Pepco — Q3 2013 Earnings Presentation
16 slides from Pepco's earnings presentation, Nov 6, 2013
Slide 1: Third Quarter 2013 Earnings Call
Exhibit 99.2 Third Quarter 2013 Earnings Call November 6, 2013
Slide 2: Safe Harbor Statement/Regulation G Information
Safe Harbor Statement/Regulation G Information Some of the statements contained in today’s presentation with respect to Pepco Holdings, Pepco, Delmarva Power and Atlantic City Electric, including each of their respective subsidiaries, are forward-looking statements within the meaning of the U.S. fed
Slide 3: Third Quarter Earnings
Third Quarter Earnings Three Months Ended September 30, 2013 2012 Nine Months Ended September 30, 2013 2012 (Millions of Dollars) Reported (GAAP) Net Income from Continuing Operations $ 110 $ 87 $ 52 $ 184 Adjustments (after-tax)*: · Change in assessment of corporate tax benefits related to the cros
Slide 4: Power Delivery Construction Expenditure Forecast
Power Delivery Construction Expenditure Forecast (Millions of Dollars) 2014 2015 2016 2017 2018 Total Distribution: Customer Driven (new service connections, meter installations, highway relocations) $ 129 $ 129 $ 143 $ 145 $ 136 $ 682 Reliability and Aging Infrastructure (facility replacements/upgr
Slide 5: Distribution Rate Cases – Recent Decision, Delmarva Power – Maryland
Distribution Rate Cases – Recent Decision Delmarva Power – Maryland Delmarva Power - Maryland Case No. 9317 Filed Position Approved Settlement (Millions of Dollars) Date 3/29/13 8/30/13 Adjusted Rate Base $507.8 Not specified Equity Ratio 49.6% Not specified Return on Equity (ROE) 10.25% 9.81% (2) N
Slide 6: Distribution Rate Cases – Approved Settlement Agreement, Delmarva Power – Delaware Gas
Distribution Rate Cases – Approved Settlement Agreement Delmarva Power – Delaware Gas Delmarva Power - Delaware Gas Docket No. 12-546 Most Recent Filed Position Approved Settlement (Millions of Dollars) Date 7/15/13 10/22/13 Adjusted Rate Base $276.8 Not specified Equity Ratio 49.2% Not specified Re
Slide 7: Proposed Forward Looking Rate Plan Filing – Delmarva Power – Delaware Electric
Proposed Forward Looking Rate Plan Filing – Delmarva Power – Delaware Electric In our November 2012 Delmarva Power Delaware Electric settlement (Docket No. 11-528), Delmarva Power, the Delaware Public Service Commission (DPSC) Staff and the Division of the Public Advocate agreed to meet to discuss:
Slide 8: Distribution Rate Cases – Pending, Delmarva Power – Delaware Electric
Distribution Rate Cases – Pending Delmarva Power – Delaware Electric Delmarva Power -Delaware Electric Docket No. 13-115 Procedural Schedule (Millions of Dollars) Most Recently Filed Position 9/20/13 Initial Filing Date 3/22/13 Test Period 12 mos. actual data ending 12/31/12 Intervenors' Testimony R
Slide 9: Distribution Rate Cases – Pending, Pepco – District of Columbia
Distribution Rate Cases – Pending Pepco – District of Columbia Pepco - District of Columbia FC No. 1103 Procedural Schedule (Millions of Dollars) Most Recently Filed Position 9/16/13 Initial Filing Date 3/8/13 12 mos. actual data ending 12/31/12 Intervenors' Testimony 8/9/13 Test Period Intervenors'
Slide 10: Pepco Undergrounding Status – District of Columbia
Pepco Undergrounding Status – District of Columbia On May 15, 2013, the Mayor of the District of Columbia accepted the recommendations in an interim report presented by the Power Line Undergrounding Task Force (established in August 2012): • A seven to ten year, $1 billion program to underground up
Slide 11: Sales and Decoupling
Sales and Decoupling Third Quarter Sales* September Year-to-Date Sales* 2013 vs. 2012 2013 vs. 2012 2013 % Change 2013 % Change Pepco 7,345 1.1% 19,852 (0.7%) Delmarva Power 3,282 (8.8%) 9,480 (2.7%) Atlantic City Electric 2,812 (4.3%) 7,132 (2.8%) Total Power Delivery 13,439 (2.6%) 36,464 (1.7%) *
Slide 12: Pepco Energy Services
Pepco Energy Services Year-to-date PES earned $3 million in net income from continuing operations compared to $1 million in adjusted* net income from continuing operations through September 2012 ESCO market is in the early stages of recovery and contract signings are up from last year • Signed $38 m
Slide 13: Reconciliation of Third Quarter GAAP EPS to Adjusted EPS
Reconciliation of Third Quarter GAAP EPS to Adjusted EPS Three Months Ended September 30, 2013 2012 Nine Months Ended September 30, 2013 2012 Reported (GAAP) Earnings per Share from Continuing Operations $ 0.44 $ 0.38 $ 0.21 $ 0.80 Adjustments (after-tax)*: · Change in assessment of corporate tax be
Slide 14: Earnings Per Share Variance – Three Months Ended September 30
Earnings Per Share Variance – Three Months Ended September 30 Three Months Ended September 30, Power Delivery Pepco Energy Services Corporate and Other Total PHI 2012 Earnings (loss) per share from Continuing Operations (GAAP) (1) $ 0.40 $ (0.01) $ (0.01) $ 0.38 Change from 2012 GAAP earnings (loss)
Slide 15: Earnings Per Share Variance – Nine Months Ended September 30
Earnings Per Share Variance – Nine Months Ended September 30 Nine Months Ended September 30, Power Delivery Pepco Energy Services Corporate and Other Total PHI 2012 Earnings (loss) per share from Continuing Operations (GAAP) (1) $ 0.84 $ (0.01) $ (0.03) $ 0.80 2012 Adjustment (2) Pepco Energy Servic
Slide 16: 2013 Earnings Guidance
2013 Earnings Guidance Pepco Holdings 2013 earnings guidance range is narrowed to $1.08 - $1.18 per share from $1.05 - $1.20 per share The guidance range excludes: • The results of discontinued operations and the impact of any special, unusual or extraordinary items, and The guidance range assumes: