Paladin Energy Ltd · ASX:PDN

Paladin Energy — Australian Uranium and Rare Earths Conference 2013

29 slides from Paladin Energy's conference presentation, Jul 17, 2013

  1. Slide 1: Uranium Mining - An Industry in Crisis

    Langer Heinrich Mining Operation URANIUM MINING - AN INDUSTRY IN CRISIS John Borshoff, Managing Director/CEO Australian Uranium and Rare Earths Conference 16-17 July 2013

  2. Slide 2: Uranium outlook

    Uranium outlook Company status & highlights Operations update Paladin outlook 1

  3. Slide 3: World Nuclear Capacity – June 2013

    World Nuclear Capacity – June 2013 “Fukushima is behind us” Demand is confirmed Current Under Planned Proposed Nuclear Construction Capacity Reactors / 435 68 162 316 (Capacity) (371.9GWe) (71.2GWe) (183.0GWe) (358.7GWe) Countries 30 13 28 37 China 17 28 49 120 (14.0GWe) (30.6GWe) (56.0GWe) (123.0GW

  4. Slide 4: Industry Situation Unsustainable

    Industry Situation Unsustainable When you have a situation 1. Demand essentially sorted and quantified post Fukushima. 2. Current low prices make it impossible to achieve 2020 supply target. Supply industry in disarray. 3. Effective moratorium in place unless the critical US$70/lb threshold is achie

  5. Slide 5: Supply/Demand Unbalanced

    Supply/Demand Unbalanced supply shortfall will widen A supply shortage is unavoidable post 2013-14 Long lead times will severely limit achieving 2020 supply targets — average lead time to full production 6 to 9 years — insufficient projects able to bring sufficient new production online rapidly Pric

  6. Slide 6: Supply Growth Uncertainty

    Supply Growth Uncertainty The impossible challenge : Primary supply will have to increase by circa 90Mlb U3O8 pa to meet 2020 requirements (in 7 years) In previous 7-year period (2005 – 2012), production increased only by 48Mlb, and Kazakhstan accounted for ~40Mlb NO OTHER “KAZATOMPROM” OR PALADIN O

  7. Slide 7: Project Development Costs

    Project Development Costs Significant CAPEX blowout over the past 8 years US$ per Annual lb Production $250 Forecast $200 Actual $150 $100 $50 $0 Design 2007/8 LHU 2011 2012 LHU Husab Toro Mkuju Criteria Stage 1 + 2 Kayelekera Stage 3 Capital $170M $300M $170M $2.5B $280M $700M Capacity 3.7Mlb/a 3.3

  8. Slide 8: Presentation Outline

    Presentation Outline Uranium outlook Company status & highlights Operations update Paladin outlook 7

  9. Slide 9: Disclaimer and Notes for JORC and NI 43-101 Mineral Resources and Ore Reserves

    Disclaimer and Notes for JORC and NI 43- 101 Mineral Resources and Ore Reserves This presentation includes certain statements that may be deemed “forward-looking statements”. All statements in this presentation, other than statements of historical facts, that address future production, reserve or re

  10. Slide 10: Quarterly/Annual Highlights

    Quarterly/Annual Highlights Safety Maintained low Lost Time Injury Frequency Rate June Qtr – US$107M/2.33Mlb at US$46.22 Sales Annual (FY13) - US$408M/8.25Mlb at US$49.82/lb average Quarterly combined production 2.142Mlb Production FY13 production 8.255Mlb (97% of total design capacity) Production o

  11. Slide 11: Paladin – Turning Vision Into Reality

    Paladin – Turning Vision Into Reality LHM construction LHM production (Mlb)  Clear commitment KM construction KM production (Mlb)  Steady growth, now at 8.0Mlb-8.5MIb pa capacity Annual growth 20%-  Applied new process 8.2 - 8.70 40% over 6 years of 8.26 technology 6.89 Developing the production

  12. Slide 12: Current Price Will Not Incentivise New Production

    Current Price Will Not Incentivise New Production Paladin decision to proceed with construction Global Financial Crisis Fukushima Disaster - 1 1 - 11

  13. Slide 13: Geographically Diverse Project Pipeline

    Geographically Diverse Project Pipeline 12

  14. Slide 14: Uranium outlook

    Uranium outlook Company status & highlights Operations update Paladin outlook 13

  15. Slide 15: Langer Heinrich Project

    Langer Heinrich Project Three successful production capacity Design Criteria Stage 2 Stage 3 Actual Design FY13 expansions completed: Ore Throughput 2.5Mtpa 3.5Mtpa 3.54Mtpa — 5.2Mlb with Stage 3 starting mid 2012 — currently producing above design Leach Throughput 1.5Mtpa 2.1Mtpa 1.99Mtpa Ore Feed

