Pepco Holdings Inc

Pepco — 46th EEI Financial Conference 2011

33 slides from Pepco's conference presentation, Nov 4, 2011

  1. Slide 1: 46th EEI Financial Conference

    ORLANDO, FL • NOVEMBER 6 - 8, 2011 46th EEI Financial Conference

  2. Slide 2: Safe Harbor Statement/Regulation G Information

    Safe Harbor Statement/Regulation G Information Some of the statements contained in today’s presentation with respect to Pepco Holdings, Pepco, Delmarva Power and Atlantic City Electric, and each of their respective subsidiaries, are forward-looking statements within the meaning of the U.S. federal s

  3. Slide 3: PHI's Strategic Focus

    PHI’s Strategic Focus Power Delivery • Invest in T&D infrastructure • Focused on reliability and operational excellence • Implement Blueprint for the Future – advanced Operating Income Business Mix metering infrastructure (AMI), energy efficiency, Forecasted 2011-2015 demand response, decoupling • A

  4. Slide 4: Reliability Enhancement Plan – Improving System Reliability is a Top Priority

    Reliability Enhancement Plan – Improving System Reliability is a Top Priority • Our focus in 2011 has been primarily in Pepco’s service territory • Our progress since last fall*: – Tree Trimming – Trimmed along more than 2,600 miles of power lines to remove limbs that threatened our equipment; 73% o

  5. Slide 5: Hurricane Irene – Storm Response

    Hurricane Irene – Storm Response • Hurricane Irene hit our service territory in late August 2011 with high winds and driving rain • Approximately 445,000 customers (~25% of total electric customers) were without power at the height of the storm • 98% of customers were restored within just over two d

  6. Slide 6: Hurricane Irene – Estimated Incremental Cost

    Hurricane Irene – Estimated Incremental Cost Estimated Deferred/ Capital O&M Expense (Millions of Dollars) Total Cost* Regulatory Asset Atlantic City Electric $12.7 $5.2 $ – $7.5 Delmarva Power Delaware 4.9 1.4 3.5 – Maryland 6.9 1.9 – 5.0 Pepco District of Columbia 3.8 1.5 2.3 – Maryland 18.5 7.0 –

  7. Slide 7: Pepco – Maryland Reliability Case 9240

    Pepco – Maryland Reliability Case 9240 • Related to power outages caused by severe weather in Pepco’s service territory in 2010 • Public Service Commission initiated the proceeding for Pepco in August 2010 to investigate the reliability of the electric distribution system and the quality of service

  8. Slide 8: Power Delivery - O&M

    Power Delivery - O&M 2011 Original 2011 Projection Forecast as of as of Reason for Increase (Millions of Dollars) April 2011 November 2011 Increased reliability initiatives and system restoration Base $ 697 $ 770 activities; higher employee- related and Power Delivery support costs Major Storms (inc

  9. Slide 9: Advanced Metering Infrastructure – Status by Jurisdiction

    Advanced Metering Infrastructure – Status by Jurisdiction Pepco Delmarva Power Atlantic City Electric DC MD MD DE NJ  60% complete; to be  4% complete; to be  Business case  99% complete  Deferred Electric meter completed 1Q2012 completed 4Q2012 submitted, awaiting  Regulatory asset  Regulato

  10. Slide 10: Mid-Atlantic Power Pathway – Project Update

    Mid-Atlantic Power Pathway – Project Update • PJM provided notice to PHI on August 18th that the MAPP project in-service date will be delayed until 2019 - 2021 • PHI suspended most permitting, engineering, and environmental studies • Maryland PSC approved our request to delay the procedural schedule

  11. Slide 11: Capital Expenditures Forecast – Updated November 2011

    Capital Expenditures Forecast – Updated November 2011 (Millions of Dollars) 2012 2013 2014 2015 2016 5 Year Total Distribution: Customer Driven (new service connections, $ 126 $ 138 $ 131 $ 137 $ 135 $ 667 m eter installations, highw ay relocations) Reliability 399 431 422 421 420 2,093 (facility re

