roof completes, installation begins, ground floor residential tower core inter
Slide 23: Contact us
CANADAANATER Contact us You can contact the Canada Water Masterplan team at: Tel: 0800 +70 4593 (freephone) Email: [email protected] Website: www.canadawater.co.uk