Impala Platinum Holdings Limited · JSE:IMP
Impala Platinum — Corporate Update (October 2005)
10 slides from Impala Platinum's corporate update, Oct 28, 2005
Slide 1: Progress on implementation of drill jigs at Impala
Progress on implementation of drill jigs at Impala Investor visit 28 October 2005 Factors impacting team productivity • Older shafts with high team efficiencies being replaced by new deep level shafts • Distance (horizontal) from barrel affecting face time and thus mining cycles (affects blast frequ
Slide 2: Technology intervention / Potential DDT benefits
Technology intervention • Drill-jigs (DDT) technology on the Merensky horizon • Including in-stope bolting as a support system 3 Potential DDT benefits • Primary benefits • Safety • Remove rockdrill operators from danger area • Permanent support close to face • Reduction in number of FOGs • Secondar
Slide 3: Drill jigs - Stoping
Drill jigs - Stoping 5 Drill jigs - Stoping 6 3
Slide 4: Drill jigs - Stoping / Gulley
Drill jigs - Stoping 7 Drill jigs - Gulley 8 4
Slide 5: CA's/Team learning curve
Team learning curve (built into 5-year plan) 530m²/team 450m²/team Training + 1 month bolt lead ± 3 months (breakeven) ± 5 months (Improvement) ± 8 months (Payback) ± 12 months (Benefits) 9 Progress over 7 months – learning curve Last three months 480 ave. = 446 CA’s YTD = 437 = 5% impr. Base = 425
Slide 6: Roof-bolting and drill jig progress of roll-out
Roof-bolting: Progress of roll-out (as at 22 October 2005) 200 184 Teams Oct ‘05 180 160 20 Teams behind schedule Teams 140 120 100 80 11 Drill jig: Progress of roll-out (as at 22 October 2005) 130 120 81 Teams on DDT 110 100 90 20 Teams behind schedule Teams 80 70 60 50 40 26 27 28 29 30 31 32 33 3
Slide 7: Falls of ground / New technology - flat-end development
Falls of ground Falls of ground larger than 4m2 - Impala Platinum 60 50 51 In Stope 50 48 GCDs RS Straps Strocams 200mm Bolting No. of FOG's 40 30 Double Roll-Out 18 20 16 16 12 12 13 13 13 12 11 11 11 10 11 11 11 8 9 8 9 9 9 9 10 7 7 8 6 6 5 4 5 6 5 4 6 4 4 3 3 1 0 Month 13 New technology - flat-en
Slide 8: Factors affecting drill jig implementation / Risks
Factors affecting drill jig implementation • Slow uptake by above average performing teams. • Prioritisation of roofbolt roll-out • Training period takes longer than anticipated. • Teams require consistent monitoring and coaching after training. 15 Risk associated with DDT implementation • Lack of t
Slide 9: The way forward / Targets for FY2006
The way forward • Drive R&D into and trials on bolters of less than 1m for the UG2 (±85cm) • Drive R&D into and trials on development technology to ensure availability of developed reserves • Revisit efficiency improvements in FY2007 and beyond, however FY2006 required as a learning period. • Contin
Slide 10: Centares / Panel Man envisaged improvement
Envisaged improvement Ca/Panel Man - DDT Technology (Merensky) 48 2% 46 47 10% 46 Centares / Panel Man 44 5% 42 42 40 40 38 0,85m 1,0m 1,0m 1,0m adv/blast adv/blast adv/blast adv/blast 36 19/23 19/23 19/23 19/23 34 blasts blasts blasts blasts 32 450 Ca's 472 Ca's 511 Ca's 530 Ca's 30 Current Realist