  1. Slide 1: Adequacy in Belgium winter 2014-15

    Adequacy in Belgium winter 2014-15 Users’ Group 25 September 2014

  2. Slide 2: Outlook for the coming winter(s)

    Outlook for the coming winter(s)

  3. Slide 3: Just before winter ≈1/3rd of our production capacity is unavailable

    Just before winter ≈1/3rd of our production capacity is unavailable!!! Installed capacity of centralised fossil fuel & nuclear plants 14000 12000 Loss of +/- 2000 MW  winter 12-13 10000 8000 MW 6000 4000 2000 0 Winter 12-13 Winter 13-14 Full nuke No D3/T2 No D4 No D4 + Strat No D4/D1 + Res Strat Re

  4. Slide 4: Overview of situation per type of power plant

    Overview of situation per type of power plant Conventional Nuclear Gas # Power plants built during the 7 NU power plants for a total 4400 MW, of which several have 60s and 70s (still in service in of 5900 MW announced mothballing and/or winter 2012-2013) have been closure. • NU phase-out (by 2025) h

  5. Slide 5: Import capacity at our borders

    Import capacity at our borders • Elia’s current grid provides market players with import transmission capacity of 3500 MW. • This meets the European safety criteria in order to avoid a grid collapse and ensuing domino effect. • Electricity flows are determined by the market. Example of import of 350

  6. Slide 6: And Belgium relies on imports

    And Belgium relies on imports Under normal circumstances ELIA allows imports up to: • 3500MW (winter) and • 3000MW (summer)  > 3500 MW: accepted case by case, only after security check by experts  29 days > 3000 MW import; partly for economic reasons (e.g. 19/11/2012 max. 3864 MW) Due to Belgium's

  7. Slide 7: Loss of Load Expected

    Loss of Load Expected Scenario without winter maintenance, with 850 MW strategic reserve AND counting on 3500MW of imports! (Without DOEL3 and TIHANGE2 LOLE Average P95 7

  8. Slide 8: Measures taken in BE

    Measures taken in BE

  9. Slide 9: In order to cope with this (r)evolution measures have already been taken

    In order to cope with this (r)evolution measures have already been taken Wathelet Plan (secretary of state for energy in BE)  Strategic reserve: 850 MW (745 Generation and 100 Demand) as of 1 Nov 2014 Elia’s role: yearly determination of required volumes, organisation of the tendering, contracting

  10. Slide 10: Elia has set up the “Be.Ready” programme

    Elia has set up the “Be.Ready” programme STRATEGIC RESERVES S1 – Review needs S2 - Review (temporary) closures and construction Maximise S10 – Increase P3 – Optimise power production capacity available plant maintenance production P7 – Accelerate DSM S4 – review timing and scope of investments S8 –

  11. Slide 11: Measures taken by our government

    +Measures taken by our government Government has announced (in order to decrease the risk of curtailment) actions to reduce consumption.  Measures taken and activated by the government  It is also expected that actions will be taken by market players (BRPs) due to an important incentive (€4,500/MW

  12. Slide 12: What if this is not enough?

    What if this is not enough? If production + imports - measures to reduce consumption are not enough then the final solution = load shedding (emergency procedure) NW NE CE SW SE 12

  13. Slide 13: Many thanks for your attention!

    Many thanks for your attention! ELIA SYSTEM OPERATOR Boulevard de l'Empereur 20 1000 Brussels +32 2 546 70 11 info@ elia.be www.elia.be An Elia Group company