Slide 1: Northwestern Energy ETAC Meeting #9, 2025 MT IRP Planning Cycle
Northwestern Energy ETAC Meeting # 9 2025 MT IRP Planning Cycle October 29th, 2025
Slide 2: Agenda
Thank Agenda you
Slide 3: Agenda
Agenda Introductions/Welcome (5 min) Updated IRP Schedule (15 min) PowerSIMM Finalized ARS Results (80 min) PowerSIMM Preliminary PCM Results (80 min)
Slide 4: Timeline – High Level
Timeline – High Level (see detailed workplan) Modeling Inputs Preliminary Modeling Draft IRP File MT ETAC Modeling Input 2026 IRP with Final Modeling IRP PSC Today Final Plan Oct. 29 Complete Internal and External Stakeholder Review Dec. 2025 Open period for Public Comment Jan. 2026 March 2026
Slide 5: Stakeholder Working Group
Thank you Stakeholder Working Group
Slide 6: Stakeholder Working Group
Stakeholder Working Group Meeting Date: 11/10/2025 10:00 AM – 4:00 PM Location: Butte General Office Building: 11 E Park Street, Butte MT 59701 Participants Olson, Megan (Meeting Organizer, NWE) Shafer, Jon (NWE) Stajcar, Matthew (NWE) Barnheiser, Quintin (NWE) Seitz, Brandt (NWE) Fitzmaurice, Nicho
Slide 7: Stakeholder Working Group
Stakeholder Working Group • Show Finalized ARS results. • Show Preliminary PCM results. • Receive feedback and comments.
Slide 8: IRP Progress Towards Draft Release
Thank you IRP Progress Towards Draft Release (Discussion Item)
Slide 9: PowerSIMM Finalized ARS Results
Thank you PowerSIMM Finalized ARS Results
Slide 10: Scenarios for 2026 MT IRP
Scenarios for 2026 MT IRP A. Base Case – Colstrip retires December 31, 2042. B. Colstrip retires June 30, 2029, according to MATS. C. Colstrip complies with MATS using baghouse on July 1, 2030. Colstrip retires December 31, 2042. D. Colstrip retires December 31, 2031, according to GHG. E. Colstrip r
Slide 11: Sensitivities for 2026 MT IRP
Sensitivities for 2026 MT IRP F. 50% power costs. M. Allow carbon emitting resources after 2035 G. 150% power costs. (PSC request from 2023 IRP) H. 50% natural gas costs. N. Only allow carbon free resources to be selected in ARS I. 150% natural gas costs. J. 150 MW of additional data center load O.
Slide 12: Puget 370 MW Share of Colstrip
Puget 370 MW Share of Colstrip • Updates Since Last Meeting: • The Puget Share of Colstrip has been removed from the base case. • As seen in previous slide, the Puget Share is modeled as a sensitivity to the base case.
Slide 13: Summer Capacity Forecast & Retirements
Summer Capacity Forecast & Retirements Summer Capacity Forecast Summer Capacity Retirements & PPA Expirations 1,800 188 149 76 69 62 55 1,600 (102)(117)(126)(149) (1) (2) (2) (2) (8) (6) Accredited Capacity (MW) 1,400 (212)(220)(232)(240)(246) (24) (17) (13) (401)(420) (56) Basin Creek 1,200 Powerex
Slide 14: Winter Capacity Forecast & Retirements
Winter Capacity Forecast & Retirements Winter Capacity Forecast Winter Capacity Retirements & PPA Expirations 1,800 93 (33) (40) (45) 1,600 (23) (199)(203)(211)(215)(237) Accredited Capacity (MW) 1,400 (300)(313)(317)(323) (3) (9) (3) (6) (18) (474)(484) (39) 1,200 (59) (100) Powerex Basin Creek Tri
Slide 15: Base Case and Main Scenarios
Thank you Base Case and Main Scenarios
Slide 16: ARS Modeling Updates Since Last ETAC Meeting
ARS Modeling Updates Since Last ETAC Meeting • Fuel infrastructure, i.e. natural gas, and electric interconnection and network upgrade costs are included in the total cost for candidate resources. Before, these costs were going to be included post-processing. • Long duration energy storage (Form Ene
Slide 17: ARS Results: Scenario A – Base Case
ARS Results: Scenario A – Base Case No overbuild constraint With overbuild constraint above 150 MW threshold Candidate Resource Additions Candidate Resource Additions 1,600 1,600 1,400 1,400 Nameplate Capacity (MW) Nameplate Capacity (MW) 1,200 1,200 1,000 1,000 800 320 800 600 150 600 100 400 400 6
Slide 18: ARS Results: Scenario B – Colstrip Retires to Comply with MATS
ARS Results: Scenario B – Colstrip Retires to Comply with MATS Candidate Resource Additions 1,600 1,400 Nameplate Capacity (MW) 1,200 1,000 800 600 50 400 200 200 320 320 100 100 100 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Wind Wind Hybrid
Slide 19: ARS Results: Scenario C – Colstrip Complies with MATS via Baghouse
ARS Results: Scenario C – Colstrip Complies with MATS via Baghouse • No change from Scenario A, Base Case.
