  1. Slide 1: TVA Kingston Fossil Fuel Plant Release Site Non-Time Critical Removal Update

    TVA Kingston Fossil Fuel Plant Release Site Non‐Time Critical Removal Update September 23, 2010

  2. Slide 2: Removal Action Areas

    Removal Action Areas Time Critical Approx 3.5 Million CYS Up to ERM 6.0 Non‐Time Critical 2.8 Million CYS Down to confluence of Emory and Clinch

  3. Slide 3: Transition Activities

    Transition Activities • North Embayment ash consolidation • Swan Pond Cir. bridge, underpass, haul road • Dredge cell contouring

  4. Slide 4: On-site Ash Numbers

    On‐site Ash Numbers • 2.8 million cys 2.8 million cys – North Embayment – Middle Embayment 4.0 million cys • 10.8 million cys – Dredge Cell • 4.0 million cys – Ash Pond – Lateral Expansion • 17.6 million cys total on‐site disposal 10.8 million cys

  5. Slide 5: Current Activities

    Current Activities EMBAYMENT RESTORATION Construct Underpass Excavate Ash - North Embayment Remove Clean Water Ditch - North Embayment Excavate Ash - Middle Embayment (Final) Dredge Middle Embayment FAILED DREDGE CELL Stack Ash - Central Dredge Cell (Cell 3) Stack Ash -North Dredge Cell (Cell 2) Clo

  6. Slide 6: What's Happening Now?

    What’s Happening Now? • Continue to build infrastructure – 78% complete – Underpass and bridge construction on‐going – Bridge scheduled to open Oct. 18 – Haul road complete

  7. Slide 7: What's Happening Now?

    What’s Happening Now? • North Embayment ash consolidation – 89% complete – Scraping ash away from natural water springs – Consolidating ash until underpass is complete

  8. Slide 8: What's Happening Now?

    What’s Happening Now? • Perimeter Containment – Deep soil mixing pilot study complete – 11 columns constructed – Column borings collected for testing – Report is pending

  9. Slide 9: What's Happening Now?

    What’s Happening Now? • Central Area contouring – 29% complete – Middle Embayment ash being removed and used to contour Central Area – Relic area and test embankment height removed down to final elevation

  10. Slide 10: Contouring

    Contouring • Central Area – Middle Embayment • Reducing height – Test Embankment – Relic Area

  11. Slide 11: EE/CA Sampling

    EE/CA Sampling • Sediment Sampling – Embayments – River sediment • Water Monitoring – 8 week SAP river sampling – Groundwater sampling • Biological Sampling – Frogs, fish, birds, benthic bugs, turtles, raccoons

  12. Slide 12: Biological Uptake

    f Recreational { SEASONALLY EXPOSED ip SEDIMENT/ASH ‘ect Contact with Surtoce Water and Seasonally Exposed Sediment Ingertion of fish and Aequat: Bota CAPPED OREOGE CELL Ingestion of Fishy

  13. Slide 13: New Work Plans

    New Work Plans • Non‐Time Critical Removal Action Work Plan • Revised Community Involvement Plan (final) • Surface Water Monitoring Plan • Air Monitoring Plan – Continuous air monitors (BAMs)

  14. Slide 14: Air Monitoring

    Air Monitoring • Real‐time air monitors (5 stations) – 2 TEOMs (PM 2.5 & 10) – 5 BAMs (PM 2.5) – 1 FRM (PM 2.5)

  15. Slide 15: Surface Water Monitoring

    Surface Water Monitoring • 3 on‐site locations sampled 1/week • ISCO automated Emory River samplers (rain events) – 3 locations on Emory River – 2 locations on Clinch River – 1 location on‐site (clean water ditch) Clinch River

  16. Slide 16: Leachability Testing

    Leachability Testing • 70% complete • Evaluating leaching behavior of ash using site‐specific conditions • Using ash, lime‐treated ash, and cement‐ treated ash • Support groundwater transport modeling

  17. Slide 17: New Well Installations

    New Well Installations • Proposed wells: – 6 existing – 3 permanent – 7 temporary – 16 boreholes • Installed wells: – 3 permanent – 2 temporary – 0 boreholes

  18. Slide 18: Instrumentation

    Instrumentation • Installing in central and north dredge cell area – 50% complete – 18 piezometers (pore pressure) – 9 slope inclinometers (vertical movement) – 5 settlement plates (vertical movement)

  19. Slide 19: Upcoming Activities

    Upcoming Activities EMBAYMENT RESTORATION Construct Underpass Excavate Ash - Middle Embayment (Initial) | Excavate Ash - North Embayment Remove Clean Water Ditch - North Embayment Restore Ecosystem - North Embayment Excavate Ash - Middle Embayment (Final) Remove Clean Water Ditch - Middle Embayment

  20. Slide 20: Next Steps

    Next Steps • Construction of perimeter containment – Working platform – Deep soil mixing columns

  21. Slide 21: Next Steps

    Next Steps • Stacking and compacting ash in dredge cell – Preparation of subgrade to capillary break elevation – Start in central contoured area (Cell 3) – Next area is north near east‐ west haul road (Cell 2)

  22. Slide 22: Next Steps

    Next Steps • Hauling ash – From North Embayment and Middle Embayment – Use underpass for North Embayment ash hauling