Slide 1: UBS Electric Power Conference
UBS Electric Power Conference March 3 & 4, 2010 Dallas, TX Exhibit 99.1

Slide 2: Forward Looking Disclosures
2 Forward Looking Disclosures The following presentation contains some “forward-looking statements” with respect to Westar Energy, Inc.’s (“Westar”) future plans, expectations and goals, including management’s expectations with respect to future operating results and dividend growth. The Private Sec

Slide 3: Recent Events
3 Recent Events Ironwood wind site acquired Abbreviated rate case approved Proposed settlement of EPA litigation 2010 transmission revenue update 2010 earnings guidance New KCC commissioner appointed

Slide 4: Ironwood Wind Site
4 Ironwood Wind Site Acquired development rights for wind site Preserves option of ownership or power purchase Build out for own use Allow 3 rd party to develop, and WR acquires power via PPA Site located near Spearville, KS Contracts with landowners cover more than 18,600 acres Able to support 500

Slide 5: Abbreviated Rate Case Approved
5 Abbreviated Rate Case Approved Filed abbreviated rate case June 2009 Address remaining Emporia and wind investments Investment of $97 million plus D&A and O&M Stipulation and Agreement filed Dec. 1, 2009 Recommended $17.1 million annual revenue increase Propose new rates reflect consolidated rates

Slide 6: Proposed Settlement of EPA Litigation
6 Proposed Settlement of EPA Litigation Agreement with EPA to resolve New Source Review allegations at the Jeffrey Energy Center Install SCR on one unit by 2014 Lower plant-wide NOx emission limit established Simpler plant modifications planned to achieve emissions target If plant unable to meet emi

Slide 7: 2010 Transmission Revenue Update
7 2010 Transmission Revenue Update October 2009 filed updated transmission formula rate Resulted in $16 million increase in revenue requirement New transmission rates effective January 1, 2010 Component applicable to wholesale and other transmission customers $10 million Companion retail component o

Slide 8: 2010 Earnings Guidance of $1.65 to $1.80
8 2010 Earnings Guidance of $1.65 to $1.80 No change in business strategy or direction No change in regulatory principles or methods Expected price adjustments: Abbreviated rate case Tracking adjustments Weather adjusted retail sales grow 2% O&M/SG&A increases 2-3% Depreciation increases $20 million

Slide 9: Kansas Corporation Commission
9 Kansas Corporation Commission Chairman Tom Wright reappointed to four-year term Has served since 2007 New commissioner appointed Ward Lloyd 25 years of public service Served 8 years in Kansas House of Representatives Served on House Utilities Committee among other committees

Slide 10: Introduction
10 Introduction

Slide 11: Committed to being a pure-play, vertically integrated utility
11 Committed to being a pure-play, vertically integrated utility Rate regulated based on cost of service Key operational facts About 7,100 MW of available generation (48% coal, 8% nuclear, 40% gas, 4% wind) 7,800 miles of transmission 685,000 customers Kansas’ Largest Electric Provider

Slide 12: In Our Favor
12 In Our Favor Coal 77% Gas 7% Wind 1.0% Uranium 15% 0.0¢ 1.0¢ 2.0¢ 3.0¢ 4.0¢ 5.0¢ 6.0¢ 7.0¢ 8.0¢ 9.0¢ 10.0¢ Westar Energy Kansas City Power and Light (KS) Empire District Electric (KS) National Average 6.9¢ 7.8¢ 8.5¢ $48.52 $16.79 $4.87 Uranium Coal Gas Low Rates Industrial 27% Other 0.5% Resident

Slide 13: Major Industrial Sectors
13 Major Industrial Sectors 36% 18% 17% 16% 13% Chemical & oil Food processing Aerospace Consumer manufacturing Other Commercial 38% Residential 34% Other 0.5% Industrial 29% Significant Industrial Sectors Based on MWh sales

Slide 14: 2009 Industrial Energy Sales
14 2009 Industrial Energy Sales 1,000 1,200 1,400 1,600 1,800 Q1 Q2 Q3 Q4 2009 2008 Budget Down 11% from 2008 Hard hit sectors include chemical, aerospace and construction Seeing positive trends in petroleum refining and animal science (13.8%) to ‘08 (11.0%) to Bud (9.5%) to ‘08 (10.9%) to Bud (12.1