  12. Slide 12: Forecast Capital Expenditures Comparison

    Forecast Capital Expenditures Comparison (Millions of Dollars) 2012 2013 2014 2015 2016 April 2011 * $ 1,169 $ 1,052 $ 1,030 $ 893 N/A November 2011 * 1,143 1,044 1,082 1,023 1,327 Change $ (26) $ (8) $ 52 $ 130 N/A Key Drivers of Change in Power Delivery Capital Forecast 2012 - 2015 MAPP - Delayed

  13. Slide 13: Distribution Rate Cases – Pending Pepco – District of Columbia

    Distribution Rate Cases – Pending Pepco – District of Columbia Case No. 1087 Procedural Pepco - DC Schedule (Millions of Dollars) 6 mos. actual 6 mos. Initial Filing Date 7/8/11 Test Year forecast ended 9/30/11 Intervenors Testimony 12/7/11 Adjusted Rate Base $1,167.5 Rebuttal Testimony 1/16/12 Equi

  14. Slide 14: Distribution Rate Cases – Pending Atlantic City Electric – New Jersey

    Distribution Rate Cases – Pending Atlantic City Electric – New Jersey Docket No. ER11080469 (Millions of Dollars) ACE - NJ Initial Filing Date 8/5/11 3 mos. actual 9 mos. Test Year forecast ending 12/31/11 Adjusted Rate Base $922.6 Equity Ratio 49.1% Return on Equity (ROE) 10.75% Revenue Requirement

  15. Slide 15: Delmarva Power – Maryland Phase II (Regulatory Lag) Case 9249

    Delmarva Power – Maryland Phase II (Regulatory Lag) Case 9249 • Following the settlement of Delmarva Power’s base rate case in July 2011, the Commission approved the establishment of a Regulatory Lag Working Group • Charged with examining the need for and design of any regulatory lag mechanism; meet

  16. Slide 16: Distribution Rate Cases – The Current Cycle

    Distribution Rate Cases – The Current Cycle • Filing Cycle Status – Pepco DC Pending - Filed July 2011 – Atlantic City Electric NJ Pending - Filed August 2011 – Delmarva Power DE - Electric Filing targeted for December 2011 – Delmarva Power MD Filing targeted for December 2011 – Pepco MD Filing targ

  17. Slide 17: Pepco Energy Services – Overview

    Pepco Energy Services – Overview • PES provides retail energy services to large customers – Government – Institutional • Energy Efficiency – PES is a leading developer of energy efficiency projects – Since 1995, completed $1 billion of energy efficiency projects • Combined Heat and Power (CHP)/Therm

  18. Slide 18: Pepco Energy Services – Energy Services Earnings Components

    Pepco Energy Services – Energy Services Earnings Components • DE Technical Community College $21 million Construction: Energy Services • Maryland Port Authority Contract Backlog and Combined Heat and Power • Other universities, state agencies and 10-month weighted municipal governments average* Oper

  19. Slide 19: Pepco Energy Services – Business Development and Marketing Update

    Pepco Energy Services – Business Development and Marketing Update (Millions of Dollars) • PES has signed $82 million of energy efficiency Contracts Signed - 2011 YTD Value contracts year-to-date Maryland Port Administration $27 • Project development pipeline has grown to $511 Virginia Dept. of Milit

  20. Slide 20: Pepco Energy Services – Typical Energy Efficiency Project

    Pepco Energy Services – Typical Energy Efficiency Project PES recently signed an $11.2 million energy performance contract with the Commonwealth of Virginia for the Department of Military Affairs (DMA) • Project (Phase 1) – PES will implement 14 energy conservation measures including lighting retrof

  21. Slide 21: Pepco Energy Services – Update of Retail Supply Wind Down/Power Plant Retirement

    Pepco Energy Services – Update of Retail Supply Wind Down/Power Plant Retirement • PES is on track in winding down this Key Metrics 2011 YTD 2010 2009 business; the retail energy supply Load Served - MW 1,446 2,011 3,195 MWh Delivered* 5.7 11.6 17.8 contracts completely roll off by 2014 Dths Deliver

  22. Slide 22: Cross-Border Energy Lease Status

    Cross-Border Energy Lease Status • Equity investment as of September 30, 2011 of $1.3 billion • Annual tax benefits of $52 million • Annual net earnings of $21 million • Current Status: – IRS audit settlement approved in November 2010 for the 2001/2002 periods; disallowed net losses on the cross-bor

