Tata Power Company Limited · NSE:TATAPOWER
Tata Power — The Tata Power Company — Investor Presentation (February 2009)
63 slides from Tata Power's investor presentation, February 2009
Slide 1: The Tata Power Company Limited Investors' Meet - February 2009
The Tata Power Company Limited Investors’ Meet - February 2009 1
Slide 2: Disclaimer
Disclaimer Certain statements made in this presentation may not be based on historical information or facts and may be “forward looking statements”, including those relating to The Tata Power Company Limited’s general business plans and strategy, its future outlook and growth prospects, and future d
Slide 3: Agenda
Agenda • Part A: Overview of Tata Power • Part B: Power Business – Section 1: Generation – Section 2: Fuel & Logistics – Section 3: T & D – Section 4: Power Trading • Part C: Other Businesses • Part D: Financial Performance • Part E: Sustainability 3
Slide 4: Part A: Overview of Tata Power
Part A: Overview of Tata Power 4
Slide 5: A Tata Company
«ip TATA A Tata Company 6% Largest Companies Tata Moto 22% 23% FY 2008 Tata Steel i Rs 251,543 cr Information Technology 3 62.5bn Tata Consultancy Services a *3% VSNL Materials Tata Chemicals 7% 4% 2% Tata Tea Services Tata Teleservices Profits FY 2007 Tata AutoComp Systems 40% Rs 21,578 or $5.4 bn
Slide 6: Tata Power: Introduction
Tata Power: Introduction • Largest private, integrated utility company in India today with presence across the value chain in fuel, generation, T&D and trading • Founded in 1906, to supply hydro-electric power to Mumbai. Set-up thermal generation in Trombay in 1960s • Expanded outside Mumbai with IP
Slide 7: Pioneer in Power Sector
Pioneer in Power Sector First 800 MW thermal unit First pump storage unit in the country of 150 MW Capacity First to Introduce SCADA and Fibre Optic ground wire communication Flue Gas De-sulphurisation plant using 220 kV sea water Cable Transmission 220 kV Network transmission Computerized lines in
Slide 8: Existing Presence in Power Sector
Existing Presence in Power Sector Tala Transmission NDPL Jojobera 428 MW Samana 29 MW Haldia 90 / 120 MW Trombay 1330 MW Supa 17 MW Mumbai Distribution Mumbai Transmission Khandke 51 MW Hydro 447 MW Bramanvel 11 MW Thermal (1839 MW) Belgaum 81 MW Gadag 16 MW Hydro (471 MW) Wind (124 MW) Other Projec
Slide 9: Tata Power Group – Major Companies
Tata Power Group – Major Companies Tata Power Subsidiaries Joint Ventures Associates Coastal Gujarat Tata BP Solar Ltd 100% Power Ltd 49% 30% KPC Tata Power Trading Tubed Coal 100% 40% Company Ltd` Mine Ltd 30% Arutmin 100% Trust Energy Mandakini Coal Resources Pte Ltd 33% Mine Ltd 74% Maithon Power
Slide 10: Businesses
• Trombay 14, 25 • Hydro 14, 32 • Jojobera 23 Businesses • Belgaum 14 • Haldia 27 • Wind Farm 33-35,60 • Solar PV 49 • Mundra Division Generation • Maithon • Tata Steel JV (IEL) Other Entities • Tata BP Solar Transmission • Mumbai 42 • Tala Power Business Distribution • Mumbai 42 • Delhi • Tata Powe
Slide 11: Part B: Power Business
Part B: Power Business – Section 1: Generation – Section 2: Fuel & Logistics – Section 3: T & D – Section 4: Power Trading 11
Slide 12: Generation: Business Models
Generation: Business Models 12
Slide 13: Impact of New CERC Norms
oe Impact of New CERC Norms TATA Parameter Before After Return on Equity 14% (post tax) * 15.5/(1-t) (pre-tax) - 17.481% (MAT) - 23.481% (Normal) * 0.5% additional for timely project completion Depreciation * 3.6% * 5.28% for first 12 years (No AAD) * AAD * Balance equally spread over life (~2%) Lon
Slide 14: Tata Power: Existing Operations
Tata Power: Existing Operations Mumbai Licence Area (1777 MW) Trombay - Thermal Hydro Power Generation Unit 4 150 MW Oil & Gas Khopoli 72 MW Unit 5 500 MW Oil, Coal & Gas Bhivpuri 75 MW Unit 6 500 MW Oil & Gas Bhira 300 MW Unit 7 180 MW Gas Total 447 MW Total 1330 MW Wind 124 MW Haldia 90 MW Jojober
Slide 15: Thermal Projects Under Implementation
