Origin Energy Limited · ASX:ORG

Origin Energy — Shareholder Meeting (October 2009)

73 slides from Origin Energy's shareholder meeting presentation, Oct 30, 2009

  1. Slide 1: Annual General Meeting

    Annual General Meeting 30 October 2009

  2. Slide 2: Important Notice

    Important Notice This presentation does not constitute investment advice, or an inducement or recommendation to acquire or dispose of any securities in Origin, in any jurisdiction (including the USA). This presentation is for information purposes only, is in a summary form, and does not purport to b

  3. Slide 3: The Board

    origin The Board Together we can make a difference.™

  4. Slide 4: J Roland Williams CBE

    The Board J Roland Williams CBE Independent p Non-Executive Director 4

  5. Slide 5: Bruce G Beeren

    The Board Bruce G Beeren Non-Executive Director 5

  6. Slide 6: Trevor Bourne

    The Board Trevor Bourne Independent p Non-Executive Director 6

  7. Slide 7: Grant A King

    The Board Grant A King Managing g g Director 7

  8. Slide 8: Company Secretary

    Company Secretary Andrew C Clarke Company p y Secretaryy & Group p General Counsel 8

  9. Slide 9: Helen M Nugent AO

    The Board Helen M Nugent AO Independent p Non-Executive Director 9

  10. Slide 10: Gordon M Cairns

    The Board Gordon M Cairns Independent p Non-Executive Director 10

  11. Slide 11: Karen A Moses

    The Board Karen A Moses Executive Director Finance and Strategy gy 11

  12. Slide 12: John H Akehurst

    The Board John H Akehurst Independent p Non-Executive Director 12

  13. Slide 13: 13

    13

  14. Slide 14: Chairman's Address

    origin Chairman’s Address Together we can make a difference.™

  15. Slide 15: Share price performance

    Share price performance Origin Share Price Performance (Indexed to 100 from 1 November 2007) 200 sme SRP ASX 100 =m QRG 175 : 177 150 125 100 86 75 50 qT T T T T T T T Nov-Q7 Jan-08 Apr-08 Jul-08: Oct-08 Jan-09 Apr-0% Jul-d9 15 origin

  16. Slide 16: Record underlying profit of $530 million

    Record underlying profit of $530 million 16

  17. Slide 17: Earnings per share – up 19 per cent

    Earnings per share – up 19 per cent 17

  18. Slide 18: Strong balance sheet provides opportunity for future investments

    Strong balance sheet provides opportunity for future investments As at 30 September 2009 Undrawn Available Funding Committed Debt Capacity at 30 A$b Cash Facilities September 2009 5 4 (1.0) 3 4.4 2 3.4 1 0 18

  19. Slide 19: Origin invested over $2 billion in gas production and electricity generation projects

    Origin invested over $2 billion in gas production and electricity generation projects Kupe Darling Downs Power Station Mortlake turbine Cullerin Range Wind Farm 19

  20. Slide 20: Chairman's Address

    O origin Chairman’ s Address 20

  21. Slide 21: Renewable Energy Target provides increased certainty for investors

    Renewable Energy Target provides increased certainty for investors in renewable energy technologies Cullerin Range Wind Farm Solar Geodynamics G d Geodynamics i 21

  22. Slide 22: Chairman's Address

    O origin Chairman’ s Address 22

  23. Slide 23: Dealing with an uncertain future requires good governance

    Dealing with an uncertain future requires good governance 23

  24. Slide 24: Chairman's Address

    O origin Chairman’ s Address

  25. Slide 25: Investing in communities - our future customers, investors, employees and neighbours

    Investing in communities - our future customers, investors, employees p y and neighbours g Helping to educate 500,000 kids about using energy wisely 25

  26. Slide 26: Investing in communities - our future customers, investors, employees and neighbours

    Investing in communities - our future customers, investors, employees p y and neighbours g Building solid partnerships with landowners and communities 26

  27. Slide 27: Chairman's Address

    O origin Chairman’ s Address 27

  28. Slide 28: Managing Director's Address

    Managing Director’s Address 28

  29. Slide 29: Contribution to underlying earnings

    Contribution to underlying earnings • Origin’s O ’ EBITDAF ffor financial f l year 2009 was $1.2 billion • EBITDAF from Origin’s integrated business excluding Contact increased by $20 million t $850 million to illi • Contact’s contribution reduced 25% to $369 million * FY 2009 EBITDAF by Segment 29

