  1. Slide 1: STRABAG SE – Capital Markets Day

    STRABAG SE – 24 October 2008 Capital Markets Day

  2. Slide 2: Disclaimer

    Disclaimer This presentation is made by STRABAG SE (the "Company") solely for use at investor meetings and is furnished to you solely for your information. This presentation speaks as of October 2008. The facts and information contained herein might be subject to revision in the future. Neither the

  3. Slide 3: Today's Schedule

    Today’s Schedule 11:00 a.m. – 11:45 a.m. Reception and breakfast 11:45 a.m. – 12.30 a.m. Presentation by Roland Jurecka, STRABAG SE Management Board “Update on Tunnelling Technology – Introduction to the Project Perschling” 12:30 a.m. – 2.30 p.m. Lunch Presentation by Christian Ebner, STRABAG SE Sec

  4. Slide 4: Update on Tunnelling Technology – Introduction to the Project Perschling

    Update on Tunnelling Technology – Introduction to the Project Perschling Mr. Roland Jurecka Member of the Management Board of STRABAG SE Technical Head Special Divisions & Concessions 4

  5. Slide 5: Tunnelling technology

    Tunnelling technology Tunnels for Caverns Water power plants infrastructure projects Motorways Electricity Galleries Railways Storages 5

  6. Slide 6: Tunnelling technology (cont.)

    Tunnelling technology (cont.) Tunnelling methods NATM TBM Shields New Austrian Tunnelling Method Tunnel Boring Maschines Drill and Blast 6

  7. Slide 7: NATM

    NATM Geological conditions – Hard rock to soft rock – Solid soil Excavation method – Drill and blast – Excavation – Rod header Support system – Rock bolts – Lattice girders – Shot crete Source: The Austrian Art of Tunnelling, ITA Austria 7

  8. Slide 8: TBM

    TBM Geological conditions – Hard rock Excavation method – Cutter head Support system – Rock bolts – Shot crete 8

  9. Slide 9: Shield

    Shield Geological conditions – Soil to soft soil – Ground water Excavation method – Cutter head in excavation chamber Support system – Segmental precast lining 9

  10. Slide 10: STRABAG's tunnelling business

    STRABAG’s tunnelling business Key facts Output volume in 2007 Output volume in 2007: € 368 million €m Output volume in 2008e: € 610 million Germany 55.6 Order backlog, Aug. 08: € 1,650 million Austria 104.2 Very volatile business field Switzerland 98.2 Responsible management board members: Canada 48

  11. Slide 11: STRABAG's tunnelling strategy

    STRABAG’s tunnelling strategy Objective: Market leader in tunnelling Strategy: – Europe as core market – World markets: to achieve full capacity utilisation (e.g. Niagara) – STRABAG’s added value – STRABAG’s own workforce – STRABAG’s resources – concrete, quarries, aggregates – Joint Ventures only i

  12. Slide 12: STRABAG's tunnelling value added along the value chain

    STRABAG’s tunnelling value added along the value chain Design Design department Züblin Road- / Earthworks STRABAG Transportation Infrastructures Underground works STRABAG / Züblin (Special ground engineering) NATM, TBM, Own equipment (BMTI) Shield Own staff Water proofing Own workforce systems Reinf

  13. Slide 13: Risks and chances in tunnelling

    Risks and chances in tunnelling Risks Chances Contractual risks Soil risks / changed underground conditions Competitors Variation offers / orders Soil risk / underground risk Design and construction improvements and Currency risk savings Escalation In-house know-how – own workforce STRABAG added val

  14. Slide 14: STRABAG's major tunnelling projects

    STRABAG’s major tunnelling projects Railway Tunnel Brixlegg Railway Tunnel Jenbach Construction of railway Construction of the main tunnel section Vomp-Terfens contract section H8 Volume: € 204m (32% share) Volume: € 110m (67% share) Project schedule: 2003-2008 Project schedule: 2006-2011 Challenge:

  15. Slide 15: Major projects under construction

    Major projects under construction Project name Order backlog* Country STRABAG share Railway Tunnel Jenbach € 27 million Austria 67% Railway Tunnel Vomp - Austria 67% Railway Tunnel Wienerwald € 8 million Austria 14% Prague Ring Road € 90 million Czech Republic 33% Niagara Power € 232 million Canada

  16. Slide 16: Focus on future major projects

    Focus on future major projects Project name Estimated Volume Country Gotthard base tunnel / Monte Cenery CHF 1.5 billion Switzerland Brenner base tunnel € 6 billion Austria Koralmtunnel € 5.0 billion Austria Stuttgart 21 € 2.8 billion Germany Linth-Limmern water power CHF 1.5 billion Switzerland Met

  17. Slide 17: Impression of the Brenner base tunnel

    Impression of the Brenner base tunnel 17

  18. Slide 18: Introduction to the Perschling tunnel project – Lot 3

    Introduction to the Perschling tunnel project – Lot 3 18

  19. Slide 19: The Perschling chain of tunnels

    The Perschling chain of tunnels Austria, part of the Trans European Network The new railway line between Vienna and St. Pölten, with a distance of 42.3km Project name: Railway line from Vienna - St. Pölten Tunnel use: Railway Project owner: ÖBB Infrastruktur Bau AG Construction: STRABAG AG Length: 3

  20. Slide 20: Total length of lot 3 is 13km

    Total length of lot 3 is 13km Wien Reiserbergtunnel Stierschweiffeldtunnel Raingrubentunnel St. Pölten 20

