Slide 1: Xcel Energy Colorado DSM Roundtable Discussion
Xcel Energy Colorado DSM Roundtable Discussion August 26, 2010 2:00pm to 5:00pm 1800 Larimer Room 03G01
Slide 2: Welcome and Introductions
Welcome and Introductions Contact Info: Suzanne Doyle Manager, DSM Regulatory Strategy & Planning Office Phone: 612-330-5518 Cell Phone: 612-599-5785 E-mail: [email protected]
Slide 3: Agenda
Agenda 2:00 – 2:05 Welcome, Introductions (Doyle) 2:05 – 2:30 Regulatory & Program Evaluation Updates (Doyle) 2:30 – 3:15 DSM Program Highlights (Warman/White) 3:15 – 3:30 Break 3:30 – 4:00 Product Development Update (Spargo) 4:00 – 4:45 Highlights of the 2010 ACEEE Summer Study on Energy Efficiency
Slide 4: Regulatory & Program Evaluations Updates
Regulatory & Program Evaluations Updates Presented by: Suzanne Doyle Compliance Complianceinformation informationisisavailable available at atXcel XcelEnergy’s Energy’sDSM DSMWebsite: Website: http://www.xcelenergy.com/Colorado/Company/About_Energy_ http://www.xcelenergy.com/Colorado/Company/About_E
Slide 5: 2010 60-Day Notices
2010 60-Day Notices February 8, 2010 AC Tune-Up Pilot Standard Offer May 3, 2010 Boiler Efficiency Cooling Efficiency Furnace Efficiency High Efficiency Air Conditioning Home Lighting & Recycling New Construction – Energy Design Assistance May 7, 2010 Lighting Efficiency 5
Slide 6: 2010 60-Day Notices
2010 60-Day Notices Summer 2010 June 1, 2010 ENERGY STAR New Homes ENERGY STAR Retailer Incentive August 16, 2010 Energy Feedback Pilot Boiler Efficiency 6
Slide 7: Timeline of Recent Filings
Timeline of Recent Filings April 5, 2010 July 1, 2010 2009 Annual Status 2011 DSM Plan (Electric & Report Gas) Docket No. 10A-471EG April 2010 Sept 2010 May 7, 2010 August 10, 2010 August 13, 2010 Motion to Alter or Amend DSM Strategic Issues Quarterly Reports to Decision Nos. C08-0560 and Applicati
Slide 8: Filing Details: Motion to Alter or Amend Decision Nos. C08-0560 and C08-0769
Filing Details Motion to Alter or Amend Decision Nos. C08-0560 and C08-0769 Filed May 7, 2010 One year Plan (for 2011 instead of biennium) to be filed July 2010 (Approved) Bifurcated Filing – separate strategic issues from 2011 Plan (Approved) 2010/11 Incentive Modification (Increase Cap on
Slide 9: Filing Details: 2011 DSM Plan (Docket No. 10A-471EG)
Filing Details 2011 DSM Plan (Docket No. 10A-471EG) Filed July 1, 2010 2011 Electric Budget & Goals: $67.4 M and 240 GWh 2011 Gas Budget & Goals: $15.8 M and 368,227 Dth Splits portfolio into 6 programs: Electric: Business, Residential, Low-Income Gas: Business, Residential, Low-Income Upd
Slide 10: Filing Details: Strategic Issues Application (Docket No. 10A-554EG)
Filing Details Strategic Issues Application (Docket No. 10A-554EG) Filed August 10, 2010 Increases electric energy saving goals ~7% annually for 2011 – 2020 Modified electric incentive mechanism, including recovery of lost margins and a performance component Asks for guidance on setting gas
Slide 11: DSM Process and Impact Evaluations
DSM Process and Impact Evaluations Residential – Conducted by The Cadmus Group Evaporative Cooling Program – Scheduled Completion Date 12/15/10 Trade Ally surveys – Completed Participant surveys and meter recruit completed Meters installed Customer Behavioral Change Program – Scheduled C
Slide 12: Overall DSM Achievements Q2 June 30, 2010
Overall DSM Achievements Q2 June 30, 2010 Electric YE Goals: 67 MW, 237 GWh, $63.6M Electric Achievements: 26 MW, 130 GWh, $20.2M Gas YE Goals: 402,808 Dth, $16.5M Gas Achievements: 143,364 Dth, $6.3M 12
Slide 13: DSM Program Highlights
DSM Program Highlights Presented By: Kate Warman Shawn White
Slide 14: Residential and Low-Income Program Highlights
Residential and Low-Income Program Highlights
Slide 15: Central AC Trade In