  23. Slide 23: Earnings Per Share Variance – Third Quarter

    Earnings Per Share Variance – Third Quarter Three Months Ended September 30, Power Pepco Energy Other Non- Corporate Total Delivery Services Regulated and Other PHI 2010 Net Income excluding Special Items - Continuing $ 0.41 $ 0.03 $ 0.04 $ 0.04 $ 0.52 Operations 1/ 2/ Change from 2010 Net Income ex

  24. Slide 24: Earnings Per Share Variance – Year-to-Date

    Earnings Per Share Variance – Year-to-Date Nine Months Ended September 30, Power Pepco Energy Other Non- Corporate Total Delivery Services Regulated and Other PHI 2010 Net Income/(Loss) excluding Special Items - Continuing $ 0.79 $ 0.14 $ 0.09 $ (0.03) $ 0.99 Operations 1/ 2/ Change from 2010 Net In

  25. Slide 25: 2012 Financing Activity

    2012 Financing Activity • Utility long-term debt issuance of $350 - $450 million • Equity issuance target of $250 - $350 million; may include the following: – Forward sale – Secondary offering – Continuous equity program • Dividend Reinvestment Plan (approximately $40 million) Note: See Safe Harbor

  26. Slide 26: 2011 Earnings Guidance

    2011 Earnings Guidance Earnings Per Share The guidance range excludes: $1.40 $1.24 $1.15 - $1.25 • Discontinued operations $1.20 • The net mark-to-market effects of economic hedging activities at Pepco Energy Services $1.00 • The impact of a tax law change to adopt a $0.80 unitary tax in DC $0.60 Th

  27. Slide 27: Delivering Value

    Delivering Value • Stable Earnings Base – Derived primarily from regulated utility business • Long-term Earnings Growth – Driven by T&D utility infrastructure investments and constructive regulatory outcomes • Secure Dividend – Attractive dividend yield • Solid Investment Grade Credit Ratings – Impr

  28. Slide 28: Appendix

    Appendix A Pepco Holdings inc

  29. Slide 29: Cross-Border Energy Lease Portfolio

    Cross-Border Energy Lease Portfolio (Millions of Dollars) Potomac Capital Investment (PCI) Investment Book Value Book Value Year Country Asset Description Expiration September 30, 2011 December 31, 2010 1994 * Netherlands Multi-Fuel-Fired Generation (210 MW) 2017 $ - $ 99 1995 Australia Coal-Fired G

  30. Slide 30: Distribution Rate Cases – Recent Decision Delmarva Power – Maryland

    Distribution Rate Cases – Recent Decision Delmarva Power – Maryland Delmarva Power MD Electric Case - Case No. 9249 (Millions of Dollars) Final Filed Position Approved Date 5/10/11 7/8/11 Adjusted Rate Base $343.8 Not specified Equity Ratio 49.81% Not specified Return on Equity 10.75% Not specified

  31. Slide 31: Distribution Rate Cases – Recent Decision Delmarva Power – Delaware Gas

    Distribution Rate Cases – Recent Decision Delmarva Power – Delaware Gas Delmarva Power DE Gas Case - Docket 10-237 (Millions of Dollars) Final Filed Position Approved Date 12/3/10 6/21/11 Adjusted Rate Base $236.5 Not specified Equity Ratio 48.3% 48.3% Return on Equity 11.0% 10.0% Revenue Requiremen

  32. Slide 32: Reliability Standards

    Reliability Standards Maryland (PSC – RM43) – Rulemaking proceeding applying to all electric utilities in the state • Working group met weekly through October 2011 • Staff report with recommendations issued October 27, 2011; benchmarks proposed for: – Service interruption – Downed wire response – Cu

  33. Slide 33: Reconciliation of GAAP Earnings to Earnings Excluding Special Items

    Reconciliation of GAAP Earnings to Earnings Excluding Special Items Three Months Ended Nine Months Ended Twelve Months Ended Net Earnings from Continuing Operations – Millions of Dollars September 30, 2010 September 30, 2010 December 31, 2010 Reported (GAAP) Net Earnings from Continuing Operations $

Pepco Holdings — 46th EEI Financial Conference 2011 on 6ix