Slide 15: 2009 Residential and Commercial Energy Sales
15 2009 Residential and Commercial Energy Sales Residential down 1.4% from ‘08 Customer growth in line with historical growth and budget Prior to cool summer average use per customer was ahead of plan and equal to 2008 Clearly the most weather sensitive group Commercial down 1.7% from ‘08 Customer g

Slide 16: Strategic Approach
16 Strategic Approach Place a high value on flexibility Create and preserve options and off ramps e.g., CapEx plans with built-in flexibility—both to timing and approach Avoid over committing to any single supply strategy Leverage actions and strategies around unique attributes Invest according to s

Slide 17: Outlook for 2010
17 Outlook for 2010

Slide 18: Service Territory Economy
18 Service Territory Economy Diverse customer base Military State government Higher education Manufacturing Oil and gas Agriculture and food processing Chemicals Kansas economy has slowed, resulting primarily in weaker industrial sales However: Receivables in arrears remain at about the same level a

Slide 19: Annualized Rate & Revenue Changes
19 Annualized Rate & Revenue Changes Actual and Estimated 2009 2010 (Estimated) 2011 (Estimated) Base rates $130 million Feb 3 $ million late Jan FERC transmission $ 4 million Jan 1 $ million Jan 1 $ million Jan 1 State TDC (transmission) $ 32 million March 13 $ million March $ million March ECRR $

Slide 20: Managing O&M and SG&A
20 Managing O&M and SG&A O&M / SG&A increased at CAGR of 4% over last four years Have reduced impact to by almost half by managing increases with revenue offsets and deferred accounting treatment: SPP transmission expense largely offset with transmission revenue Amortization of deferred storm expens

Slide 21: Current Capital Expenditure Forecast 2010-2012
21 Current Capital Expenditure Forecast 2010 - 2012 Actual Forecast Forecast Forecast Forecast 2009 2010 2011 2012 2010-2012 Method of Cost Recovery Generation Replacements and other 103.9 $ 99.9 $ 106.2 $ 126.6 $ 332.7 $ General Rate Case (GRC) Additional Generation Emporia Energy Center 4.4 - - -

Slide 22: Approximate Rate Base
22 Approximate Rate Base $ 516 $ 470 Transmission rate base $ 4,330 $ 4,103 Total (Dollars in millions) KCC Jurisdiction - Incentive rate base (1) $ 416 $ 470 Standard rate base FERC Transmission $ 3,814 $ 3,633 Estimated retail rate base Incremental environmental $ 3,490 $ 3,393 Standard rate base

Slide 23: Projected Rate Base
23 $3.2 $3.4 $3.4 $3.5 $3.7 $3.9 Projected Rate Base 2009 2014 (in billions) 2009 2010 2011 2012 2013 2014 Base Renewable Environmental Transmission $6.6 $6.3 $5.8 $5.2 $4.7 $4.3

Slide 24: Transmission
24 Transmission

Slide 25: R R
R R

Slide 26: y YF
aR R R y YF

Slide 27: y YF
aR R R y YF

Slide 28: 345kV Transmission System Additions
25 345kV Transmission System Additions Wichita – Salina Segment 1 Wichita-Hutchinson Completed December 2008 Investment $100 million Segment 2 Hutchinson-Salina Under construction target completion latter half 2010 Investment $100 million Rose Hill – Oklahoma Construction to follow the Hutchinson-Sa

Slide 29: Southwest Power Pool RTO
26 Southwest Power Pool RTO New Mexico Oklahoma Louisiana Texas Nebraska Kansas Arkansas Missouri

Slide 30: Prairie Wind Transmission, LLC
27 Prairie Wind Transmission, LLC Joint venture formed between Westar Energy and Electric Transmission America Venture to develop 765 kV transmission in Kansas 50% Westar / 50% ETA ETA is joint venture between AEP Transmission Holding Company and MEHC America Transco, LLC (wholly-owned subsidiary of

Slide 31: Prairie Wind Transmission, LLC
28 Prairie Wind Transmission, LLC Received FERC incentives Abandonment costs Recovery of pre-commercial development costs CWIP recovery in rate base Use of hypothetical capital structure of 50% debt and 50% equity Allowed ROE of 12.8% KCC Approved Stipulation resolved dispute regarding construction

Slide 32: Prairie Wind Transmission LLC Part of the Conceptual SPP EHV Overlay Plan
29 Prairie Wind Transmission LLC Part of the Conceptual SPP EHV Overlay Plan From the 2008 SPP Transmission Expansion Plan