Central AC Trade In Rebate added late spring 2010 Rebate is in addition to high efficiency new equipment, with quality installation $500 Trade In rebate for old systems, 12 SEER max, and new equipment 14 SEER minimum Few Trade In rebates received to date, but high activity (phone calls with
Slide 16: Central AC Rebates – Trade Relations
Central AC Rebates – Trade Relations Contractors reluctant to use the program Load calculations (right sizing) take 1 – 2 hours Rebate paperwork requires technical measurements sometimes not done today (quality installation related) The requirement for a NATE technician Minnesota is having
Slide 17: Central AC Tune-Up Pilot
Central AC Tune-Up Pilot Pilot re-launched with changes spring 2010 Proactive demand is very low during spring season Customers don’t think of tuning their AC in cooler weather Customers haven’t responded well to marketing efforts During summer, there’s limited technician time for a compre
Slide 18: Low-Income Kits
Low-Income Kits Secured a contract with the Mile High Youth Corps to create kits, perform all data collection, and to distribute to qualified customers M&V results are showing higher installation rates compared to 2009. All kit materials are now offered in Spanish Running into challenges wit
Slide 19: Refrigerator Recycling
Refrigerator Recycling Program offers a free scheduled pick up of the secondary refrigerator unit and offers a $35 rebate As of 6/31, we have recycled 1,109 units Participation improved from 2009 but customer interest is still low Similar marketing efforts are more successful in other states
Slide 20: Community Energy Efficiency Activities
Community Energy Efficiency Activities Worked with over 20 cities & counties that received EECBG funds (ARRA) Partnering with Boulder, Denver, and Garfield County to develop business/residential energy efficiency initiatives with ambitious participation goals (funded by EECBG-C) Fulfilled more
Slide 21: Business Energy Efficiency Program Highlights
Business Energy Efficiency Program Highlights
Slide 22: Boiler Efficiency
Boiler Efficiency Participant Goals: Filed 146 participants; 31,650 Dth Q2 YTD Achievement: 64 projects; 16,843 Dth (53% of goal) Q2 Program Promotions: Researched all eligible businesses with boilers, conducting 4 phase campaign to promote product Launched Plan B boilers (higher rebate
Slide 23: Process Efficiency
Process Efficiency Participant Goals: Electric Filed 4 participants; 7.79 GWh Q2 YTD Achievement: 9 projects; 2.46 GWh (31% of year-end goal) Q2 Program Activity: 5 new customers joined the program in 2010 for a total of 14 since program availability Our customer base now consists of s
Slide 24: Lighting Efficiency
Lighting Efficiency Participant Goals: Electric Filed 678 participants; 35.9 GWh Q2 YTD Achievement: 803 participants; 37.1 GWh (103% of year-end goal) Q2 Program Activity: Positive results due to Diversity of available rebate measures Increased rebate levels commenced with the 2009
Slide 25: Break
(2) Xcel Energy’ Break
Slide 26: DSM Product Development Update
DSM Product Development Update Presented by: George Spargo DSM DSMWebsite Websiteprovides providesprogram programidea ideasubmission submissionforms formsat: at: http://www.xcelenergy.com/Colorado/Company/About_Energy_and_Ra http://www.xcelenergy.com/Colorado/Company/About_Energy_and_Ra tes/DemandSi
Slide 27: Product Development Team
Product Development Team George Spargo – Manager – 612-330-6036 Anne Kraft – Commercial Segment – 612-330-7582 Pat Goggin – Industrial Segment – 303-294-2370 Nathan Huso – Residential Segment – 612-330-2812 27
Slide 28: 60-Day Notice for Modified Products
60-Day Notice for Modified Products ENERGY STAR New Homes (6/1/10) Updated Technical Assumptions More Accurate (Lower) Incremental Costs Used Modeled HERS scores for measures (not deemed values) Addressed Cost/Benefit Issues Reduced Admin Expenses Corrected Net-to-Gross Used actual p