Thermal Projects Under Implementation Maithon1050 MW Mundra 4000 MW Jojobera/Jamshedpur 240 MW Haldia 30 / 120 MW Trombay 250 MW Thermal (5570 MW) 15
Slide 16: Mundra UMPP
Project Capacity • 4000 MW (5 x 800 MW) Ownership Structure • 100% subsidiary: Coastal Gujarat Power Limited Business Model • Case 2 Customers • Gujarat (1805 MW), Maharashtra (760 MW), Punjab (475 MW), Haryana (380 MW), Rajasthan (380 MW) Funding • Project Cost: Rs 17,000 Crore (D/E: 75:25) • Finan
Slide 17: Mundra UMPP
Project Milestone • Over 13% work already completed Construction • Structural erection is in progress for two boiler units and civil work is Activities progressing well at site On-site • Over 2500 people already located on site Funding • CGPL completed all pre-disbursement conditions and received it
Slide 18: Mundra - Boiler and TG Building
Mundra - Boiler and TG Building 18
Slide 19: Mundra - Cooling Water Conduits below TG Rafts
Mundra - Cooling Water Conduits below TG Rafts 19
Slide 20: Maithon
Project Capacity • 1050 MW (2 x 525MW) Ownership Structure • Maithon Power Limited 74: 26 JV of Tata Power and Damodar Valley Corporation Business Model • Regulated Customers • DVC (300 MW), NDPL (300 MW), WBSEB (150 MW), PSEB (300 MW) Funding • Project Cost: Rs 4450 Crores • (D/E: 70:30) • Debt syn
Slide 21: 400 KV Switchyard Column Casting
Project Milestone • Over 21% of work completed Ordering • Ordering for all packages completed Construction • Column erection completed for Boiler Unit-1 Activity • Foundation completed for Boiler Unit-2 Fuel Supply • Coal linkage sanctioned. Active discussions on to sign Fuel Supply Agreements with
Slide 22: Unit 1- Erection of column & roof girder
Unit 1- Erection of column & roof girder Unit - 2 Foundation work Unit 1- Column casting in progress for TG deck slab. Unit 1- Mill Bunker 22
Slide 23: Captive Power Plants
JAMSHEDPUR (PH #6) JOJOBERA (Unit #5) Project Capacity • 120 MW • 120 MW Ownership Structure • IEL (74:26 JV of Tata • IEL Power and Tata Steel) Business Model • CPP • CPP Funding • Project Cost: Rs 490 Crores • Project Cost: Rs 620 Crores • D/E 70:30 • D/E 70:30 Completion • March 2009 • December 2
Slide 24: Jamshedpur (PH #6) – Site Photographs
Jamshedpur (PH #6) – Site Photographs TG Rotor erection IDCT Commissioned 24
Slide 25: Trombay Unit 8
Project Capacity • 250 MW Ownership Structure • Tata Power Division Business Model • Regulated + Merchant Funding • Project Cost: Rs 1066 Crore • D/E 70:30 Completion • Synchronized in January 2009 • Commissioning by March 2009 Project Description • Fuel: Imported coal Trombay Unit 8 25
Slide 26: Trombay (Unit 8) – Site Photographs
Trombay (Unit 8) – Site Photographs 26
Slide 27: Haldia
Project Capacity • 120 MW (2 x 45 MW + 30MW) Ownership Structure • Tata Power Division Business Model • Merchant and Regulated Customers • Hoogly Metcoke, PPA with Tata Power Trading and WBSEDCL Funding • Project Cost Rs 605 Crores • D/E 70:30 Completion • 1st two 45MW units commissioned in August ‘
Slide 28: Haldia – Site Photographs
Haldia – Site Photographs 2 1 TG Unit # 1 & 2 in operation Boiler # 3 – 2 under erection 28
Slide 29: Projects in Pipeline
Projects in Pipeline Total 5670 Planning & development activities initiated 29
Slide 30: Captive Coal Blocks
Captive Coal Blocks Mandakini Coal Block • 7.5 MTPA (jointly allotted with Jindal Photo Film and Monnet Ispat & Energy - each JV Partner having a share of 2.5 MTPA) at Dist. Angul, Orissa • Submission of EIA Report: Jan / Feb ‘09 • Approval of mining plan by MoC: Jan / Feb ‘09 • Start of Production:
Slide 31: Generation Capacity (Tata Power Group)
Generation Capacity (Tata Power Group) Tata Power - Capacity 14000 12000 10000 5200 8000 Capacity in MW 6000 3075 Added in the Year 1125 7398 Opening Capacity 4000 220 613 4323 2000 2365 2365 2978 3198 0 2008 2009 2010 2011 2012 2013 Year Ended Mar 31 31
Slide 32: Hydro Electric Power
