AGL Energy Limited · ASX:AGL
AGL Energy — Corporate Update (June 2020)
15 slides from AGL Energy's corporate update, Jun 4, 2020
Slide 1: Newcastle Community Dialogue Group
Newcastle Community Dialogue Group 04 June 2020 – Meeting 14
Slide 2: Open and welcome, apologies, declarations, previous minutes and business arising
Open and welcome, apologies, Newcastle Gas Storage Facility 1 declarations, previous minutes and business arising 3 Latest news Newcastle Power Station Project 2 4 General business Latest news and next steps Next meeting and close
Slide 3: Apologies, declarations, previous minutes and business arising
Apologies, declarations, previous minutes and business arising
Slide 4: Newcastle Power Station Project: Latest news and next steps
Newcastle Power Station Project Latest news and Next steps
Slide 5: Timeline
Timeline Jan April Nov Dec April July Nov Dec 2019 2019 2019 2019 2020 2020 2020 2020 Lodge PEA Lodge EPBC Submit EIS Exhibition of AGL submit AGL submits Minister EPBC Approval application Referral with EIS ends Response to RFI response recommends granted – CA with DPIE (CSSI) DoEE Submissions Proj
Slide 6: Response to Submissions
• Our ‘Response to Submissions’ was lodged with the Department of Planning Industry and Environment on 30th April 2020, and subsequently published by the Department. • This is our response to 30 submissions sent to the Environmental Impact Statement, including: • 15 from public authorities • 9 from
Slide 7: Report distributed to
Report distributed to • Community Dialogue Group • Office of Sussan Ley MP, Minister for the Environment • TAC • Office of Ms Meryl Swanson MP, Member for Paterson • Hunter Water (Federal), New South Wales • Department of Defence • Office of Ms Kate Washington, MP, Member for Port Stephens • DWA (Fe
Slide 8: DPIE requests for additional information
• DPIE has requested additional information: • BCD – relating to Biodiversity and Flooding • CASA – minor word updates • EPA – air quality and Noise • Health – air quality • PSC – stormwater • Hazards – PHA update and NSSF laydown area • DoD – updating response • AGL is actively engaging with stakeh
Slide 9: Newcastle Gas Storage Facility: Latest news
Newcastle Gas Storage Facility Latest news
Slide 10: General
General • The plant has completed liquification in March. • Tank filled to 95% of its capacity. • AGL is ready for the increase in customer demand in autumn leading into winter. • COVID-19 slowed down all maintenance and capital project activities. • We have been mainly in HOLDING mode since March d
Slide 11: Environmental Update
Environmental Update • Air Emissions testing was undertaken on H-101 Unit in April with no exceedance reported. • 6-monthly groundwater and surface water monitoring was undertaken in March with no exceedance reported • Air Emissions testing being undertaken on F-501A, B & C Heaters in June/July. • N
Slide 12: Local Community Investment Program and COVID-19
• Once COVID-19 restrictions were put in place, potential recipients of the Local Community Investment Program (LCIP) advised that their initiatives had been indefinitely postponed or cancelled. • The LCIP will resume in the new financial year 2021, with updated guidelines that will reflect federal,
Slide 13: Community support initiatives and stakeholders contacted
Contacted government Identified problems Contacted community groups organisations • Port Stephens Council • Domestic violence • Port Stephens Family and Neighbourhood Services • Maitland City Council • Homelessness • Tomaree Neighbourhood Centre • Newcastle City Council • Financial aid • Yacaaba Cen
Slide 14: Next meeting and close
General Business Next meeting and close
Slide 15: Contacts
Lisa Andrews Ernesto Calderon Independent Chairperson Newcastle Gas Storage Facility and 0401 609 693 Newcastle Power Station Project Community Relations Manager [email protected] 0498 001 536 [email protected]