Boral — Corporate Update (November 2022)
28 slides from Boral's corporate update, Nov 25, 2022
Slide 1: Teven Community Consultative Committee Meeting
Click to edit Master title style Subheader Teven Community Consultative Committee Meeting Teven Quarry 25 November 2022
Slide 2: Agenda
Agenda 1. Welcome and apologies 2. Operations summary 3. Environmental works update 4. Planning and projects 5. Communications update 6. General business and contacts 7. Next meeting 2
Slide 3: Welcome and apologies
01 Welcome and apologies
Slide 4: Attendees
Attendees CCC representatives Denis Perkins (resident) Peter Blackwood (resident) Boral staff Phil ‘Dick’ Pallisier, Quarry Manager, Boral Teven Quarry Rod Johnson, Environment Business Partner, Boral HSE (NSW and ACT) Kate Woodbridge, Stakeholder Relations Manager NSW and ACT 4
Slide 5: Review of minutes and actions arising from last meeting
Review of minutes and actions arising from last meeting ˃ Matters arising from last meeting • Meet with Council regarding the state of the North Teven and Beacon Roads – wrote to Council on two occasions regarding the state of the roads and it being a safety issue. • Invite Council representatives t
Slide 6: Operations review
Operations review
Slide 7: Quarry development: basalt pit
Quarry development: basalt pit We are currently looking at reshaping the northem wall of the basalt pit to create a new north ‘ramp’, allowing usto extractthe existing central ramp.
Slide 8: This section is well underway
THIS SECTION IS WELL UNDERWAY
Slide 9: Stripping Sep-Oct 21
a STP — 12+ Month Extraction Blocks BTQ-2110 Ss "4{ BTQ-2304 Pathe BTo.2105 aay BTQ-2303
Slide 10: Operations
Operations ˃ New dust suppression unit operating well ˃ Sales are steady to Flood recovery. ˃ No major safety incidence onsite ˃ We are tendering on the Ballina airport upgrade approx. 32000 t ˃ We are currently upgrading the site facilities ˃ The primary wall upgrade will commence in March-April 20
Slide 11: Environmental Works Update
03 Environmental Works Update
Slide 12: Deposited Dust
Environmental monitoring – Deposited Dust 12
Slide 13: Deposited Dust
Environmental monitoring – Deposited Dust Annual Average Dust Deposition (Insoluble Solids) 0.73 g / m2 / month 13
Slide 14: Deposited Dust
Environmental monitoring – Deposited Dust Annual Average Dust Deposition (Insoluble Solids) 0.90 g / m2 / month 14
Slide 15: Deposited Dust
Environmental monitoring – Deposited Dust Annual Average Dust Deposition (Insoluble Solids) 3.05 g / m2 / month 15
Slide 16: Deposited Dust
Environmental monitoring – Deposited Dust Annual Average Dust Deposition (Insoluble Solids) 1.15 g / m2 / month 16
Slide 17: Blast Overpressure
Environmental monitoring – Blast Overpressure 17
Slide 18: Blast Vibration
Environmental monitoring – Blast Vibration 18
Slide 19: Surface Water Discharge
Environmental monitoring – Surface Water Discharge NO Surface water discharge in period 19
Slide 20: Surface Water Discharge
Environmental monitoring – Surface Water Discharge NO Surface water discharge in period 20
Slide 21: Weed Management
Environmental monitoring – Weed Management 21
Slide 22: Environmental monitoring: BSC compliance audit
Environmental monitoring • BSC Compliance Audit • Ballina Shire Council undertook an Environmental Compliance Audit onsite in November. • No major issues raised by Council. • Request to supply a separate Annual Environmental Report • Undertake an audit of Bunding of oils and chemicals onsite 22
Slide 23: Communications update
04 Communications update
Slide 24: Whole of Community meeting and road repairs
• The CCC met on 9 May to discuss the postponement of the Whole of Community meeting due to damage at the quarry after severe flooding at the site. • Due to continued wet weather in the region for most of the year a new date for the WoC meeting needs to be found for early 2023 – July?. • Kate wrote
Slide 25: General business and contacts
05 General business and contacts
Slide 26: General business and contacts
General business and contacts Items of general business Boral Quarries Teven contacts: ˃ Phil (Dick) Pallisier Quarry Manager 6687 8360/ 0427 600 194/ [email protected] ˃ Kate Woodbridge Stakeholder Relations Manager 0401 893 815/ [email protected] ˃ www.boral.com.au/tevenqua
Slide 27: Next meetings
06 Next meetings Next CCC meeting – July 2023 Next ‘Whole of Community’ meeting July 2023
Slide 28: Thanks for your participation
Thanks for your participation 28