  21. Slide 21: Three tunnels

    Three tunnels Reiserberg tunnel – TBM driven section 1,307m – Open cut section 23m Stierschweiffeld tunnel – Open cut section East 396m – TBM driven section 2,857m Raingruben tunnel – Cover method between bored piles 408m – TBM driven section 2,120m – Open cut section West 204m TOTAL 7,315m 21

  22. Slide 22: Perschling tunnel boring machine

    Perschling tunnel boring machine Technical data of the TBM Cutter head Diameter cutterhead: 13.03m Length of shield: 10.00m Backup system: 80.00m Weight of cutterhead + shield: 1,520to Installed power: 6,200kW Torque: 13,500kNm Segment lining: 5+1 segments 22

  23. Slide 23: Breakthrough at the Westbahn (Stierschweiffeld tunnel)

    Breakthrough at the Westbahn (Stierschweiffeld tunnel) 23

  24. Slide 24: STRABAG SE – Update on Strategy

    STRABAG SE – Update on Strategy Dr. Christian Ebner Secretary General of STRABAG SE 24

  25. Slide 25: 4.4% guaranteed. Asset resistant to crisis since 1842.

    * * 4.4% guaranteed. Asset resistant to crisis since 1842. Source: FT, 20 October 2008 25

  26. Slide 26: Highlights

    Highlights Record level of approx. € 15 billion Order 53% public clients, 47% private clients backlog Still full employment in all markets Output volume 2008 + 24 %, 2009: +20 % Guidance +28% EBIT in 2008 -> € 400 million – stable EBIT in 2009 Positive Free Cash Flow in 2009 expected Margin increase

  27. Slide 27: What we promised in the prospectus

    What we promised in the prospectus Driving market consolidation through selective acquisitions – Bolt-on acquisitions in CEE-markets to expand market leadership – Acquisitions in road construction in Western European markets – Acquisitions in specialized growth segments (e.g. environmental technolog

  28. Slide 28: What we delivered

    What we delivered 2007 2008 Total Output volume / ~25(1) 160(2) ~27(2) 350(3) 121(2) 276(3) ~28(2) 70(2) 1,000(4) 2,057 revenue (in € mln) Employees 270 370 280 1,600 400 1,500 168 700 6,240 11,528 Germany, Czech Germany, Austria, Country Croatia Italy Germany Sweden Switzerland Czech Rep., Republic

  29. Slide 29: Russia – Robust growth

    Russia – Robust growth Russian key indicators 25% 20% 15% % change YoY 10% 5% 0% 2000 2001 2002 2003 2004 2005 2006 2007 2008E 2009E 2010E -5% Investment Private Consumption Real GDP Industrial Production Government Consumption Strong investment and private consumption expected Very low level of pri

  30. Slide 30: Russia – Construction output

    Russia – Construction output Russian construction output growth % Euroconstruct revised Russian growth figures 25 downwards in September 2008 20 Expected growth still in the double-digit area 15 All segments > 10 % 10 2008-2010 annual GDP growth 5 7.6 % on average expected 0 2006 2007 2008 2009e 201

  31. Slide 31: Stable Russian budget and high reserves

    Stable Russian budget and high reserves Revenues / Expenditures / Balance Debt / Forex reserves / Stabilisation fund 25 500 20 400 15 300 10 200 5 100 0 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 0 -5 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 -10 YTD Revenues (% of GDP) Expenditu

  32. Slide 32: Development of oil price

    Development of oil price USD / barrel 140 132.4 133.2 122.7 120 113 109 103.7 100 95 98.1 92.6 91 92 82.5 80 76.9 75.9 60 40 20 0 Sep.07 Oct.07 Nov.07 Dec.07 Jan.08 Feb.08 Mar.08 Apr.08 May.08 Jun.08 Jul.08 Aug.08 Sep.08 Oct.08 Source: Statista.org, October 2008 32

  33. Slide 33: Very low public debt

    Very low public debt 120% 107% In % of BIP 2007 100% 91% 76% 80% 66% 58% 57% 54% 60% 45% 45% 45% 41% 38% 38% 40% 30% 17% 13% 12% 20% 7% 0% Czech Republic Euro Area Romania Germany Lithuania Hungary Ukraine Turkey Poland France Japan China Serbia Russia India Italy US UK The Russian government is nea

  34. Slide 34: Private households nearly debt-free

    Private households nearly debt-free 100% 90% 80% 70% 60% % of GDP 50% 40% 30% 20% 10% 0% USA UK Brazil Hungary Germany Romania India Kazakhstan Ukraine Czech Rep Turkey Russia Slovenia Bulgaria Poland Slovakia China Croatia Estonia Mortgage Loans (end of 2007) Retail Loans (end of 2007) Source: Merr

  35. Slide 35: Russia – Largest projects of order backlog

    Russia – Largest projects of order backlog Company Project name Location Order backlog* Project start Project end Project description share in % Residential building incl. Zareschje Moscow 100 € 420 million 09/2008 09/2013 infrastructure Steelworks Wyksa Wyska 100 € 293 million 11/2007 10/2010 Steel

  36. Slide 36: Millipede pays off

    Millipede pays off Output % of total IMF GDP** Construction IMF GDP** Construction IMF GDP** Construction Country in HY 08 output growth 2008e growth* 2008e growth 2009e growth* 2009e growth 2010e growth* 2010e Germany 1,822 34.4 1.9 1.2 0.0 1.5 1.0 1.5 Austria 955 18.0 2.0 2.3 0.8 2.3 2.1 2.9 Polan

  37. Slide 37: Q&A session

    Q&A session Dr. Hans Peter Haselsteiner CEO of STRABAG SE 37