  1. Slide 1: Pareto Oil & Offshore Conference

    total subsea solutions Pareto Oil & Offshore Conference August 31st 2005 Kristian Siem Chairman of Subsea 7 Inc

  2. Slide 2: Introduction

    total subsea solutions Introduction Subsea 7 Key Focus Areas Subsea 7 Corporate Changes Financial Highlights The Fleet Market Outlook

  3. Slide 3: Subsea 7 Current Key Focus Areas

    total subsea solutions Subsea 7 Current Key Focus Areas Projects undertaken safely, on time Move to Pan-European way of doing Project business in the North Sea and within budget Execution Leadership Training Programme Engineering Conversion Course Investment in technology Strengthen Graduate Trainin

  4. Slide 4: Corporate Changes

    total subsea solutions Corporate Changes Key events ƒ November 2004 – Siem Offshore entered into a Heads of Agreement with Halliburton to acquire Halliburton’s 50% share in Subsea 7 ƒ January 2005 – transaction completed. Prior to completion, Siem raised NOK 991 million in new equity (~ $160 million

  5. Slide 5: Subsea 7 Financials

    total subsea solutions Subsea 7 Financials The pro-forma financial information set out in this presentation (including comparatives) reflects solely the Subsea activities of Subsea 7 as if Subsea 7 had always been 100% owned.

  6. Slide 6: Financial Highlights – First Half 2005

    total subsea solutions Financial Highlights – First Half 2005 Order Intake Revenue EBITDA Net Income $ 852 M $ 73 M Unaudited Figures $M $ 23 M $ 591 M $ 340 M $ 319 M $ (2) M $ (49) M H1 04 H1 05 H1 04 H1 05 H1 04 H1 05 H1 04 H1 05

  7. Slide 7: Four Consecutive Quarters of Strong Performance

    total subsea solutions Four Consecutive Quarters of Strong Performance EBITDA US $M $ 140 M Unaudited Figures $M $ 52 M $ 38 M $ 29 M $ 20 M $ 21 M $ 13 M $5M $ (5) M $ (7) M Q3 03 Q3 04 Q4 03 Q4 04 Q1 04 Q1 05 Q2 04 Q2 05 4 Qtrs 4 Qtrs to to 30.6.04 30.6.05

  8. Slide 8: Selected Projects Completed in Last 12 Months

    total subsea solutions Selected Projects Completed in Last 12 Months CLIENT PROJECT DESCRIPTION REGION TOTAL VALUE COMPLETION DATE SANTOS MUTINEER / SUBSEA DEVELOPMENT AND FPSO INSTALLATION ASIA PACIFIC $28M MAR 05 EXETER CONOCO BELANAK FPSO INSTALLATION ASIA PACIFIC $15M NOV 04 STATOIL ASGARD Q SUB

  9. Slide 9: Backlog US $M

    total subsea solutions Backlog US $M $ 1.3 B $ 1.3 B $ 1.2 B 11% 79% $ 695 M 30-Sep-04 31-Dec-04 31-Mar-05 30-Jun-05

  10. Slide 10: Key Projects Secured in Last 12 Months

    total subsea solutions Key Projects Secured in Last 12 Months CLIENT PROJECT DESCRIPTION REGION TOTAL VALUE EST COMPLETION DATE MURPHY KIKEH EPIC - JV WITH TECHNIP INCL INSTALLATION OF FPSO ASIA PACIFIC $74M 3Q06 PETROBRAS PDEG B EPIC – 10” +12” PIPELINE TOTALLING 168KM IN LENGTH BRAZIL $249M 2Q07 P

  11. Slide 11: Breakdown of Backlog

    total subsea solutions Breakdown of Backlog B y R e g io n B y C o n tra c t T y p e B y B u s in e s s L in e $ 1 ,3 4 2 M $ 1 ,3 4 2 M $ 1 ,3 4 2 M 148 296 372 + 134% 116 31 $ 574 M $ 574 M $ 574 M 1 ,1 9 4 533 61 88 970 52 222 57 55 72 129 513 352 250 237 30 June 2004 30 June 2005 30 June 2004 30

  12. Slide 12: Cash Flow – First Half 2005 US $M

    total subsea solutions Cash Flow – First Half 2005 US $M Unaudited Figures $M $M $M Cash at 1st January, 2005 169.0 Add Cash Inflows Less Cash Outflows Cash Balance of Subsea 7 at Acquisition 77.0 Purchase of Halliburton Share of Subsea 7 (203.0) Refinance of Debt 33.0 Debt Repayment (42.5) Operatin