  30. Slide 30: APLNG continues to grow its CSG reserves

    APLNG continues to grow its CSG reserves with significant reserves increases that demonstrate the size and quality of APLNG APLNG’ss CSG resource 3C 2C 3P 2P S Source: Origin O igi 30

  31. Slide 31: In New Zealand - the Kupe Gas Project is nearing completion

    In New Zealand - the Kupe Gas Project is nearing completion Kupe Gas Project onshore production facilities • Project construction essentially complete • Project handed over from construction team to operations team • Expecting to open the wells and bring raw gas ashore in December Quarter 2009 • Gro

  32. Slide 32: Generation: power station capacity has more than doubled in 2009

    Generation: power station capacity has more than doubled in 2009 Cullerin Range g Wind Farm,, NSW Uranquinty Power Station, NSW Quarantine Power Station, SA 32

  33. Slide 33: Mt Stuart Power Station expansion due for completion late calendar 2009

    Mt Stuart Power Station expansion due for completion late calendar 2009 Mt Stuart Power Station • Peaking power station being expanded from 288MW to 414MW • Townsville, Queensland • Currently kerosene-fired and capable of being g converted to natural gas g 33

  34. Slide 34: Darling Downs Power Station will be the largest CCGT plant in Australia

    Darling Downs Power Station - once commissioned - will be the largest CCGT plant in Australia • 630 MW Base Load plant • Largest CCGT plant in Australia • All gas turbines installed at site • Firing of first gas turbine expected in November 2009 • All three gas turbines synchronised to grid during D

  35. Slide 35: Mortlake Power Station will add significant generation capacity in Victoria

    Mortlake Power Station will add significant generation capacity in Victoria • 550 MW peaking ki plant l • Site currently being prepared and pipeline under construction • Turbines delivered ((as above)) • Expected to be completed in late 2010 • Designed for conversion to CCGT at a later stage if requ

  36. Slide 36: Energy retailing is the largest segment in our business today

    Energy retailing is the largest segment in our business today 36

  37. Slide 37: Retail Transformation

    Retail Transformation • Partnered with WIPRO to transition to an integrated SAP billing and customer management platform • Project expected to improve customer service and use of technology to engage with customers • Process improvement and business simplification activities have commenced • Deliver

  38. Slide 38: Transmission constraints

    Transmission Transmission constraints and unusual weather conditions adversely constraints impacted Contact in New Zealand • Two high voltage DC cables (Poles 1 and 2) connect the North and South So th Islands • Pole 1 was unexpectedly removed from service in November 2007 resulting in the Transmiss

  39. Slide 39: Projects to restore flexibility back into Contact's portfolio are on track

    Projects to restore flexibility back into Contact’s portfolio are on track for commercial operation p in mid-2010 Stratford peakers (200 MW) Ahuroa gas storage • Adds flexible generation capacity. Replaces • Adds flexibility to gas supply by storing gas New Plymouth with new technology fast- during

  40. Slide 40: Renewables Energy Target will drive significant investment in wind power generation

    The Renewables Energy Target will drive significant investment in wind power generation and will require a significant capacity of peaking ki generation ti tto bbe b built ilt tto supportt it its iintermittency… t itt Forecast Additional NEM Generation by • Wind is currently the most cost effective

  41. Slide 41: Significant offshore exploration programme targeting substantial reserves increases

    In the coming year Origin has committed to a significant offshore exploration programme targeting substantial reserves increases near domestic markets in AAustralia stralia and Ne New Zealand Northland Basin Origin, as Operator of permit PEP 38619, has secured the semi submersible rig “Kan Kan Tan I

  42. Slide 42: APLNG is progressing well with the development of its CSG to LNG project

    APLNG is progressing well with the development of its CSG to LNG project p j and has now selected a site at Gladstone for its downstream operations • APLNG has secured the Laird Point site on Curtis Island in the Port of Gladstone for its proposed CSG to LNG plant • 230 hectare site that is well pos

  43. Slide 43: Managing Director's Address

    Managing Director’s Address 43

  44. Slide 44: Chairman's Address

    origin Chairman’ s Address Together we can make a difference.™

  45. Slide 45: Financial Statements

    origin Financial Statements Together we can make a difference.™

  46. Slide 46: Resolution 2: Adoption of Remuneration Report

    Resolution 2: Adoption p of Remuneration Report 46

  47. Slide 47: Resolution 2: Adoption of Remuneration Report Proxy votes received

    Resolution 2: Adoption of Remuneration Report Proxy votes received: For 395,982,877 Against 19,302,311 Open 15,463,025 Abstain 2 744 625 2,744,625 47