Slide 20: ARS Results: Scenario D – Colstrip Retires to Comply with GHG
ARS Results: Scenario D – Colstrip Retires to Comply with GHG Candidate Resource Additions 1,600 1,400 Nameplate Capacity (MW) 1,200 1,000 800 600 400 640 100 200 300 50 100 100 100 50 50 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Wind Wind Hy
Slide 21: ARS Results: Scenario E – Colstrip Retires in 2035
ARS Results: Scenario E – Colstrip Retires in 2035 Candidate Resource Additions 1,600 1,400 Nameplate Capacity (MW) 1,200 1,000 800 600 400 100 200 320 320 50 150 200 50 50 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Wind Wind Hybrid Solar Sola
Slide 22: ARS Summary of Base Case and Main Scenarios
ARS Summary of Base Case and Main Scenarios 2026 MT IRP ARS Results - Base Case vs Scenarios 1490 150 1290 250 1240 1190 100 320 640 250 150 MW 200 640 250 150 50 250 100 320 640 200 300 150 50 50 A Base Case B CSretMATS D CSretGHG E CSret2035 Wind Solar Hybrid Aero CT DF CCCT 150 CCCT 320 SC CT BES
Slide 23: Commodity Sensitivities
Thank you Commodity Sensitivities
Slide 24: ARS Results: Sensitivity F – Power Price Reduced by 50%
ARS Results: Sensitivity F – Power Price Forecast Reduced by 50% Candidate Resource Additions 1,600 1,400 Nameplate Capacity (MW) 1,200 1,000 800 600 400 640 200 100 108 100 150 50 50 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Wind Wind Hybrid
Slide 25: ARS Results: Sensitivity G – Power Price Increased by 50%
ARS Results: Sensitivity G – Power Price Forecast Increased by 50% Candidate Resource Additions 1,600 1,400 Nameplate Capacity (MW) 1,200 1,000 800 600 400 640 200 100 150 50 100 50 100 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Wind Wind Hybr
Slide 26: ARS Results: Sensitivity H – Natural Gas Price Reduced by 50%
ARS Results: Sensitivity H – Natural Gas Price Forecast Reduced by 50% Candidate Resource Additions 1,600 1,400 Nameplate Capacity (MW) 1,200 1,000 800 600 400 640 200 100 150 50 100 50 100 50 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Wind Wi
Slide 27: ARS Results: Sensitivity I – Natural Gas Price Increased by 50%
ARS Results: Sensitivity I – Natural Gas Price Forecast Increased by 50% Candidate Resource Additions 1,600 1,400 Nameplate Capacity (MW) 1,200 1,000 800 600 400 640 200 100 150 100 108 50 100 50 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Wind
Slide 28: ARS Summary of Commodity Sensitivities
ARS Summary of Commodity Sensitivities 2026 MT IRP ARS Results - Base Case vs Commodity Sensitivities 1290 1298 1240 1198 1190 640 640 640 640 640 MW 150 150 100 150 150 250 250 250 250 250 150 200 50 150 150 50 108 50 50 108 A Base Case F Power50 G Power150 H NatGas50 I NatGas150 RICE Aero CT DF CC
Slide 29: Data Center Sensitivities
Thank you Data Center Sensitivities
Slide 30: ARS Results: Sensitivity J – Add Data Center Load
ARS Results: Sensitivity J – Add 150 MW of Data Center Load Candidate Resource Additions 1,600 1,400 Nameplate Capacity (MW) 1,200 1,000 800 600 960 400 200 100 150 50 50 50 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Wind Wind Hybrid Solar Sol
Slide 31: ARS Results: Sensitivity K – Add Data Center Load
ARS Results: Sensitivity K – Add 650 MW of Data Center Load Candidate Resource Additions 1,600 1,400 Nameplate Capacity (MW) 1,200 1,000 800 600 200 960 400 320 50 200 300 150 200 50 50 100 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Wind Wind
Slide 32: ARS Results: Sensitivity L – Add 1,160 MW of Data Center Load
ARS Results: Sensitivity L – Add 1,160 MW of Data Center Load Candidate Resource Additions 1,600 1,400 Nameplate Capacity (MW) 1,200 50 1,000 800 960 600 960 400 200 150 200 50 100 100 50 100 100 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Wind
Slide 33: ARS Summary of Data Center Sensitivities
ARS Summary of Data Center Sensitivities 2026 MT IRP ARS Results - Base Case vs Data Center Sensitivitites 2820 2380 960 960 150 250 MW 1290 1360 150 200 250 640 200 960 960 320 150 250 150 100 50 250 150 200 300 50 50 50 100 A Base Case J DC150 K DC650 L DC1160 Wind Solar Hybrid Aero CT DF CCCT 150
Slide 34: Resource Sensitivities
Thank you Resource Sensitivities
Slide 35: ARS Results: Sensitivity M – No Limitation on Carbon Emitting Resources
ARS Results: Sensitivity M – No Limitation on Carbon Emitting Resources Candidate Resource Additions 1,600 1,400 Nameplate Capacity (MW) 1,200 1,000 800 600 400 50 200 320 320 50 200 150 50 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Wind Wind
Slide 36: ARS Results: Sensitivity N – Carbon Free Candidate Resources Only
ARS Results: Sensitivity N – Carbon Free Candidate Resources Only Candidate Resource Additions 1,600 1,400 Nameplate Capacity (MW) 1,200 1,000 800 600 400 600 640 200 100 100 50 50 100 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Wind Wind Hybri
Slide 37: ARS Results: Sensitivity O – PSE Colstrip Share Used for Retail Load
ARS Results: Sensitivity O – PSE Colstrip Share is used for Retail Load Candidate Resource Additions 1,600 1,400 Nameplate Capacity (MW) 1,200 640 1,000 800 150 100 600 400 600 200 100 50 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Wind Wind Hy
Slide 38: ARS Results: Sensitivity P – Avista's Colstrip Shares Not Acquired
ARS Results: Sensitivity P – Avista’s Colstrip Shares are not Acquired Candidate Resource Additions 1,600 1,400 Nameplate Capacity (MW) 1,200 1,000 800 600 400 320 200 300 150 320 50 100 50 100 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Wind W
Slide 39: ARS Summary of Resource Sensitivities
ARS Summary of Resource Sensitivities 2026 MT IRP ARS Results - Base Case vs Resource Sensitivities 1640 1640 1390 1290 640 640 320 50 1140 640 250 150 MW 150 150 250 250 250 150 640 320 250 600 600 300 200 150 50 50 50 A Base Case M NoCO2Lim N CO2Free O wPseCS P NoAvaCS Wind Aero CT DF CCCT 150 CCC
Slide 40: Other Sensitivities
Thank you Other Sensitivities
Slide 41: ARS Results: Sensitivity Q – Add 300 MW of NPC Capacity
ARS Results: Sensitivity Q – Add 300 MW of NPC Capacity • No change from Scenario A, Base Case.
Slide 42: ARS Results: Sensitivity R – Increase DSM and NEM Forecasts
ARS Results: Sensitivity R – Increase DSM and NEM Forecasts Forecasted Peak Load Comparison Candidate Resource Additions 1,500 1,600 1,400 1,400 Nameplate Capacity (MW) 1,200 1,300 1,000 800 MW 1,200 600 320 1,100 400 50 100 200 1,000 300 150 108 100 50 100 50 2026 2027 2028 2029 2030 2031 2032 2033
Slide 43: ARS Summary of Other Sensitivities
ARS Summary of Other Sensitivities 2026 MT IRP ARS Results - Base Case vs Other Sensitivities 1328 1290 320 640 100 250 MW 150 150 108 250 100 200 300 50 A Base Case R IncDsmNem Wind Solar Hybrid RICE Aero CT DF CCCT 150 SC CT BESS 4hr BESS 100hr SMR Total
Slide 44: PowerSIMM Preliminary PCM Results
Thank you PowerSIMM Preliminary PCM Results
Slide 45: PCM Results: Scenario A – Base Case
Thank you PCM Results: Scenario A – Base Case
Slide 46: Energy production for PCM results of Scenario A – Base Case
Energy production for PCM results of Scneario A – Base Case. Annual Energy 23 M 20 M 17 M 14 M MWh 11 M 8M 5M 2M (1 M) 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Hydro Coal Petroleum Coke Natural Gas Solar Hybrid Solar XMSN Wind SMR STCC BESS
Slide 47: Capacity Factor for PCM results of Scenario A – Base Case
Capacity Factor for PCM results of Scenario A – Base Case. Capacity Factor 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Basin Creek 203606 CELP Heartland 203112 Colstrip Dave Gates Yellowstone Powerex
Slide 48: Emissions for PCM results of Scenario A – Base Case
Emissions for PCM results of Scenario A – Base Case. CO2 Emissions 14 M 12 M 10 M 8M Metric Tons 6M 21% 20% 19% 21% 4M 21% 21% 21% 21% 20% 21% 28% 28% 23% 25% 25% 26% 27% 2M 60% 55% 62% 58% 57% 57% 57% 54% 55% 59% 64% 64% 59% 61% 64% 63% 63% 68% 66% 66% - 2026 2027 2028 2029 2030 2031 2032 2033 2034
Slide 49: Transmission volumes for PCM results of Scenario A – Base Case
Transmission volumes for PCM results of Scenario A – Base Case Transmission Export & Import Volumes 6M 5M 4M MWh 3M 2M 1M - 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Exports Imports
Slide 50: Average transmission usage for PCM results of Scenario A – Base Case
Average transmission usage for PCM results of Scenario A – Base Case Average of Total Transmission Export & Import Volumes 700 600 500 400 aMW 300 200 100 0 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 aExports aImports
Slide 51: Transmission revenues for PCM results of Scenario A – Base Case
Transmission revenues for PCM results of Scenario A – Base Case. Total Transmission Export Revenues & Import Costs $700 M $600 M $500 M Revenues/Costs ($) $400 M $300 M $200 M $100 M - 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 Export Revenues
Slide 52: Total portfolio costs for PCM results of Scenario A – Base Case
Total portfolio costs for PCM results of Scenario A – Base Case. 20-year NPV Costs ($M) $77 $3,319 Total Import Cost 0% $5,672 Total Production Cost $1,935 Total Candidate Resource RR Total Existing Resource RR $3,092 Total Export Cost Net Total Cost $(2,752) A-BaseCase
Slide 53: PCM Summary
Thank PCM Summaryyou
Slide 54: Base Case & Main Scenarios
Thank you Base Case & Main Scenarios
Slide 55: Total energy production of Base Case and Main Scenarios relative to load
The total energy production of the Base Case and the Main Scenarios relative to the forecasted load. 20-year Total Energy Production and Consumption (MWh) 0% 2% 0% 0% -2% 187 M 190 M 187 M 187 M 184 M - 140 M - 140 M - 140 M - 140 M - 140 M A BaseCase B CSretMATS C BaseCase wCS BagHouse D CSretGHG E
Slide 56: CO2 emissions from the Base Case and the Main Scenarios
CO2 emissions from the Base Case and the Main Scenarios. 20-year Total CO2 Emissions (MT) 0% 0% 100 M 100 M 19 M 19 M -20% 80 M -26% -29% 74 M 71 M 24 M 24 M 25 M 34 M 42 M 21 M 0% 0% 19 M 57 M 57 M 17 M -38% 35 M -63% -78% 21 M 12 M A BaseCase B CSretMATS C BaseCase wCS BagHouse D CSretGHG E CSret2
Slide 57: Transmission imports and exports, Base Case and Main Scenarios
Transmission imports and exports from the Base Case and the Main Scenarios. 20-year Total Portfolio Exports and Import Volumes (MWh) 9% 0% 0% 3% -1% 61 M 56 M 56 M 58 M 55 M 0% 23% 0% 24% 33% -8M - 10 M -8M - 10 M - 11 M A BaseCase B CSretMATS C BaseCase wCS BagHouse D CSretGHG E CSret2035 20-year T
Slide 58: PCM results for the Base Case and the Main Scenarios
PCM results for the Base Case and the Main Scenarios 20-year NPV Total Costs ($) $100 M $434 M $89 M $105 M $77 M $77 M $3,612 M 18% $3,412 M $3,293 M $3,319 M $3,319 M 10% $6,711 M 8% 9% 0% $6,105 M $6,176 M $6,231 M $5,672 M $3,111 M $2,656 M $2,624 M $1,935 M $1,935 M $3,092 M $2,750 M $3,092 M $
Slide 59: Remaining book value for candidate resources, Main Scenarios
Remaining book value for candidate resources in the Base Case and the Main Scenarios. 20-year NPV of Candidate Resource Remaining Book Value ($) 0% 0% $2,389 M $2,389 M -34% $1,578 M -49% $1,214 M -66% $803 M A BaseCase B CSretMATS C BaseCase wCS BagHouse D CSretGHG E CSret2035 Total Candidate Resou
Slide 60: Base Case & Commodity Sensitivities
Thank you Base Case & Commodity Sensitivities
Slide 61: Total energy production of Base Case and Commodity Sensitivities
The total energy production of the Base Case and Commodity Sensitivities relative to the forecasted load. 20-year Total Energy Production and Consumption (MWh) 18% 220 M 9% 0% 205 M 187 M -6% 176 M -19% 152 M - 140 M - 140 M - 140 M - 140 M - 140 M A BaseCase F Power50 G Power150 H NatGas50 I NatGas
Slide 62: Carbon emissions from the Base Case and Commodity Sensitivities
Carbon emissions from the Base Case and Commodity Sensitivities. 20-year Total CO2 Emissions (MT) 14% 114 M 6% 106 M 0% 100 M -6% 29 M 94 M 26 M 19 M 11 M -24% 76 M 4M 24 M 24 M 24 M 27 M 24 M 6% 0% -1% 0% 60 M 57 M -17% 56 M 57 M 47 M A BaseCase F Power50 G Power150 H NatGas50 I NatGas150 20-year C
Slide 63: Transmission imports and exports, Commodity Sensitivities
Transmission imports and exports from the Base Case and Commodity Sensitivities. 20-year Total Portfolio Exports and Import Volumes (MWh) 50% 84 M 27% 71 M 0% 56 M -17% 46 M -50% 28 M -62% -30% 0% 21% 88% -3M -6M -8M - 10 M - 16 M A BaseCase F Power50 G Power150 H NatGas50 I NatGas150 20-year Total
Slide 64: PCM results for the Base Case and Commodity Sensitivities
PCM results for the Base Case and Commodity Sensitivities. 20-year NPV Total Costs ($) $34 M $77 M $42 M $101 M $67 M $3,964 M $3,319 M 14% $3,246 M $3,174 M 9% 0% $6,490 M $2,340 M $6,167 M $5,672 M -8% -24% $5,206 M $1,935 M $1,841 M $4,318 M $1,975 M $2,164 M $2,339 M $3,092 M $3,092 M $3,092 M $
Slide 65: Remaining book value for candidate resources, Commodity Sensitivities
Remaining book value for candidate resources in the Base Case and Commodity Sensitivities. 20-year NPV of Candidate Resource Remaining Book Value ($) 0% 0% 0% $2,395 M $2,397 M $2,389 M -2% $2,339 M -5% $2,281 M A BaseCase F Power50 G Power150 H NatGas50 I NatGas150 Total Candidate Resource RBV Cost
Slide 66: Base Case & Data Center Sensitivities
Thank you Base Case & Data Center Sensitivities
Slide 67: Total energy production of Base Case and Data Center Sensitivities
The total energy production of the Base Case and the Data Center Sensitivities relative to the forecasted load. 20-year Total Energy Production and Consumption (MWh) 91% 358 M 52% 284 M 18% 0% 220 M 187 M - 140 M - 140 M - 140 M - 140 M -26 M 18% -101 M -165 M -177 M 72% -241 M 126% -317 M A BaseCas
Slide 68: Carbon emissions from the Base Case and the Data Center Sensitivities
Carbon emissions from the Base Case and the Data Center Sensitivities. 20-year Total CO2 Emissions (MT) 96% 196 M 68% 168 M 63 M 39% 139 M 36 M 10 M 0% 27 M 27 M 27 M 100 M 19 M 24 M 81% 86% 87% 103 M 105 M 106 M 0% 57 M A BaseCase J DC150 K DC650 L DC1160 20-year Colstrip Emissions (MT) 20-year CEL
Slide 69: Transmission imports and exports, Data Center Sensitivities
Transmission imports and exports from the Base Case and the Data Center Sensitivities. 20-year Total Portfolio Exports and Import Volumes (MWh) 13% 0% 63 M 2% 1% 56 M 57 M 56 M 0% -4% -8M -8M 57% 70% - 13 M - 14 M A BaseCase J DC150 K DC650 L DC1160 20-year Total Exports (MWh) 20-year Total Imports
Slide 70: PCM results for the Base Case and Data Center Sensitivities
PCM results for the Base Case and Data Center Sensitivities. 20-year NPV Total Costs ($) $176 M 135% $13,326 M $133 M $6,200 M 68% $77 M $9,553 M $77 M $4,826 M $3,319 M $3,612 M $6,096 M 0% 3% $5,672 M $5,841 M $3,863 M $1,935 M $1,591 M $3,092 M $3,559 M $3,559 M $3,559 M $(2,752) M $(2,997) M $(2
Slide 71: Net total cost per total load, Data Center Sensitivities
PCM results for the Base Case and Data Center Sensitivities represented as the 20-year NPV total cost per total 20-year total load. Net Total Cost per 20-year Total Load ($/MWh) 4% $42.05 0% $40.61 -2% $39.70 -13% $35.35 A BaseCase J DC150 K DC650 L DC1160 Net Total Cost per 20-year Total Load ($/MW
Slide 72: Remaining book value for candidate resources, Data Center Sensitivities
Remaining book value for candidate resources in the Base Case and Data Center Sensitivities. 20-year NPV of Candidate Resource Remaining Book Value ($) 67% 69% $3,994 M $4,041 M 33% $3,184 M 0% $2,389 M A BaseCase J DC150 K DC650 L DC1160 Total Candidate Resource RBV Cost NPV
Slide 73: Base Case & Resource Sensitivities
Thank you Base Case & Resource Sensitivities
Slide 74: Total energy production of Base Case and resource sensitivities
The total energy production of the Base Case and the resource sensitivities relative to the forecasted load. 20-year Total Energy Production and Consumption (MWh) 12% 209 M 4% 0% -1% -1% 195 M 187 M 185 M 186 M - 140 M - 140 M - 140 M - 140 M - 140 M A BaseCase M NoCO2Lim N CO2Free O wPseCS P NoAvaC
Slide 75: Carbon emissions from the Base Case and the resource sensitivities
Carbon emissions from the Base Case and the resource sensitivities. 20-year Total CO2 Emissions (MT) 32% 132 M 6M 4% 26 M 0% 104 M 100 M -4% 96 M 21 M -14% 19 M 12 M 86 M 24 M 27 M 27 M 32 M 75% 100 M 27 M 0% 0% 1% 57 M 57 M 57 M -52% 27 M A BaseCase M NoCO2Lim N CO2Free O wPseCS P NoAvaCS 20-year C
Slide 76: Transmission imports and exports, resource sensitivities
Transmission imports and exports from the Base Case and the resource sensitivities. 20-year Total Portfolio Exports and Import Volumes (MWh) 32% 74 M 14% 0% -1% -1% 63 M 56 M 55 M 55 M -45% 0% 16% 12% 0% -5M -8M - 10 M -9M -8M A BaseCase M NoCO2Lim N CO2Free O wPseCS P NoAvaCS 20-year Total Exports
Slide 77: PCM results for the Base Case and the resource sensitivities
PCM results for the Base Case and the resource sensitivities. 20-year NPV Total Costs ($) $75 M $77 M $97 M $89 M $39 M $3,411 M $3,129 M $3,319 M $3,311 M 11% $3,408 M 5% $6,303 M 0% -2% $5,969 M $5,672 M $5,542 M -15% $4,849 M $1,935 M $2,254 M $1,277 M $2,804 M $1,632 M $3,559 M $3,092 M $3,092 M
Slide 78: Remaining book value for candidate resources, resource sensitivities
Remaining book value for candidate resources in the Base Case and the resource sensitivities. 20-year NPV of Candidate Resource Remaining Book Value ($) 20% $2,858 M 9% $2,605 M 0% $2,389 M -26% $1,776 M -56% $1,051 M A BaseCase M NoCO2Lim N CO2Free O wPseCS P NoAvaCS Total Candidate Resource RBV Co
Slide 79: Base Case & Other Sensitivities
Thank you Base Case & Other Sensitivities
Slide 80: Total energy production of Base Case and other sensitivities
The total energy production of the Base Case and the other sensitivities to the forecasted load. 20-year Total Energy Production and Consumption (MWh) 0% -2% -4% 187 M 183 M 180 M -6% - 140 M - 140 M - 132 M A BaseCase Q AddNPC300 R IncDsmNem 20-year Net Energy Production (MWh) 20-year Total Retail
Slide 81: Carbon emissions from the Base Case and the other sensitivities
Carbon emissions from the Base Case and the other sensitivities. 20-year Total CO2 Emissions (MT) 0% -1% -2% 100 M 99 M 98 M 19 M 15 M 16 M 24 M 27 M 27 M 0% 0% 0% 57 M 57 M 57 M A BaseCase Q AddNPC300 R IncDsmNem 20-year Colstrip Emissions (MT) 20-year CELP & YELP Emissions (MT) 20-year Remaining E
Slide 82: Transmission imports and exports, other sensitivities
Transmission imports and exports from the Base Case and the other sensitivities. 20-year Total Portfolio Exports and Import Volumes (MWh) 39% 78 M 0% 4% 56 M 58 M 0% -20% -8M -7M 340% - 37 M A BaseCase Q AddNPC300 R IncDsmNem 20-year Total Exports (MWh) 20-year Total Imports (MWh)
Slide 83: Sensitivity Q transmission with the WECC interconnection
Sensitivity Q transmission imports and exports from and to the WECC interconnection. Average of WECC Transmission Export & Import Volumes 700 600 500 400 aMW 300 200 100 0 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 aNWE-WECC ATC Forecast 20250
Slide 84: Sensitivity Q transmission with the SPP power market
Sensitivity Q transmission imports and exports from and to the SPP power market. Average of MISO Transmission Export & Import Volumes 700 600 500 400 aMW 300 200 100 0 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 aMISO Sales 150 MW aMISO Purchas
Slide 85: Sensitivity Q transmission with the MISO power market
Sensitivity Q transmission imports and exports from and to the MISO power market. Average of SPP Transmission Export & Import Volumes 700 600 500 400 aMW 300 200 100 0 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 aSPP Sales 150 MW aSPP Purchases
Slide 86: PCM results for the Base Case and the other sensitivities
PCM results for the Base Case and the other sensitivities. 20-year NPV Total Costs ($) $77 M $373 M $58 M $3,319 M $3,114 M $3,179 M 0% $5,672 M -8% -9% $5,198 M $5,155 M $1,935 M $1,935 M $1,593 M $3,092 M $3,092 M $3,092 M $(2,752) M $(2,767) M $(3,317) M A BaseCase Q AddNPC300 R IncDsmNem Total E
Slide 87: Remaining book value for candidate resources, other sensitivities
Remaining book value for candidate resources in the base case and the other sensitivities. 20-year NPV of Candidate Resource Remaining Book Value ($) 0% 0% $2,389 M $2,389 M -27% $1,733 M A BaseCase Q AddNPC300 R IncDsmNem Total Candidate Resource RBV Cost NPV
Slide 88: Questions/Comments?
Thank you Questions/Comments?