  13. Slide 13: Bank Debt and Cash on Hand as at 30th June, 2005

    total subsea solutions Bank Debt and Cash on Hand as at 30th June, 2005 Total Debt Facility $ 142.5 M Available $ 35.0 M Drawn $ 107.5 M Net Debt $ 52.1 M $ 55.4 M Cash

  14. Slide 14: Safety: Lost Time Injury/Illness Frequency Rates

    total subsea solutions Safety: Lost Time Injury/Illness (LTI) Frequency Rates per 200,000 man Hours 1.00 0.94 0.93 0.90 DSND Subsea 0.80 Halliburton Subsea 0.70 Subsea 7 0.60 0.56 Competitor 0.50 0.53 0.46 0.43 0.40 0.45 0.36 0.36 0.33 0.35 0.32 0.30 0.29 0.29 0.27 0.27 0.20 0.18 0.14 0.13 0.12 0.10

  15. Slide 15: Subsea 7 Assets: Market Alignment Programme. A Timeline of Events

    total subsea solutions Subsea 7 Assets: Market Alignment Programme. A Timeline of Events 2006+ 2006 – K3000 upgrade to 300T Sept 2005 – Lochnagar upgrade to 255T August 2005 – Skandi Navica upgrade to 205T August 2005 - 5 new ROVs commissioned May 2005 – New build Pipelay & Construction Vessel commi

  16. Slide 16: New build Reeled Pipelay & Construction Vessel – Summary Spec

    total subsea solutions New build Reeled Pipelay & Construction Vessel – Summary Spec Principal Particulars Length overall: 157.1m Length on water line: 145.7m Breadth: 28.4m Depth to maindeck: 12.5m Draught design: 7.5m Ship Capability Service speed over 13 knots Propulsion: 3 aft azimuth thrusters

  17. Slide 17: Vessel Utilisation – First Half 2005 versus First Half 2004

    total subsea solutions Vessel Utilisation – First Half 2005 versus First Half 2004 100 90 80 70 60 % Utilisation 50 40 30 72% 96% 60% 87% 75% 88% 63% 90% 20 10 0 Pipelay DSV Construction Construction ROV ROV/Survey First Half 2004 First Half 2005 ƒ Increased utilisation in all vessel classes. Most p

  18. Slide 18: ROV Utilisation: First Half 2005 versus First Half 2004

    total subsea solutions ROV Utilisation: First Half 2005 versus First Half 2004 100 90 80 70 60 % Utilisation 50 40 63% 80% 30 20 36% 51% 10 0 W orkclass Observation class First half 2004 First half 2005 ƒ Improved utilisation in both classes of vehicle but most significant in work class. ƒ 80% work

  19. Slide 19: IEA World Primary Energy Demand Forecast

    total subsea solutions IEA World Primary Energy Demand Forecast 9,000 8,000 7,000 6,000 5,000 Mtoe 4,000 3,000 2,000 1,000 0 OECD Developing Countries 2002 2030 • By 2030, the majority of world primary energy demand is expected to come from the developing countries, far outstripping demand from the

  20. Slide 20: Global Subsea Capex 1999 to 2008

    total subsea solutions Global Subsea Capex (excluding drilling and completions) 1999 to 2008 8,000 7,000 6,000 5,000 $M 4,000 3,000 2,000 1,000 0 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 Africa Asia Pac Europe (Excl UK & Norway) UK Norway Brazil GOM ƒ After being flat to 2004, capex taking

  21. Slide 21: Subsea 7 Global Markets - Outlook

    total subsea solutions Subsea 7 Global Markets - Outlook NORTH SEA • Demand dominated by few major frame agreements and a GULF OF MEXICO multitude of small EPICs • Move from deep water to • Supply side has shed capacity, with vessels making for ultra deep water international waters • Consolidation o

  22. Slide 22: Summary

    total subsea solutions Summary ƒ Clearly defined business segment ƒ Focus on project execution / personnel development ƒ Strong management ƒ Market driven asset investment ƒ Record backlog ƒ Strong market ahead ƒ Acceptable return on capital CONFIDENCE IN THE FUTURE FOR SUBSEA 7