Hydro Electric Power • Oldest and one of the largest private sector players with capacity of 447 MW • Several awards and recognitions – Bhira Pump Storage Scheme received the CEA Silver Shield • Agreed to take 26% equity stake in 114 MW Dagachhu Hydro Electric Power Project being developed by The Ro
Slide 33: Initiatives In Renewables
Initiatives In Renewables • 124 MW operational • 72 MW to be commissioned – 52 MW by March ’09, 20 MW by April ‘09 • 300 MW being additionally explored • Developing a 3 MW grid connected solar PV farm in Maharashtra • Evaluating potential for concentrated solar thermal (CST) generation • Signed MoU
Slide 34: Wind Farms
Installed Capacity • 124 MW Project Under • 73 MW Implementation (35 MW Karnataka, 21 MW Gujarat, 17 MW Maharashtra) Ownership Structure • Tata Power division Business Model • Regulated Funding • Project Cost: Rs 633 Crores Completion • March - April 2009 Project Description • Turnkey projects by En
Slide 35: Wind Projects Under Implementation
Wind Projects Under Implementation Samana 21 MW Sadawaghapur 17 MW Gadag 35 MW Wind (73 MW) 35
Slide 36: Part B: Power Business
Part B: Power Business – Section 1: Generation – Section 2: Fuel & Logistics – Section 3: T & D – Section 4: Power Trading 36
Slide 37: Fuel
Fuel ears y Fuel supplies 0-25 fo r new projects fo r2 37
Slide 38: Indonesian Coal Mines
Indonesian Coal Mines Deal Highlights Performance • Acquired 30% equity stake in KPC and • Quantity mined in Jan-Sep 2008 ~ Arutmin from PT Bumi Resources, 37MT Indonesia • Average realised price per tonne (FOB) • Acquisition value of USD 1.1 bn – US$70.5 (Jan-Sep 2008) • Off-take contract with KPC
Slide 39: Trust Energy Asia Pte Limited
Trust Energy Asia Pte Limited • SPV incorporated in Singapore for owning ships to meet shipping requirements and trading in fuels • Present shipping requirements of 8-9 vessels for Mundra • To be met through a combination of long term charters and out right purchases – 3 LT charters signed and 2 Kor
Slide 40: Part B: Power Business
Part B: Power Business – Section 1: Generation – Section 2: Fuel & Logistics – Section 3: T & D – Section 4: Power Trading 40
Slide 41: Distribution Opportunities
Distribution Opportunities • Second License – parallel licensing unlikely to happen soon • Privatization – not much progress in replicating Delhi model • Outsourcing – opportunity for marginal players • Franchisee Opportunity – window is open for private participation 41
Slide 42: Mumbai: Transmission and Distribution
Mumbai: Transmission and Distribution • 23,000 customers with 2500 MUs of sales (mostly to high value bulk consumers) • 17 receiving and distribution stations, 318 consumer substations and 1335 Kms of HT & LT Cable network. Total asset base over Rs 1400 crores • MERC regulated tariff with 16% RoE on
Slide 43: North Delhi Power Limited (NDPL)
North Delhi Power Limited (NDPL) • 51:49 JV of Tata Power and Delhi Vidyut Praday Nigam (Govt. of Delhi) • Over 1 million consumers with 5000 MUs consumption and net asset base of over Rs 1800 Crores • Assured returns upto 16%, plus incentives on loss reduction YTD FY09: Sales – Rs 18.14 billion, PA
Slide 44: Powerlinks Transmission Limited
Powerlinks Transmission Limited • 51:49 JV of Tata Power and Power Grid Corporation of India • 1200 km 400 kV double-circuit transmission lines • Transmits power from Tala Hydroelectric Project and Eastern/North-Eastern region to New Delhi and adjoining areas. • Total investment of Rs 1560 Crores (D
Slide 45: Part B: Power Business
Part B: Power Business – Section 1: Generation – Section 2: Fuel & Logistics – Section 3: T & D – Section 4: Power Trading 45
Slide 46: Tata Power Trading Company Limited
Tata Power Trading Company Limited TPTCL Sales (MU) Role 6750 7000 • Identify and tap surplus power source in 6000 the country • Locate a customer who is ready to pay 5000 4500 in cash the for power at its landed cost 4000 inclusive of transmission losses MUs 3000 3000 • Settle commercial terms on b
Slide 47: Part C: Other Businesses
kd TATA Part C: Other Businesses
Slide 48: Strategic Electronics Division (SED)
