Orica Limited · ASX:ORI

Orica — Corporate Update (February 2015)

19 slides from Orica's corporate update, Feb 23, 2015

  1. Slide 1: Community Reference Group Meeting

    COMMUNITY REFERENCE GROUP MEETING 23 February 2015 Orica Kooragang Island

  2. Slide 2: Welcome and Introductions

    WELCOME AND INTRODUCTIONS Interested Stockton resident • Emma McCauley EPA • Hamish Rutherford, Senior Operations Officer Orica • Paul Hastie, Orica KI Operations Manager • Kylie Cooper, Community Relations Advisor • Nicole Masson, Hunter Media Advisor • Sherree Woodroffe, Environment and Community

  3. Slide 3: Contents

    CONTENTS • Site Status • Guest Speaker – Hamish Rutherford EPA • AMI update • Planning for 2015 CRG program • Key Points from Community SHEC Reports in last quarter • Community Update • Other Business • Summarise discussion points for sharing with the community • Review of outstanding meeting action

  4. Slide 4: Acceptance of Previous Meeting Notes

    ACCEPTANCE OF PREVIOUS MEETING NOTES Meeting notes were sent by email on 19 December for November meeting 4 © Orica Limited Group

  5. Slide 5: Site Update

    SITE UPDATE Paul Hastie 5 © Orica Limited Group

  6. Slide 6: EPA Briefing

    EPA BRIEFING Hamish Rutherford 6 © Orica Limited Group

  7. Slide 7: Ammonia Management Improvement Program

    AMMONIA MANAGEMENT IMPROVEMENT PROGRAM Antony Taylor 7 © Orica Limited Group

  8. Slide 8: AMI Update

    AMI UPDATE 8 © Orica Limited Group

  9. Slide 9: Planning for 2015 CRG Program

    PLANNING FOR 2015 CRG PROGRAM Kylie Cooper 9 © Orica Limited Group

  10. Slide 10: Community SHEC Report Summary

    COMMUNITY SHEC REPORT SUMMARY Sherree Woodroffe 10 © Orica Limited Group

  11. Slide 11: Community SHEC Report Summary

    COMMUNITY SHEC REPORT SUMMARY Injury • One injury which required medical treatment during the quarter, with a worker receiving a small cut during scaffold construction that required suturing Environmental Compliance • There were no environmental non-compliances during the period • Effluent temperatu

  12. Slide 12: Community SHEC Report Summary

    COMMUNITY SHEC REPORT SUMMARY Environmental Projects • The NAP2 drainage program was completed in late 20142014, providing double containment on potential acid containing solutions • Two new new, fully bunded tanks were installed in December to replace two tanks that did not meet current bunding req

  13. Slide 13: Community SHEC Report Summary

    COMMUNITY SHEC REPORT SUMMARY Arsenic Management Order Update • Field work to further delineate the contamination and geotechnical properties of the remediation area commences this week • Work has commenced on refining an existing groundwater model to assist in design • A communication strategy was

  14. Slide 14: Community Update

    COMMUNITY UPDATE Kylie Cooper 14 © Orica Limited Group

  15. Slide 15: Community Investment Program

    COMMUNITY INVESTMENT PROGRAM Next round opens 1 March and closes 31 March African/Australian Refugee Water Safety Program concluded with beach safety workshop Orica Kermesse in 10th year. year Saturday 7 March 2015 at HEZ 15 © Orica Limited Group

  16. Slide 16: Sponsorships

    SPONSORSHIPS Orica Kermesse in 10th year. Saturday 7 March 2015 at HEZ Orica Team Challenge at Surfest was a success 16 © Orica Limited Group

  17. Slide 17: Other Business

    OTHER BUSINESS All 17 © Orica Limited Group

  18. Slide 18: Other Business

    OTHER BUSINESS AN Truck on Industrial Drive – Thursday 19 February 2015 18 © Orica Limited Group

  19. Slide 19: Action Review

    ACTION REVIEW Kylie Cooper 19 © Orica Limited Group

Orica — Corporate Update (February 2015) on 6ix