  48. Slide 48: 48

    48

  49. Slide 49: Resolution 3: Election of Directors

    Resolution 3: Election of Directors 49

  50. Slide 50: Resolution 3: Trevor Bourne

    Resolution 3 Trevor Bourne Independent p Non-Executive Director 50

  51. Slide 51: Resolution 3: Election of Director – Trevor Bourne Proxy votes received

    Resolution 3: Election of Director – Trevor Bourne Proxy votes received: For 413,842,376 Against 3,114,480 Open 15,522,675 Abstain 1 016 414 1,016,414 51

  52. Slide 52: 52

    52

  53. Slide 53: Resolution 3: Election of Directors

    Resolution 3: Election of Directors 53

  54. Slide 54: Resolution 3: Helen M Nugent AO

    Resolution 3 Helen M Nugent AO Independent p Non-Executive Director 54

  55. Slide 55: Resolution 3: Election of Director – Helen Nugent Proxy votes received

    Resolution 3: Election of Director – Helen Nugent Proxy votes received: For 413,875,037 Against 3,119,166 Open 15,518,398 Abstain 983 344 983,344 55

  56. Slide 56: 56

    56

  57. Slide 57: Resolution 3: Election of Directors

    Resolution 3: Election of Directors 57

  58. Slide 58: Resolution 3: John H Akehurst

    Resolution 3 John H Akehurst Independent p Non-Executive Director 58

  59. Slide 59: Resolution 3: Election of Director – John Akehurst Proxy votes received

    Resolution 3: Election of Director – John Akehurst Proxy votes received: For 414,733,289 Against 2,048,124 Open 15,633,659 Abstain 1 080 873 1,080,873 59

  60. Slide 60: 60

    60

  61. Slide 61: Resolution 3: Election of Directors

    Resolution 3: Election of Directors 61

  62. Slide 62: Resolution 3: Karen A Moses

    Resolution 3 Karen A Moses Executive Director Finance and Strategy gy 62

  63. Slide 63: Resolution 3: Election of Director – Karen Moses Proxy votes received

    Resolution 3: Election of Director – Karen Moses Proxy votes received: For 412,203,967 Against 3,185,612 Open 16,942,573 Abstain 1 157 509 1,157,509 63

  64. Slide 64: 64

    64

  65. Slide 65: Resolutions 4 and 5: Grant of Options and Performance Share Rights

    Resolutions 4 and 5: Grant of Options p and Performance Share Rights 65

  66. Slide 66: Resolution 4: Grant of Options and Performance Share Rights to Grant A King

    Resolution 4: Grant of Options p and Performance Share Rights to Grant A King – Managing Director 66

  67. Slide 67: Resolution 4: Grant of Options and Performance Share Rights to Mr Grant A King

    Resolution 4: Grant of Options and Performance Share Rights to Mr Grant A King – Managing Director To consider and, if thought fit, pass the following resolution as an ordinary resolution: “That to satisfy the Company’s decision to deliver Managing Director Mr Grant King with a long term incentive f

  68. Slide 68: Resolution 4: Proxy votes received

    Resolution 4: Grant of Options and Performance Share Rights to Mr Grant A King – Managing Director Proxy votes received: For 394,151,263 Against 20,849,007 Open 8,760,233 Abstain 2 620 894 2,620,894 68

  69. Slide 69: 69

    69

  70. Slide 70: Resolution 5: Grant of Options and Performance Share Rights to Ms Karen Moses

    Resolution 5: Grant of Options p and Performance Share Rights to Ms Karen Moses – Executive Director 70

  71. Slide 71: Resolution 5: Grant of Options and Performance Share Rights to Ms Karen Moses

    Resolution 5: Grant of Options and Performance Share Rights to Ms Karen Moses – Executive Director To consider and, if thought fit, pass the following resolution as an ordinary resolution: “That to satisfy the Company’s decision to deliver Executive Director Ms Karen Moses with a long term incentive

  72. Slide 72: Resolution 5: Proxy votes received

    Resolution 5: Grant of Options and Performance Share Rights to Ms Karen Moses – Executive Director Proxy votes received: For 393,806,139 Against 21,145,140 Open 8,756,927 Abstain 2 617 090 2,617,090 72

  73. Slide 73: Annual General Meeting

    30 October 2009 Annual General Meeting

Origin Energy — Shareholder Meeting (October 2009) on 6ix