Slide 29: 60-Day Notice for Modified Products
60-Day Notice for Modified Products ENERGY STAR Retailer Incentive(6/1/10) Updated Technical Assumptions Updated Baseline Products New ENERGY STAR 4.1 & 5.1 Televisions (Apr. 1, 2010) New CEE Standards Used updated data to adjust Net-to-Gross Focused on Mid-Stream Retailer incentives
Slide 30: 60-Day Notice for Modified Products
60-Day Notice for Modified Products Boiler Efficiency (8/16/10) Updated Technical Assumptions to correct an omission in the Deemed Savings Doesn’t affect goals, budgets, or the product’s TRC previously filed 30
Slide 31: 60-Day Notice for New Products
60-Day Notice for New Products Energy Feedback Pilot (8/16/10) Energy Feedback Pilot included in 2011 DSM Plan 2010 activity consists of: Set up Data gathering Report delivery. 2010 goals for kWh and Dth will be zero. 31
Slide 32: Energy Feedback Pilot
Energy Feedback Pilot Energy Feedback Pilot included in 2011 DSM Plan 60-Day Notice to begin set-up of program posted August 16 Testing 35,000 participants receiving paper reports in the mail ~7 times per year versus similar “control” group Testing 15,000 receiving 1 initial paper report and
Slide 33: DSM Roundtable New Product Development Procedure
DSM Roundtable New Product Development Procedure Interested persons may submit new program ideas or proposed revisions to existing programs to the Company in writing (link below). The Company screens and prioritizes all new program ideas for further research and development. Within three month
Slide 34: DSM Roundtable New Product Development Procedure
DSM Roundtable New Product Development Procedure No products from DSM Roundtable participants during quarter 34
Slide 35: Product Development Timeline - Next DSM Plan filing in 2011
Product Development Timeline - Next DSM Plan filing in 2011 Ideation July 1 – August 15 Framing July 15 –August 31 Design Sept. 1 through Q1 2011 Build Oct. 1 through Q2 2011 Test Nov. 1 through 2012 Launch Jan. 1 through 2013 35
Slide 36: Product Development Process
Product Development Process Traditional “Stage-Gate” process that includes team or management review at key decision points: Ideation Framing Design Build Test Launch 36
Slide 37: Stakeholder Input Ideas
Stakeholder Input Ideas ECM Furnace Motor Retrofit Conservation Membership (BC Hydro PowerSmart) Similar to OPower Upstream HE Window rebate/incentive Energy Efficiency Support Services Forced Air Duct Sealing 37
Slide 38: New Products Under Consideration
New Products Under Consideration Commercial Industrial Computer Efficiency ASD/VFD Study Commercial Energy Feedback Pilot Efficient Small Motors - ECMs Commercial Efficiency Pilot "Plan A" FOR 10 to 49 HP VSD Compressors Desktop PC Virtualization Pumping Equipment Rebates Expand Refrigeration Recomm
Slide 39: A/C Tune-up Pilot Update
A/C Tune-up Pilot Update 283 tests through July 147 have enough data to analyze Many of the early tests weren’t complete – Training, learning curve – Weather conditions not conducive to testing. Many units with a high pre-test don’t receive a post-test 73 tune-ups passed pilot program crit
Slide 40: Whole House Energy Efficiency Study
Whole House Energy Efficiency Study Study description included in 2011 DSM Plan 10 Houses will be selected for Energy Efficient improvements Different combinations of efficient technology upgrades Track pre-study home energy usage versus post- improvement energy usage. Measures: Insulation
Slide 41: Highlights of the 2010 ACEEE Summer Study on Energy Efficiency in Buildings
Highlights of the 2010 ACEEE Summer Study on Energy Efficiency in Buildings Presented by: Howard Geller Southwest Energy Efficiency Project (SWEEP)
Slide 42: Open Discussion/Wrap-Up
Open Discussion/Wrap-Up Upcoming UpcomingRoundtable RoundtableSchedule: Schedule: Q3: Q3:November November17, 17,2010 2010