Slide 1: Mt. Hope and Liberty Asset Tour
Mt. Hope and Liberty Asset Tour September 10, 2008 The Right Moly Investment
Slide 2: Forward Looking Statements
Forward Looking Statements 2 This presentation contains “forward-looking statements” within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended that are intended to be covered by the safe harbor created by such sect
Slide 3: Mt. Hope – Engineering Progress and Costs
Mt. Hope – Engineering Progress and Costs 3 • Direct Labor: More accurately reflects actual wages, benefits, and overhead required to construct in Eureka, NV • Indirect labor: Now more accurately reflects correct level of construction management and construction support facilities • Materials/Freigh
Slide 4: Mt. Hope – Engineering Progress and Operating Costs
Mt. Hope – Engineering Progress and Operating Costs 4 Mt. Hope Operating Cost anticipated to increase to $5.30-$5.80 per pound Molybdenum from $4.42 per pound in BFS Energy-related costs account for 70% of overall increase •Diesel fuel increase accounts for more than 1/3 of total cost increase •Dies
Slide 5: Corporate Transactions: Off-take arrangements provide price protection
Corporate Transactions: Off-take arrangements provide price protection 5 11.5M annual pounds committed with price protection that includes: • A hard floor price approaching $15 per pound on average; • PPI escalation annually; • A modest discount to customer above floor price
Slide 6: Corporate Transactions - Financing Plan
Corporate Transactions - Financing Plan 6 Total Hard Capital (100% basis)1: $1,000 - $1,080 Million Working Capital, Deposits: + $100 - $150 Million Total Requirements for Mt. Hope: $ 1,100 - $1,230 Million Spent to Date: $50 Million POSCO Initial Contribution: + $170 Million General Moly Cash on Ha