Strategic Electronics Division (SED) • Revenues of Rs.59 crores (Mar 08) against Rs.51 crores during the previous year. • Current revenue contributors include electronics system for the Rocket Launchers, Fire Control Computers for Arjun Tank and Command and Control systems. • Future revenue to come
Slide 49: Tata BP Solar
Tata BP Solar • 51:49 JV between BP Solar and Tata Power • Market leader in Solar Photovoltaic technology in India with turnover of Rs 660 Crores • Nearly 75% of sales from exports largely to Europe and USA • India’s first Polycrystalline Solar cell manufacturing plant and 45 MW module manufacturing
Slide 50: Part D: Financial Performance
Part D: Financial Performance 50
Slide 51: Financials - Year Ended March 31, 2008
Financials - Year Ended March 31, 2008 Year Ended Rupees in Billions 31-Mar-08 31-Mar-07 Operating Income 59.16 47.15 Operating Expenditure (49.79) (39.92) Operating Profit 9.37 7.23 Interest & Finance charges (1.42) (1.89) Depreciation (2.91) (2.92) Other Income 4.66 3.44 Profit Before Tax 9.70 5.8
Slide 52: Financials – Nine Months ended December 31, 2008
Financials – Nine Months ended December 31, 2008 Quarter Ended Nine Months Ended Rupees in Billions 31-Dec- 08 31-Dec-07 31-Dec-08 31-Dec-07 Operating Income 17.77 14.19 57.62 42.81 Operating Expenditure (15.17) (11.51) (49.21) (34.98) Operating Profit 2.60 2.69 8.41 7.84 Interest & Finance charges
Slide 53: Financials - Consolidated
Financials - Consolidated Year Ended March 31, 2008 Year Ended Rupees in Billions 31-Mar-08 31-Mar-07 Operating Income 108.91 64.76 Operating Expenditure (87.70) (53.85) Operating Profit 21.21 10.91 Interest & Finance charges 4.88 2.83 Depreciation 5.59 4.15 Other Income 4.79 2.67 Profit Before Tax
Slide 54: Tata Power – Financials (Standalone)
Tata Power – Financials (Standalone) Annual Sales (MU) Profit After Tax (In Billion Rs.) EPS (in Rs.) Net Worth (In Billion Rs.) 54
Slide 55: Dividend History
Dividend History Earnings (Rs.) 40 40 Dividends (Rs.) Payout ratio (%) 30 30 20 % Rs. 20 10 10 0 0 2003 2004 2005 2006 2007 2008 55
Slide 56: Funding by Tata Power - Projects under Implementation
Funding by Tata Power - Projects under Implementation Own Funds Debt (Rs.5,100 Crores) (Rs.18,000 Crores) • Internal accruals: Rs.2800 Crores • Domestic loans through domestic • Remainder financial institutions, banks and – Disinvestment of various holdings capital markets or assets • Foreign loans
Slide 57: Part E: Sustainability
kd TATA Part E: Sustainability
Slide 58: Climate Change
Climate Change • Trombay SO2 emission of 24TPD (1330MW) - one of the most stringent • Forum of 46 global companies: New policy framework on Combating Climate Change (3C) • Carbon Footprint for the Company completed • Sustainability Council formed - 17 CDM Projects Identified • Utilization of waste h
Slide 59: Renewable and Clean Coal Technology
Renewable and Clean Coal Technology • Solar Concentrated Thermal (SCT) • Geo Thermal energy • Coal Bed Methane (CBM) • Coal beneficiation technologies
Slide 60: Wind Farms
Wind Farms • Existing installed Renewable plants • CDM host country approval received for the 62 MW of the new wind farms • 73 MW of wind power projects under implementation • 17 MW in Maharashtra, 21 MW in Gujarat, 35 MW in Karnataka.
Slide 61: Demand Side Management
Demand Side Management • DSM Workshop conducted for all utilities in Maharashtra • Energy conservation awareness campaigns for Customers & School • Launched “I will, Mumbai will” (joint Adv. campaign with other Dist. Lic.) • Tata Power Energy Club formed for curbing energy wastage
Slide 62: Human Resource Management
Human Resource Management • Long Term Settlement with the Union signed • Succession Planning process implemented • Competency Development exercise in progress • Organization Transformation Initiatives are being implemented
Slide 63: Thank you
« TATA Thank you We take pride in Lighting up Lives! — ee
The Tata Power Company — Investor Presentation (February 2009) on 6ix