Slide 33: New
New Aeris wine Substation New Ae cee rains Substation UML New Spearville A-~ Substation’ ~~ Now Prairie Wind Transmission Line New ITC Great Plains Transmission Line Possible Route wu for New Prairie Wind Transmission Line to OK Manhattan * alina Hutchinson * Spearville ° New New Comanche County Sub

Slide 34: Next Steps and Tentative Schedule
31 Next Steps and Tentative Schedule Inclusion in SPP regional plans Region-wide rate authority Obtain siting authority from KCC Engineer and design Acquire right-of-way Construct

Slide 35: Financial Overview/Profile
32 Financial Overview/Profile

Slide 36: Capitalization and Liquidity
33 Capitalization and Liquidity Target capital structure Solid credit & liquidity position Investment grade ratings $730 million revolver Minimal refunding obligations No maturities until 2014 Dec 31, 2009 (millions) Long-term, net $2,492 Preferred Common 2,245 Total Capitalization $4,758 Debt 52% E

Slide 37: Dividend
34 $0.92 $1.00 $1.08 $1.16 $1.20 $1.24 $0.75 $0.85 $0.95 $1.05 $1.15 $1.25 $1.35 2005 2006 2007 2008 2009 2010 Dividend Long-standing dividend payout target of 60%-75% of earnings Dividend payout 69%-75% based on 2010 guidance Indicated annual rate

Slide 38: Westar Remains Well-Positioned for Targeted Shareholder Base
35 Westar Remains Well-Positioned for Targeted Shareholder Base Stable, experienced utility management team Thoughtful, flexible approach to capital planning and financing Maintaining control of our business Diverse customer base and stable service territory Focus on containing risks and maintaining

Slide 39: Rates & Regulation
Rates & Regulation 36

Slide 40: Regulatory Approach
37 Regulatory Approach A sound regulatory and energy policy platform Stable, more predictable Collaborative, constructive approach Timely Benefits for customers: Minimize rate volatility Time Traditional GRC Riders coupled with GRC Ultimately, lower rates

Slide 41: Methods of Cost Recovery for Westar
38 Methods of Cost Recovery for Westar Smoothes period expenses for extraordinary storm restoration costs Traditionally deferred accounting treatment as rate base Extraordinary storm damages 6. Smoothes period expenses in excess of amount in base rates Deferred as a regulatory asset for subsequent r

Slide 42: Retail Energy Cost Adjustment (RECA)
39 Retail Energy Cost Adjustment (RECA) Provides timely price adjustments for fuel and purchased power costs Retail rates based on forecast of fuel and purchased power costs and retail sales Set quarterly Difference between forecast and actual is accrued/deferred Quarterly approach produces more sta

Slide 43: Environmental Cost Recovery Rider
40 Environmental Cost Recovery Rider Mechanics ECRR adjusts retail rates annually to reflect capital costs for emission controls Investment at December 31 begins recovery in rates following June Eliminates need to file a rate case to capture rate base additions Return of and on capital that is in se

Slide 44: Illustrative ECRR Mechanics
41 Illustrative ECRR Mechanics (1) Illustration reflects only the projects publicly announced and assumes one-half of annual investment in service at year end (2) Illustration uses 12% pretax return and 4% depreciation recovery (3) Annual ECRR Tariff is effective June 1; assume Jan-May at prior year

Slide 45: Transmission Cost Recovery
42 Transmission Cost Recovery FERC formula transmission rate Changes in cost of service reflected in annual update of FERC tariff Update posted each October using projected test year Forecasted capital expenditures Forecasted O&M Tariff is based on year-end consolidated capital structure FERC transm

Slide 46: Transmission Formula Rate Mechanics
43 Transmission Formula Rate Mechanics Fixed formula with changing inputs Updated annually using Form 1 data Established protocols for updates Uses projected test year Rate base (based on 13 mo. Avg.) O&M, depreciation and taxes Cost of debt Annual true-up incorporated in subsequent year’s formula i

Slide 47: Statutes for Predetermination and CWIP
44 Statutes for Predetermination and CWIP Predetermination Utilities can obtain order establishing ratemaking principles that will apply over the life of the asset Construction Work in Progress (CWIP) Utilities can include CWIP in rate cases

