  1. Slide 1: Waddi Wind Farm

    Waddi Wind Farm Community Reference Group (CRG) - Meeting Three 18 May 2026

  2. Slide 2: Acknowledgment of Country

    Acknowledgment of Country Tilt Renewables acknowledges the Traditional Custodians of the lands on which we meet today – the Yued people. ​ We recognise the enduring connection to land, waters and community of all Aboriginal and Torres Strait Islander peoples. ​ We wish to pay our respect to Elders,

  3. Slide 3: Attendees

    Attendees Tim O’Rourke Stakeholder Engagement Advisor, Tilt Renewables Jamie Breen Site Manager, Tilt Renewables Joel Levin Facilitator, Aha! Consulting Waddi Wind Farm CRG Meeting Three | May 2026 3 3

  4. Slide 4: CRG Purpose and Terms of Reference

    CRG Purpose and Terms of Reference Recap of CRG Purpose • Discuss the Project with a focus on construction related issues • Raise awareness of local concerns and opportunities, and represent a broad range of stakeholder views • Share community knowledge to understand and mitigate potential impacts •

  5. Slide 5: Tonight’s Session Goals

    Tonight’s Session Goals Session Goals 1. Welcome CRG members and introduce new project team members. 2. Review and confirm completion of actions from CRG Meeting #2. 3. Provide construction and benefit sharing updates 4. Discuss potential for a site visit next CRG. Waddi Wind Farm CRG Meeting Three

  6. Slide 6: Outstanding actions

    Outstanding actions

  7. Slide 7: Outstanding actions

    Outstanding actions CRG #2: Recap and closeout of actions Action Owner Outcome • Send 2026 CRG Calendar / Confirm Tilt / CRG Complete. Calendar sent via email and availability confirmed. availability to attend 2026 CRG dates. • Share details of home sporting matches in CRG Complete. Tilt contacted D

  8. Slide 8: TV and radio reception

    TV and radio reception

  9. Slide 9: Spinning blades

    Spinning blades intermittently disrupt. the signal How we resolve issues with TV and radio reception Complete electromagnetic field (EMF) assessments to identify signal paths Site turbines to avoid or minimise impacts, where. possible Engage qualified technicians to solve any issues identified befor

  10. Slide 10: TV and radio reception interference

    TV and radio reception interference All television broadcasts in Australia are digital. Digital TV signals are generally much less susceptible to interference from wind farms than analogue signals, however, it is possible in areas of low signal strength. We understand there is low signal strength in

  11. Slide 11: Construction update

    Construction update

  12. Slide 12: Construction update

    Construction update Site compound offices installed 45 to 65 workers on site 30 to 40 vehicles on site Benches (compound, laydowns, batch plant) around 70% complete Waddi Wind Farm CRG Meeting Three | May 2026 12

  13. Slide 13: What we’ve been up to

    What we’ve been up to Figure 1: View north-west from site entrance on Mullering Road Figure 2: View south looking toward Mullering Road Waddi Wind Farm CRG Meeting Three | May 2026 13

  14. Slide 14: What we’ve been up to

    What we’ve been up to Figure 3: Aerial view of main site compound Figure 4: View west looking toward the coast Waddi Wind Farm CRG Meeting Three | May 2026 14

  15. Slide 15: What we’ve been up to

    What we’ve been up to Figure 5: Earthworks on site Figure 6: Internal access tracks Waddi Wind Farm CRG Meeting Three | May 2026 15

  16. Slide 16: What’s coming next

    What’s coming next *Update since CRG – Mullering Road works expected to start late June and complete in October, subject to change based on weather conditions May 2026 Jun 2026 Late Jul 2026 Aug 2026 • Mullering Road upgrade • Site compound and • Mullering Road works • CRG site visit starts hardstan

  17. Slide 17: Mullering Road upgrade

    Mullering Road upgrade • Tilt Renewables is sealing a section of Mullering Road from the intersection to a location east of the wind farm. • Affected landowners have been consulted and access will be maintained throughout the works. • Works are due to start in May. • We have advertised the closure i

  18. Slide 18: Benefit sharing update

    Benefit sharing update

  19. Slide 19: Construction benefit sharing

    Construction benefit sharing We’ve been busy working with local organisations to identify and fund projects since the last CRG meeting. $85,050 Education Community projects $42,525 $42,525 Badgingarra Primary School Dandaragan CRC Value: $5,000 Value: $48,177 Contribution to mobile antenna Rooftop s

  20. Slide 20: Central Midlands Wind Farm

    Central Midlands Wind Farm

  21. Slide 21: Central Midlands Wind Farm

    Central Midlands Wind Farm Tilt acquired the Central Midlands Wind Farm located east of Moora in WA. • The wind farm development has a potential capacity of up to 1,100 MW, capable of strengthening energy security for up to 650,000 homes. • Ownership of the project transferred from Zeff Energy Pty L

  22. Slide 22: Complaints Register and next steps

    Complaints Register and next steps

  23. Slide 23: Complaints Register

    Complaints Register Overview of Complaints Register • Complaints received to date:  June 2025 – Objection to wind farm  August 2025 – Gates left open  February 2026 – Entered host property without adequately notifying landholder Waddi Wind Farm CRG Meeting Three | May 2026 23 23

  24. Slide 24: Next steps

    Next steps Actions Minutes • Drafted within 10 business days • Feedback within 2 weeks • Finalised 1 week after feedback Next Meeting • Site visit (date and time to be discussed) Waddi Wind Farm CRG Meeting Three | May 2026 24

  25. Slide 25: Thank you for your time

    i Thank you for your time /| | oH.