Sunrise Energy Metals Limited · ASX:SRL
Sunrise Energy Metals — Corporate Update (June 2023)
21 slides from Sunrise Energy Metals's corporate update, Jun 7, 2023
Slide 1: Sunrise Project Community Consultative Committee
Sunrise Project Community Consultative Committee 7 June 2023
Slide 2: Contents
Contents 1 Sunrise Regional Update – Water Bore Installation, Mineral Exploration & Test Work 2 Community Update 3 Environmental Management Update 4 Environmental Approvals Update 5 CCC Member Questions 2 Powering innovation | June 23
Slide 3: Sunrise Regional Update – Water Bore Installation, Mineral Exploration & Test Work
01 Sunrise Regional Update – Water Bore Installation, Mineral Exploration & Test Work 3 Powering innovation | June 23
Slide 4: Water Bore Drilling – Sunrise Project Borefield
Water Bore Drilling – Sunrise Project Borefield › Sunrise commenced construction of the remaining four approved water bores in April 2023 due to requirements of the Water Supply Works Approval › Watson Drilling (Deniliquin) successful tenderer › DPE notification of staging of the development › Consu
Slide 5: Powering innovation | June 23
5 Powering innovation | June 23
Slide 6: Water Bore Drilling – Sunrise Project Borefield
Water Bore Drilling – Sunrise Project Borefield 6 Powering innovation | June 23
Slide 7: Mineral Exploration in the Region – Limestone
Mineral Exploration in the Region – Limestone › Scout reverse circulation (RC) drilling programs have been completed at our Boona Gap & Ezy Lime tenements over the first half of 2023. › 25 RC Holes were drilled at the Ezy Lime tenement and 10 RC holes at the Boona Gap tenement › These programs showe
Slide 8: Test Work & Technology Development
Test Work & Technology Development › Process test work completed to optimize the residence time in the U-Column desorption process for nickel and cobalt. This will be used as an input during the detailed design of the U-Column and downstream Ni & Co refinery › Battery recycling test work completed a
Slide 9: Community Update
02 Community Update 9 Powering innovation | June 23
Slide 10: Community – Working Together
Community – Working Together › Community Events – Supported the Trundle Back in Time event on 26th March and sponsored the sheaf toss › Preparing to support the 2023 local agricultural shows › Attended the NSW Minerals Council careers night in Orange on 31st May to promote the mining industry as a c
Slide 11: Keeping People Informed
Keeping People Informed › Community Communication – Parkes and Condobolin shopfronts are open, first and third Tuesday/Thursday of the month › Sunrise Energy Metals website – Complaints register published monthly, with zero complaints YTD – Community Complaints line listed on our website – 1800 952
Slide 12: Environmental Management Update
03 Environmental Management Update 12 Powering innovation | June 23
Slide 13: Environmental Monitoring
Environmental Monitoring › Continuing environmental monitoring: – Air Quality – Surface Water – Groundwater (December/January and May) – Meteorological › Depositional dust and Particulate Matter (PM10 and PM2.5) › Surface water monitoring events – November 2022 › Groundwater monitoring – Next round
Slide 14: Environmental Approvals Update
04 Environmental Approvals Update 14 Powering innovation | June 23
Slide 15: Government Reporting
Government Reporting › Annual project reporting recently completed – Annual Return to the EPA – 2022 Annual Review to DPE 15 Powering innovation | June 23
Slide 16: Project Execution Plan Modification
Project Execution Plan Modification › Updated Environmental Management Plans (EMPs) are on the Sunrise website – Air Quality and Greenhouse Gas Management Plan* – Blast Management Plan – Biodiversity Management Plan and Revegetation Strategy – Environmental Management Strategy – Heritage Management
Slide 17: Non-Urban Water Metering Requirements
Non-Urban Water Metering Requirements › New water metering requirements came into force on 1 June 2023 › Application was made to DPE Water to make one groundwater bore inactive – i.e. the pump is no longer capable of taking water › New groundwater bores will also be made inactive › One bore being fi
Slide 18: Critical Asset Approvals
Critical Asset Approvals › 132kV Electrical Transmission Line (ETL) – Conditional Offer of $10M Grant Funding from NSW Critical Minerals and High-Tech Metals Activation Fund – Connection agreement with Network Service Providers progressing including initial line design completed with Essential Energ
Slide 19: Critical Asset Approvals
Critical Asset Approvals › Raw Water Pipeline and Borefield – Short term licence granted by Crown Lands for drilling of pilot holes – Licence granted by Crown Lands for installation of production bore on Crown Land – Licence and easement application over Crown Land progressing › Oversize Transport R
Slide 20: CCC Member Questions
05 CCC Member Questions 20 Powering innovation | June 23
Slide 21: Thank you
Thank you 0: sunrise energy metals