Slide 48: Pension Tracker
45 Pension Tracker Defer on balance sheet differences between funding of GAAP pension/OPEB expense and pension/OPEB currently authorized in rates Maintain minimum funding level equal to GAAP pension/OPEB expense Recover deferrals over period up to 5 years at time of future rate case

Slide 49: Energy Efficiency Initiatives
46 Energy Efficiency Initiatives Selected by DOE to begin negotiations for smart grid implementation in Lawrence, Kansas Installation of about 48,000 “smart” meters Total project cost of $40 million Eligible for 50% match To be implemented over 2 to 3 years Regulatory orders may allow deferral of co

Slide 50: Kansas' Comprehensive Energy Bill Passed
47 Kansas’ Comprehensive Energy Bill Passed Renewable Portfolio Standard established Installed capability standard in lieu of energy standard 10% of peak load by 2011, 15% by 2016 and 20% after 2020 Implies additional 150 to 200 MW for Westar If generated in Kansas, treated at 110% of requirement Li

Slide 51: Capital Structure for Ratemaking (Per Recent Orders)
48 Capital Structure for Ratemaking (Per Recent Orders) 12.00% 8.50% 100.00% 8.77 5.29 10.40 50.83 Common .04 .02 4.55 0.51 Preferred 3.19% 3.19% 6.55% 48.66% Long-term debt Pre-tax Weighted Cost of Capital Weighted Cost of Capital Cost of Capital Capitalization Ratio 11.76% 8.18% 100.00% 8.99 5.43

Slide 52: Background
49 Background

Slide 53: Westar Energy Legal Structure
50 Westar Energy Legal Structure Kansas Gas and Electric Company Consolidated capital structure is used for ratemaking (Rate re g ulated utility) (Rate regulated utility) Westar Energy, Inc. Parent Subsidiary Combined company does business under the name “Westar Energy”

Slide 54: Management and Organization Structure
51 Management and Organization Structure Executive Management President & CEO, Bill Moore EVP & COO, Doug Sterbenz EVP & CFO, Mark Ruelle EVP, Public Affairs / Consumer Services, Jim Ludwig Officers average 23+ years utility experience, largely with Westar Independent Board of Directors Non-executiv

Slide 55: Wholesale Sales
52 Wholesale Sales Market-based sales (asset-based margins) Opportunistic sales using as available capacity Real time up to 1 year Margins reflected as credit to RECA Tariff-based sales Long-term agreements Cost-based tariffs Primarily with coops, municipals and participation agreements with other u

Slide 56: Westar's Plants
53 Westar’s Plants Westar Energy 2008 Results NERC 5-Year Average Plant Performance 83.4% 82.2% 82.7% 89.3% 87.0% 90.1% 73.7% 73.7% 0% 20% 40% 60% 80% 100% Coal Capacity Factor Wolf Creek Capacity Factor Coal Availability Factor Wolf Creek Availability Factor W estar's MW Operator Years Installed Pu

Slide 57: Coal Supply
54 Westar-operated plant supply (80%) JEC supply under contract through 2020 (10+ million tons/year) 70% has no market openers 30% reopened on price every 5 years Next re-pricing will occur in 2013 All volumes have cost escalators Rail contract through 2013 LEC/TEC supply under contract until 2010 (

Slide 58: Wolf Creek Generating Station
55 Wolf Creek Generating Station Commercial operation in September 1985 1166 MW Westinghouse PWR Co-owners Westar Energy – 47% (548 MW) Great Plains Energy – 47% KEPCo – 6% Operated by Wolf Creek Nuclear Operating Corporation Separate and dedicated operating company Owned and governed by plant’s co-

Slide 59: Future Wind Resources
56 Future Wind Resources Kansas statute requires additional - MW by end of 2011 Currently in discussions with short list of providers Expect to firm up plans by year end Can include either PPAs, ownership or both
Source: SEC EDGAR · 8-K filed Mar 3, 2010
More decks from Westar Energy Inc
Merger or Acquisition (January 2018)27 slides · Jan 10, 2018
Q3 2017 Earnings Presentation19 slides · Nov 3, 2017
Q2 2017 Earnings Presentation20 slides · Aug 10, 2017
Q3 2016 Earnings Presentation6 slides · Nov 1, 2016
Merger or Acquisition (September 2016)29 slides · Sep 8, 2016
Merger or Acquisition (August 2016)59 slides · Aug 22, 2016