  16. Slide 16: Langer Heinrich Quarterly Production

    Langer Heinrich Quarterly Production Stage 3 Capacity 15

  17. Slide 17: Kayelekera Project

    Kayelekera Project Production capacity of 3.3Mlb U3O8 pa Design Criteria Design Actual FY13 Ore Throughput 1.5Mtpa 1.3Mtpa Achieved 97% nameplate in June 2013 quarter Ore Feed Grade 1150ppm 1143ppm First modern resin-in-pulp (RIP) uranium Recovery 87% 84.6% processing facility U3O8 Production 3.3Mlb

  18. Slide 18: Kayelekera Quarterly Production

    Kayelekera Quarterly Production KM Quarterly Production and Feed Grade Design Capacity 16 days planned maintenance1 1 Equates to 135,000lb reduced production 17

  19. Slide 19: Uranium outlook

    Uranium outlook Company status & highlights Operations update Paladin outlook 18

  20. Slide 20: Strategic Initiative

    Strategic Initiative The Paladin platform becoming increasingly more attractive as uranium supply stagnates Key objectives from the strategic initiatives - unlock value from Paladin’s extensive uranium asset base and accomplishments - utilise current platform for future growth leverage with the assi

  21. Slide 21: Positioned for the Future

    Positioned for the Future First phase of growth complete — 8.5Mlb of installed production capacity — pipeline established Site cost and corporate overhead reduction well advanced Continuation of optimisation and innovation — production innovation and optimisation for continued unit cost reduction —

  22. Slide 22: Key Takeaways

    Key Takeaways Uranium specialist company with demonstrated achievements — only company in world outside Kazatomprom to have delivered new uranium mines — has established a strong and positive reputation in industry Mining — installed nameplate capacity of 8.5Mlb pa — operations de-risked with improv

  23. Slide 23: Paladin Energy Ltd Contact Details

    Paladin Energy Ltd Contact Details Head Office Level 4, 502 Hay Street Subiaco Western Australia 6008 PO Box 201, Subiaco Western Australia 6904 Telephone: +61 (0) 8 9381 4366 Facsimile: +61 (0) 8 9381 4978 Email: [email protected] Website: www.paladinenergy.com.au Investor Relations Team

  24. Slide 24: Paladin - A Modern Uranium Company

    Paladin - A Modern Uranium Company Uranium specialist company with demonstrated achievements — employs 1,800 staff and contractors — top 10 producer in the world — founded 1994, head office in Perth Mining X — mines in Namibia and Malawi — installed production capacity of 8.5Mlb U3O8 pa — operations

  25. Slide 25: Company Status and Highlights

    Company Status and Highlights Safety Performance - - continued high safety performance Kayelekera achieved a milestone 459 days LTI free to end June 2013 X Operational Highlights - combined production for FY13 8.255Mlb, up 19.8% on previous year - positive June quarter results Sustainable Cost Savin

  26. Slide 26: Nuclear Outlook Positive

    Nuclear Outlook Positive key drivers Japan – sorting out schedule for re-starts Liberal Democratic Party (LDP) elected Dec 2012 reversed 2040 phase out policy – LDP expected to win upper house July 2013. Unique opportunity to accelerate reactors starts Paladin’s detailed assessment of Japanese react

  27. Slide 27: Major Global Uranium Mining Companies

    Major Global Uranium Mining Companies industry unprepared to deal with the supply challenge Government (vertically integrated) agencies: (3) — — — ARMZ (UUU included) Areva CGNPC ] battling growth ] have stumbled with new projects ] new miner – risks associated X Government (mining companies only) a

  28. Slide 28: Paladin – Positioned for Advantage

    Paladin – Positioned for Advantage Why Paladin is positioned to take advantage of the current outlook? Unique intellectual property — experienced and committed management team X — technical team with the capability to develop new projects in challenging and complex environments — sector leader in te

  29. Slide 29: Conclusion

    Conclusion Paladin on track to continue solid production results – FY14 guidance 8.2-8.7Mlb Focused on further cost rationalisation X Production optimisation through innovation to improve efficiency Strategic initiatives to reduce debt and strengthen the balance sheet Paladin’s pipeline projects – r

Paladin Energy — Australian Uranium and Rare Earths Conference 2013 on 6ix