  1. Slide 1: Overhaul Hyper Compressor & Booster Primary (BP): From Planning to Execution

    OVERHAUL HYPER COMPRESSOR & BOOSTER PRIMARY (BP) FROM PLANNING TO EXECUTION Winterthur, April 2021 Falk Jähnigen, Thiago Heinen © Copyright 2021. Burckhardt Compression AG. All rights reserved.

  2. Slide 2: Content

    Content  Planning and execution of overhaul for LDPE compressors  1 x Hyper F8  1 x B/P 6B5A  In service since 2002  Capacity increase in 2010 Hyper and BP, From Planning to Execution April 2021 Page 2 © Burckhardt Compression AG

  3. Slide 3: Content

    Content  Planning and execution of Overhaul for LDPE compressors  1 x Hyper F8  1 x B/P 6B5A 2 3 1 4 5 Scope Detail Identification Execution Closure Definition Planning 2.5 years before overhaul Hyper and BP, From Planning to Execution April 2021 Page 3 © Burckhardt Compression AG

  4. Slide 4: Customer Request

    Customer Request  Hyper F8: on-site overhaul  BP: on-site overhaul  Evaluate foundation  Evaluate main motor  Manpower: coordination, supervision and mechanics by BCAG  Definition and supply of spare parts  Schedule of activities, guaranteed duration Hyper and BP, From Planning to Execution A

  5. Slide 5: Our Background and Customer Needs

    Our Background and Customer Needs  Modernization of plant and components  Feasibility studies  RCA Hyper and BP, From Planning to Execution April 2021 Page 5 © Burckhardt Compression AG

  6. Slide 6: Our Background and Customer Needs

    Our Background and Customer Needs  LDPE process evaluation  Other brand compressors  Overhaul  Reverse engineering Hyper and BP, From Planning to Execution April 2021 Page 6 © Burckhardt Compression AG

  7. Slide 7: Scope Definition

    Scope Definition  Compressor mechanical inspection  Frame alignment  Piston rod run out  Tightening anchor bolts Hyper and BP, From Planning to Execution April 2021 Page 7 © Burckhardt Compression AG

  8. Slide 8: Scope Definition

    Scope Definition  Complete BP vibration check, including piping Hyper and BP, From Planning to Execution April 2021 Page 8 © Burckhardt Compression AG

  9. Slide 9: Scope Definition

    Scope Definition  Complete BP vibration check, including recommendations Hyper and BP, From Planning to Execution April 2021 Page 9 © Burckhardt Compression AG

  10. Slide 10: Scope Definition

    Scope Definition  Motor inspection: Life expectancy analysis by OEM  Good condition for both B/P and Hyper Hyper and BP, From Planning to Execution April 2021 Page 10 © Burckhardt Compression AG

  11. Slide 11: Scope Definition

    Scope Definition  Motor inspection: Life expectancy analysis  Foundation consultancy Hyper and BP, From Planning to Execution April 2021 Page 11 © Burckhardt Compression AG

  12. Slide 12: Scope Definition: Supporting Documents

    Scope Definition: Supporting Documents  Report of inspections, with technical recommendations Hyper and BP, From Planning to Execution April 2021 Page 12 © Burckhardt Compression AG

  13. Slide 13: Overhaul Acquisition Plan

    Overhaul Acquisition Plan Spare Parts Tools Repair – Services Center Hyper and BP, From Planning to Execution April 2021 Page 13 © Burckhardt Compression AG

  14. Slide 14: Scope Definition: Supporting Documents

    Scope Definition: Supporting Documents  Proposal of interventions: schedule (± 10% accuracy)  Option 1: incl. foundation repair – Complete removal of compressors  Option 2: without foundation repair – Replacement and repair of capital parts Hyper and BP, From Planning to Execution April 2021 Page

  15. Slide 15: Detailed Commercial Planning

    Detailed Commercial Planning  Commercial offer for overhaul execution  Description of scope  Matrix of responsibilities  Manpower & contracting Hyper and BP, From Planning to Execution April 2021 Page 15 © Burckhardt Compression AG

  16. Slide 16: BC Strategy

    BC Strategy  Planning and execution of TAM for LDPE compressors  1 x Hyper F8  1 x B/P 6B5A 1 2 3 4 5 Customer Scope Detail Execution Closure Request Definition Planning 1 year before overhaul Hyper and BP, From Planning to Execution April 2021 Page 16 © Burckhardt Compression AG

  17. Slide 17: Execution of Technical Planning

    Execution of Technical Planning Preparation Checks & Measurements Compressor Maintenance Service on Accessories & Foundation Startup of Compressor Manpower Requirements Hyper and BP, From Planning to Execution April 2021 Page 17 © Burckhardt Compression AG

  18. Slide 18: Preparation

    Preparation Small team one week in advance of stop – 1 Site manager BCAG – 1 Shift leader Hyper - Day shift BCAG – Burckhardt Compression Admin – Customer (Team)  Safety training & medical check (Corona)  Preparing of job site  Our first site visit and observations – Hyper cylinder lubrication un

  19. Slide 19: Checks and Measurements

    Checks and Measurements Start of the overhaul  First site visit of complete workforce – 1x Site manager BCAG – 2x Teams BP (Day / Night) BCAG – 2x Teams Hyper (Day / Night) BCAG – 1x Mechanic per team from customer  Checks and measurements according to planning Hyper and BP, From Planning to Execu

  20. Slide 20: Compressor Maintenance

    Compressor Maintenance The execution  Maintenance according to planning  Not planned work on Hyper (additional) – Cylinder lubrication Hyper complete overhaul with customer mechanics Supervision support by BCAG – Removing of complete cylinders 3 & 8 due to damaged elastic rods coupling surfaces 

  21. Slide 21: Service on Foundation & Accessories

    Service on Foundation & Accessories  Alignment of crankcase  Checking of motor bearings (with ABB under BC scope)  Overhaul of oils skids & cleaning of gas and oil piping (by customer)  Not planned work on Hyper (additional) – BC Support on gas piping installation – BC Support on flushing of oil

  22. Slide 22: Controlling during the Overhaul

    Controlling during the Overhaul  Progress – Daily reporting to customer Hyper and BP, From Planning to Execution April 2021 Page 22 © Burckhardt Compression AG

  23. Slide 23: Startup of the Compressor

    Startup of the Compressor  Start of lubrication systems  Restart of compressor/plant under BC presence (only small start up team)  Two BCA supervisor present during operation (two days) Hyper and BP, From Planning to Execution April 2021 Page 23 © Burckhardt Compression AG

  24. Slide 24: Closure

    Closure  Project work reports  Meeting with customer  Lessons learned  Opportunities for next TAM  Future projects 1 2 3 4 5 Customer Scope Detail Execution Closure Request Definition Planning Hyper and BP, From Planning to Execution April 2021 Page 24 © Burckhardt Compression AG

  25. Slide 25: Conclusion

    Conclusion  Benefits for our customer  Strong technical background  Decision process is supported by concrete data  Planned and delivered in time – Documentation is revised by experienced engineers, 4-hands principle – External specialists under request  Flexibility and customization  BCAG sin

  26. Slide 26: Speakers

    Speaker 1: Falk Jähnigen, Burckhardt Compression Speaker 2: Thiago Heinen, Burckhardt Compression

  27. Slide 27: Compressors for a Lifetime

    &, Burckhardt y Compression Compressors for a Lifetime”